Finding 1239723 (2025-002)

Material Weakness Repeat Finding
Requirement
P
Questioned Costs
-
Year
2025
Accepted
2026-10-01
Audit: 414435
Organization: Jewish Family Services (OH)
Auditor: GBQ PARTNERS

AI Summary

  • Core Issue: The Organization's Schedule of Expenditures of Federal Awards (SEFA) omitted $157,189 in federal expenditures, leading to inaccurate financial reporting.
  • Impacted Requirements: Noncompliance with 2 CFR 200.510(b) and 2 CFR 200.518, resulting in insufficient audit coverage and increased risk of misreporting.
  • Recommended Follow-Up: Strengthen internal controls by implementing a SEFA preparation checklist, enhancing review procedures, and ensuring all federal awards are accurately identified and reported.

Finding Text

Reference Number: 2025-002 (Material Weakness - Internal Control over Financial Reporting and Noncompliance – Preparation of the Schedule of Expenditure of Federal Awards) Background: The Organization is required to prepare a Schedule of Expenditures of Federal Awards (SEFA) in accordance with 2 CFR 200.510(b), which serves as the basis for determining major programs and calculating the percentage of coverage under 2 CFR 200.518. During our audit, we identified omitted federal expenditures totaling $157,189 that primarily related to ALN 93.566. Criteria: • 2 CFR 200.510(b): The auditee must prepare a SEFA that includes total federal awards expended for each federal program. • 2 CFR 200.518(f): The auditor must obtain sufficient coverage of total federal awards expended (generally at least 40% for low-risk auditees and 20% for high-risk auditees). • 2 CFR 200.303(a): The auditee must establish and maintain effective internal control over federal awards to provide reasonable assurance of compliance, including accurate financial reporting. Condition: The Organization’s SEFA did not include $157,189 of federal expenditures. As a result, total federal expenditures were understated, and the auditor’s initial major program determination and testing did not achieve the required percentage of coverage under Uniform Guidance. Cause: Management’s controls over SEFA preparation and review were not adequately designed or implemented to ensure completeness of federal award identification and reporting. Specifically: • There was no formal reconciliation of federal expenditures to the general ledger and grant activity. • The review control did not include procedures to validate completeness of all ALNs, particularly for pass-through or less prominent programs. Effect: • The SEFA was materially misstated due to federal expenditures that were not included. • The initial major program determination resulted in insufficient audit coverage relative to total federal expenditures. • Additional audit procedures were required to achieve compliance with 2 CFR 200.518. • There is an increased risk that other federal programs or compliance requirements could be improperly reported or tested. Questioned Costs: None. Recommendation: We recommend that management strengthen internal controls over SEFA preparation and review by: • Implementing a formal SEFA preparation checklist that includes reconciliation of total federal expenditures to the general ledger and grant records. • Establishing a control to identify all federal awards by ALN, including pass-through funding, prior to SEFA finalization. • Enhancing management review procedures to include verification of completeness and accuracy, with documented evidence of review. • Coordinating with program personnel to ensure all sources of federal funding are captured. Views of Responsible Officials: Management acknowledges the omission of federal expenditures from the SEFA and agrees with the finding. Corrective actions will include implementing enhanced reconciliation and review controls to ensure completeness of the SEFA in future reporting periods.

Corrective Action Plan

Finding Number: 2025-002 Condition: The Organization failed to accumulate all expenditures of federal awards into their SEFA resulting in an understatement of expenditures on their 2025 SEFA. Planned Corrective Action: Management has implemented a formal SEFA preparation checklist that includes reconciliation of total federal expenditures to the general ledger and grant records. This includes establishing a control to identify all federal awards by ALN, including pass-through funding, prior to SEFA finalization and enhanced management review procedures to include verification of completeness and accuracy. Additionally, management will coordinate with program personnel to ensure all sources of federal funding are captured. Contact Person Responsible for Corrective Action: Justin Fisher, Senior Director of Accounting Anticipated Completion Date: August 31, 2026

Categories

Reporting

Other Findings in this Audit

  • 1239722 2025-001
    Material Weakness Repeat
  • 1239724 2025-003
    Material Weakness Repeat

Programs in Audit

ALN Program Name Expenditures
19.510 U.S. REFUGEE ADMISSIONS PROGRAM $531,312
93.575 CHILD CARE AND DEVELOPMENT BLOCK GRANT $315,934
16.889 GRANTS FOR OUTREACH AND SERVICES TO UNDERSERVED POPULATIONS $143,504
93.558 TEMPORARY ASSISTANCE FOR NEEDY FAMILIES $114,753
93.048 SPECIAL PROGRAMS FOR THE AGING, TITLE IV, AND TITLE II, DISCRETIONARY PROJECTS $84,070
21.027 CORONAVIRUS STATE AND LOCAL FISCAL RECOVERY FUNDS $75,000
93.566 REFUGEE AND ENTRANT ASSISTANCE STATE/REPLACEMENT DESIGNEE ADMINISTERED PROGRAMS $68,232
93.788 OPIOID STR $30,000