Finding 1239296 (2025-001)

Material Weakness Repeat Finding
Requirement
C
Questioned Costs
-
Year
2025
Accepted
2026-09-30

AI Summary

  • Core Issue: NMMF requested federal fund advances that exceeded immediate cash needs, violating 2 CFR § 200.305.
  • Impacted Requirements: Advances must align with actual costs incurred, risking noncompliance with federal cash management rules.
  • Recommended Follow-Up: Management should calculate cash needs before draws and monitor federal cash balances and interest earned.

Finding Text

Programs: Research and Development Cluster. The condition was identified on the following awards within the cluster: Basic and Applied Scientific Research (ALN 12.300, Awards N00014-24-1-2000, N00014-22-1-2706, and N00014-22-1-2833; U.S. Department of Defense, Office of Naval Research), Biological Sciences (ALN 47.074, Award 2316379; National Science Foundation), and Gulf Coast Ecosystem Restoration Science, Observation, Monitoring, and Technology (ALN 11.451, Award NA23NOS4510310; U.S. Department of Commerce, National Oceanic and Atmospheric Administration). Criteria: 2 CFR § 200.305 requires recipients to minimize the time between receipt and disbursement of federal funds. Advances must be limited to actual, immediate cash needs. Condition: NMMF requested advances for certain federal awards that exceeded actual or near-term program cash needs. We examined all 21 federal drawdown transactions during 2025, totaling $1,235,184 across five awards; no sampling was used. Advances exceeded costs incurred on five awards, and $471,412 of federal cash remained on hand at December 31, 2025 in excess of costs incurred to date. Cause: The year ended December 31, 2025 was the first year NMMF drew federal funds in advance of costs incurred; in prior years these awards operated on a cost-reimbursement basis. Effect: Federal funds may have been held longer than permitted, increasing the risk of noncompliance with federal cash management requirements and unremitted interest on excess cash. Questioned Costs: None reported. The issue relates to timing of cash draws, not the allowability of program costs. Recommendation: Management should document a cash needs calculation before each federal draw and monitor federal cash on hand, including any interest earned on advances. Repeat Finding Status: This is not a repeat of a finding reported in the immediately preceding audit.

Corrective Action Plan

The funds in question either already have been, or will be prior to year-end, fully spent down in 2026. No further draws are/will be taken in 2026 unless the need is critical, and if that is the case we will only take that which will (based on budget) be spent over a three-month span. Additionally, we have returned to billing for the awards in question on a cost reimbursement basis in 2026. Anticipated Completion Date is December 31, 2026. Responsible Official - Mike Marchesano, CFO

Categories

Cash Management

Other Findings in this Audit

  • 1239292 2025-001
    Material Weakness Repeat
  • 1239293 2025-001
    Material Weakness Repeat
  • 1239294 2025-001
    Material Weakness Repeat
  • 1239295 2025-001
    Material Weakness Repeat

Programs in Audit

ALN Program Name Expenditures
11.451 GULF COAST ECOSYSTEM RESTORATION SCIENCE, OBSERVATION, MONITORING, AND TECHNOLOGY $276,691
47.074 BIOLOGICAL SCIENCES $88,863
11.454 UNALLIED PROJECTS $29,827
12.300 BASIC AND APPLIED SCIENTIFIC RESEARCH $14,732
11.472 UNALLIED SCIENCE PROGRAM $10,444