Finding 1239111 (2025-002)

Material Weakness Repeat Finding
Requirement
I
Questioned Costs
-
Year
2025
Accepted
2026-09-30
Audit: 413977
Organization: City of River Falls (WI)

AI Summary

  • Core Issue: The City lacks a proper suspension and debarment policy, failing to comply with federal requirements.
  • Impacted Requirements: Non-compliance with 2 CFR Part 200, which mandates checks on contractors to ensure they are not suspended or debarred.
  • Recommended Follow-up: The City should review and update its policies to align with Uniform Guidance and ensure compliance moving forward.

Finding Text

Federal Agency: U.S. Department of Treasury Federal Program: COVID-19 Flexible Facilities Program Assistance Listing # 21.029 Federal Award Identification Number and Year: CPFFN0201-2022 Pass-Through Agency: Wisconsin Department of Administration Pass-Through Number(): FFP 24-29 Type of Finding: Material Weakness in Internal Control Over Compliance and Other Matters Criteria: The City should have a suspension and department policy that adheres to the requirements of the Uniform Guidance. 2 CFR Part 200 Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Award requires compliance with the provisions of procurement, suspension, and debarment. Non-federal entities are prohibited from contracting with or making subawards under covered transactions that are suspended or debarred. Before entering into a covered transaction, the entity must verify that the contractor is not suspended, debarred, or otherwise excluded from participating in the transaction. Condition: During our testing, it was noted the City did not have a suspension and debarment policy that adheres to the requirements of the Uniform Guidance. During Auditor testing over suspension and debarment, we noted the City did not perform a suspension and debarment check for two sample items. Questioned Costs: None Context: During our testing, it was noted that 2 out of the 3 items were not reviewed to ensure the contractor’s suspension and debarment status was documented. The sampling methodology used is not, and is not intended to be statistically valid. Cause: The condition is due to limited availability of staff and the governing board. Effect: The City could procure goods or services with federal funds that are not in accordance with requirements of the Uniform Guidance. Repeat Finding: The finding is new in the current year. Recommendation: The City should continue to evaluate its policies to ensure they are in accordance with Uniform Guidance. Views of Responsible Officials: There is no disagreement with the audit finding.

Corrective Action Plan

Suspension and Debarment Policy Deficiencies Federal Agency: U.S. Department of Treasury Federal Program: COVID-19 Flexible Facilities Program – ALN 21.029 Award Period: October 7, 2024 through October 31, 2026 Recommendation: The City should continue to evaluate its policies to ensure they are in accordance with Uniform Guidance. Explanation of disagreement with audit finding: There is no disagreement with the audit finding. Action planned in response to finding: The City continues to work to ensure procurement policies are followed. Name(s) of the contact person(s) responsible for corrective action: Josh Solinger, Finance Director Planned completion date for corrective action plan: The City will review procurement policies in accordance with the Uniform Guidance by December 31, 2026.

Categories

Procurement, Suspension & Debarment

Programs in Audit

ALN Program Name Expenditures
21.029 CORONAVIRUS CAPITAL PROJECTS FUND $1.43M
21.027 CORONAVIRUS STATE AND LOCAL FISCAL RECOVERY FUNDS $685,902
20.507 FEDERAL TRANSIT FORMULA GRANTS $154,612
20.939 SAFE STREETS AND ROADS FOR ALL $73,610
97.047 BRIC: BUILDING RESILIENT INFRASTRUCTURE AND COMMUNITIES $69,767
93.568 LOW-INCOME HOME ENERGY ASSISTANCE $31,804
10.351 RURAL BUSINESS DEVELOPMENT GRANT $12,644
16.607 BULLETPROOF VEST PARTNERSHIP PROGRAM $2,197