Finding 1240634 (2025-005)

Material Weakness Repeat Finding
Requirement
B
Questioned Costs
-
Year
2025
Accepted
2026-10-16
Audit: 415020
Organization: Housing Hope and Subsidiaries (WA)
Auditor: CLARK NUBER PS

AI Summary

  • Core Issue: There is a significant deficiency in internal controls over compliance related to allowable costs, specifically regarding the lack of manager review and approval of employee timesheets for six months.
  • Impacted Requirements: The Agency failed to meet the requirements under 2 CFR § 200.303, which mandates effective internal controls for managing federal awards.
  • Recommended Follow-Up: Strengthen monitoring processes to ensure timely and consistent manager review and approval of employee timesheets moving forward.

Finding Text

Significant deficiency in internal controls over compliance related to allowable costs. Federal Agencies: Department of Treasury Program Titles: Coronavirus State and Local Fiscal Recovery Fund Assistance Listing Numbers: 21.027 Award Numbers: HCS-23-AR-2110-048, EL-23-AR-47-048, EL-23-AR-49-353, and SLFRP0194. Project Period: November 1, 2021 - June 30, 2025 Criteria Under 2 CFR § 200.303, a nonfederal entity is required to establish, document, and maintain effective internal control over federal awards that provides reasonable assurance that the entity is managing federal awards in compliance with federal statutes, regulations, and the terms and conditions of the federal award. Condition/Context for Evaluation During the audit for the year ending June 30, 2025, it was noted that the Agency did not consistently have manager review and approval for employee timesheets during a period of six months. The employees were signing the timesheets, but the control for the manager review and approval was not followed. Cause The Agency had switched payroll systems during that time and there was an expectation that there would be a change in the review process. The updated control was determined not to be effective and the Agency switched back to manual review and approval of timesheets. However, due to employee turnover in the finance department, this switch back to the original control did not occur timely, leading to a lapse in control activities. Effect or Potential Effect The Agency did not apply their stated controls over allowable costs during a six-month period. Questioned Costs Not applicable. Repeat Finding Yes, see finding 2024-003. Recommendation We recommend that the Agency strengthen monitoring over its allowable costs to ensure manager review and approval of employee timesheets is performed consistently and timely throughout the year. Views of Responsible Officials of Auditee Management concurs with the finding and has provided the accompanying management corrective action.

Corrective Action Plan

Contact Person(s): Brianna Mariani - BriannaMariani@housinghope.org Kathryn Opina - KathrynOpina@housinghope.org Explanation and specific reasons for disagreement with the audit finding or that corrective action is not required (if applicable): N/A Corrective action planned: Beginning July 1, 2025, the Payroll Specialist began saving physically signed timesheets that document allocations to grants. Beginning August 1, 2025, allocations to grants are captured within the payroll system, ADP, along with the supervisor approval. The Payroll Specialist verifies each line on the timesheet is approved, which the system requires for the employee to receive payment. Anticipated completion date: Corrective action of signed allocation timesheets was implemented July 1, 2025. Corrective action of allocations to grants within ADP was implemented August 1, 2025.

Categories

Subrecipient Monitoring Allowable Costs / Cost Principles Significant Deficiency Matching / Level of Effort / Earmarking Internal Control / Segregation of Duties

Other Findings in this Audit

  • 1240623 2025-004
    Material Weakness Repeat
  • 1240624 2025-004
    Material Weakness Repeat
  • 1240625 2025-004
    Material Weakness Repeat
  • 1240626 2025-004
    Material Weakness Repeat
  • 1240627 2025-004
    Material Weakness Repeat
  • 1240628 2025-004
    Material Weakness Repeat
  • 1240629 2025-002
    Material Weakness Repeat
  • 1240630 2025-002
    Material Weakness Repeat
  • 1240631 2025-005
    Material Weakness Repeat
  • 1240632 2025-005
    Material Weakness Repeat
  • 1240633 2025-005
    Material Weakness Repeat
  • 1240635 2025-003
    Material Weakness Repeat
  • 1240636 2025-003
    Material Weakness Repeat
  • 1240637 2025-006
    Material Weakness Repeat
  • 1240638 2025-006
    Material Weakness Repeat
  • 1240639 2025-006
    Material Weakness Repeat

Programs in Audit

ALN Program Name Expenditures
14.228 COMMUNITY DEVELOPMENT BLOCK GRANTS/STATE'S PROGRAM AND NON-ENTITLEMENT GRANTS IN HAWAII $1.05M
21.027 CORONAVIRUS STATE AND LOCAL FISCAL RECOVERY FUNDS $1.04M
14.235 SUPPORTIVE HOUSING PROGRAM $400,000
10.420 RURAL SELF-HELP HOUSING TECHNICAL ASSISTANCE $322,020
14.247 SELF-HELP HOMEOWNERSHIP OPPORTUNITY PROGRAM $285,000
14.239 HOME INVESTMENT PARTNERSHIPS PROGRAM $198,564
14.267 CONTINUUM OF CARE PROGRAM $90,263
81.128 ENERGY EFFICIENCY AND CONSERVATION BLOCK GRANT PROGRAM (EECBG) $90,000
10.561 STATE ADMINISTRATIVE MATCHING GRANTS FOR THE SUPPLEMENTAL NUTRITION ASSISTANCE PROGRAM $81,762
10.558 CHILD AND ADULT CARE FOOD PROGRAM $28,503
14.218 COMMUNITY DEVELOPMENT BLOCK GRANTS/ENTITLEMENT GRANTS $10,999
97.024 EMERGENCY FOOD AND SHELTER NATIONAL BOARD PROGRAM $7,028
14.231 EMERGENCY SOLUTIONS GRANT PROGRAM $6,696