Finding 1239177 (2025-002)

Material Weakness Repeat Finding
Requirement
N
Questioned Costs
-
Year
2025
Accepted
2026-09-30

AI Summary

  • Core Issue: The Public Housing Authority (PHA) failed to conduct timely re-inspections of units that did not meet Housing Quality Standards (HQS), risking noncompliance with federal requirements.
  • Impacted Requirements: Annual inspections and timely correction of deficiencies are mandated; 385 units failed inspections, with 3 not re-inspected within the required 30 days.
  • Recommended Follow-Up: Implement stronger internal controls to ensure compliance with HQS inspections and timely correction of deficiencies to protect federal funding.

Finding Text

Finding 2025-002 Federal Agency: U.S. Department of Housing and Urban Development Federal Program Titles: Section 8 Housing Choice Vouchers Program Federal Assistance Listing Numbers: 14.871 Noncompliance – N. Special Tests and Provisions – Housing Quality Standards Non Compliance Material to the Financial Statements: No Significant Deficiency in Internal Control over Compliance for Special Tests and Provisions Criteria: Housing Quality Standards Inspections. The PHA must inspect the unit leased to a family at least annually to determine if the unit meets Housing Quality Standards (HQS) and the PHA must conduct quality control re-inspections. The PHA must prepare a unit inspection report (24 CFR sections 982.158(d) and 982.405(b)). These inspection reports are required to be maintained and available for examination at the time of audit. For units that fail inspection the PHA must correct all life threatening HQS deficiencies within 24 hours and all other deficiencies within 30 days. Condition: Based upon inspection of the Authority’s files and on discussion with management, there were units that failed inspections and did not pass reinspection within 30 days without penalty. Context: There are approximately three hundred eighty five (385) units with failed inspections. Of a sample size of twenty five (25) failed inspections, three (3) units did not pass reinspection within 30 days. Housing assistance payments were not abated nor was the tenant relocated. Our sample size is statistically valid. Known Questioned Costs: Amount is below threshold of $25,000. Cause: There is a significant deficiency in internal controls over the compliance for the special tests and provisions type of compliance related to HQS inspections. The Authority has not properly performed annual HQS inspections in compliance with program requirements. Effect: The Authority's failure to ensure timely correction of HQS deficiencies and enforce required abatement procedures increases the risk that federal funds were used to provide housing assistance for units that did not meet HUD Housing Quality Standards. As a result, the Authority cannot demonstrate that assisted units complied with program requirements during the period of noncompliance. Recommendation: We recommend the Authority design and implement internal control procedures that will reasonably assure compliance related to HQS inspections in accordance with the Uniform Guidance and the compliance supplement.

Corrective Action Plan

Authority Response and Planned Corrective Action: The Authority accepts the recommendation of the auditor. The Authority will increase oversight in the Section 8 Housing Choice Vouchers Program to ensure that established internal control policies are being followed on a timely basis. Jacqueline Lopez, Interim Executive Director, is responsible for implementing this corrective action by December 31, 2026.

Categories

HUD Housing Programs

Other Findings in this Audit

  • 1239176 2025-001
    Material Weakness Repeat

Programs in Audit

ALN Program Name Expenditures
14.871 SECTION 8 HOUSING CHOICE VOUCHERS $7.40M
14.850 PUBLIC AND INDIAN HOUSING $1.98M
14.872 PUBLIC HOUSING CAPITAL FUND $651,206
14.870 RESIDENT OPPORTUNITY AND SUPPORTIVE SERVICES - SERVICE COORDINATORS $103,004