Finding 1240597 (2023-004)

Material Weakness Repeat Finding
Requirement
I
Questioned Costs
-
Year
2023
Accepted
2026-10-16
Audit: 414996
Organization: TOWN OF ROBERSONVILLE (NC)

AI Summary

  • Core Issue: The Town failed to document that it verified vendors were not suspended or debarred before awarding contracts.
  • Impacted Requirements: This oversight violates federal procurement regulations outlined in 2 CFR 200.212 and related sections.
  • Recommended Follow-Up: Establish and maintain procedures for verifying vendor eligibility and keep records in procurement files to ensure compliance.

Finding Text

Finding 2023-004 Significant Deficiency – Suspension and Debarment Criteria: Per 2 CFR 200.212, 2 CFR 180.300, 2 CFR 200.318(h), and 48 CFR 52.209-6, the Town is required toverify that entities receiving covered contracts are not suspended, debarred, or otherwise excluded from participation in federal programs prior to award. Condition: The Town could not provide evidence that suspension and debarment verification was performed prior to contract award. The audit team independently verified the vendor's status through FAC.gov and noted no suspension or debarment concerns; however, documentation demonstrating that the Town performed this verification before awarding the contract was not available. Effect: Because the vendor was subsequently verified by the audit team as eligible, no known cost questioned were identified. However, the lack of documented verification increases the risk of contracting with an ineligible vendor and noncompliance with federal procurement requirements. Cause: Management did not maintain documentation evidencing that suspension and debarment verification procedures were performed and reviewed prior to contract execution. Recommendation: The Town should implement procedures requiring suspension and debarment verification prior to contract award and retain evidence of the verification in the procurement file to demonstrate compliance with federal requirements. Management Response: Management agrees with the finding and is implementing procedures to correct this, which is further discussed in the corrective action plan.

Corrective Action Plan

Finding 2023-004 Significant Deficiency – Suspension and Debarment Town’s Response: We agree with and understand this finding. For the projects currently underway, it was the current staff’s belief that the consulting engineer (who was responsible for handling the bid/award process) in conjunction with the Town Manager was ensuring that suspension/debarment was being prior to Town Council making award decisions. Award decisions also had additional review by the funding agency (DEQ, USDA) to ensure compliance with the grant documents. However, current staff have not been able to document that this occurred on past projects but will make it a standard part of the contract review process moving forward and ask the consulting engineer to document actions to ensure contractors have not been debarred and/or suspended prior to award decisions are made by Town Council. Contact: Linda Modlin, Finance Officer Implementation date: September 2026

Categories

Procurement, Suspension & Debarment

Other Findings in this Audit

  • 1240595 2023-004
    Material Weakness Repeat
  • 1240596 2023-004
    Material Weakness Repeat

Programs in Audit

ALN Program Name Expenditures
66.468 DRINKING WATER STATE REVOLVING FUND $389,650
21.027 CORONAVIRUS STATE AND LOCAL FISCAL RECOVERY FUNDS $35,300