Finding 1240418 (2025-004)

Material Weakness Repeat Finding
Requirement
N
Questioned Costs
-
Year
2025
Accepted
2026-10-14
Audit: 414907
Organization: Wilmington Housing Authority (NC)

AI Summary

  • Core Issue: The PHA failed to conduct timely reinspections for units that did not meet Housing Quality Standards, leading to continued housing assistance payments for non-compliant units.
  • Impacted Requirements: Annual inspections and timely corrective actions for failed inspections are mandated by HUD regulations, specifically within 30 days for non-life-threatening deficiencies.
  • Recommended Follow-Up: Establish procedures for prompt abatement of payments or tenant relocation for non-compliant units, and implement regular internal monitoring to ensure compliance with HQS requirements.

Finding Text

Finding 2025-004 Federal Agency: U.S. Department of Housing and Urban Development Federal Program Titles: Housing Voucher Cluster - Section 8 Housing Choice Vouchers, Mainstream Vouchers, and Emergency Housing Vouchers Federal Assistance Listing Numbers: 14.871, 14.879, and 14.EHV Noncompliance - N. Special Tests and Provisions – Housing Quality Standards Inspections Non Compliance Material to the Financial Statements: No Significant Deficiency in Internal Control over Compliance for Special Tests and Provisions Criteria: Housing Quality Standards Inspections. The PHA must inspect the unit leased to a family at least annually to determine if the unit meets the Housing Quality Standards ("HQS") and the PHA must conduct quality control re-inspections. The PHA must prepare a unit inspection report (24 CFR sections 982.158(d) and 982.405(b)). For units that fail inspection the PHA must correct all life threatening HQS deficiencies within 24 hours and all other deficiencies within 30 days. Condition: Based upon inspection of the Authority’s files and on discussion with management, there were units that failed inspections that did not pass reinspection within 30 days without penalty. Context: There are approximately five hundred ninety four (594) Housing Voucher Cluster units with failed inspections. Of a sample size of twenty five (25) failed inspections, one (1) unit did not pass reinspection within 30 days. Housing assistance payments were not abated and the tenant was not relocated in a timely manner. Our sample size is statistically valid. Known Questioned Costs: Below $25,000 threshold. Cause: There is a significant deficiency in internal controls over the compliance for the special tests and provisions type of compliance related to housing quality standards inspections. The Authority's oversight and supervisory review procedures are not adequately structured to detect or prevent delays in reinspection and enforcement of HQS requirements. Effect: Due to the breakdown in internal controls over HQS inspection follow-up, at least one sampled unit did not receive a timely reinspection within the required 30-day timeframe following an initial failed inspection. This resulted in continued Housing Assistance Payments being made for a unit that was not in full compliance with HQS requirements, without timely implementation of required corrective actions such as abatement or tenant relocation. Recommendation: We recommend the Authority establish procedures to ensure Housing Assistance Payments are promptly abated or tenant relocation is initiated when units fail to meet HQS requirements beyond regulatory timeframes. Periodic internal monitoring or quality control reviews should also be implemented to ensure ongoing compliance with HUD regulations and to mitigate the risk of recurring deficiencies.

Corrective Action Plan

Authority's Response and Planned Corrective Action Plan: The Authority accepts the recommendation of the auditor. The Authority will increase oversight in the Housing Voucher Cluster to ensure that established internal control policies are being followed on a timely basis. Kinteh Darboe, Chief of Financial Operations & Management, is responsible for ensuring the deficiencies have been rectified by March 31, 2026.

Categories

HUD Housing Programs

Other Findings in this Audit

  • 1240415 2025-002
    Material Weakness Repeat
  • 1240416 2025-003
    Material Weakness Repeat
  • 1240417 2025-004
    Material Weakness Repeat

Programs in Audit

ALN Program Name Expenditures
14.871 SECTION 8 HOUSING CHOICE VOUCHERS $16.05M
14.850 PUBLIC HOUSING OPERATING FUND $5.55M
14.872 PUBLIC HOUSING CAPITAL FUND $1.37M
14.228 COMMUNITY DEVELOPMENT BLOCK GRANTS/STATE'S PROGRAM AND NON-ENTITLEMENT GRANTS IN HAWAII $726,503
14.895 JOBS-PLUS PILOT INITIATIVE $299,484
14.879 MAINSTREAM VOUCHERS $179,185
14.877 PUBLIC HOUSING FAMILY SELF-SUFFICIENCY UNDER RESIDENT OPPORTUNITY AND SUPPORTIVE SERVICES $106,558
14.870 RESIDENT OPPORTUNITY AND SUPPORTIVE SERVICES - SERVICE COORDINATORS $43,716
14.241 HOUSING OPPORTUNITIES FOR PERSONS WITH AIDS $31,482