Finding 1239023 (2025-005)

Material Weakness Repeat Finding
Requirement
I
Questioned Costs
-
Year
2025
Accepted
2026-09-30
Audit: 413892
Auditor: EIDE BAILLY LLP

AI Summary

  • Core Issue: The Cooperative lacks effective internal controls over procurement, leading to potential noncompliance with federal requirements.
  • Impacted Requirements: Key regulations include 2 CFR 200.303(a) for internal controls, 2 CFR 200.318 for procurement policies, and 2 CFR 200.214 for vendor eligibility checks.
  • Recommended Follow-Up: Update procurement policies to meet Uniform Guidance, implement verification procedures for vendor eligibility, and ensure all contracts include necessary provisions.

Finding Text

Department of Energy, Federal Financial Assistance Listing 81.254, DE-GD0000886, 2025 Grid Infrastructure Deployment and Resilience Procurement, Suspension & Debarment Material Weakness in Internal Control over Compliance and Noncompliance Criteria: 2 CFR 200.303(a) establishes that the auditee must establish and maintain effective internal control over the federal award that provides assurance that the entity is managing the federal award in compliance with federal statutes, regulations, and the terms and conditions of the federal award. 2 CFR 200.318 maintains that recipients must have and use documented procurement policies and must conform procurement standards to sections 200.317 through 200.327. 2 CFR 200 Appendix II requires certain provisions to be included in contracts if criteria are applicable. Additionally, 2 CFR 200.214 requires recipients to restrict the subawards and contract with certain parties that are debarred, suspended, or excluded from ineligible participation in Federal assistance programs or activities. Condition: Testing of procurement activities and related controls identified the following exceptions: • The Cooperative's documented procurement policy did not include several elements required by Uniform Guidance. • One contract tested did not contain all applicable Uniform Guidance contract provisions. • In one instance involving a contract exceeding $25,000, the Cooperative did not document a review to verify that the vendor was not suspended or debarred from participation in federal programs. Cause: The Cooperative had not established procedures to periodically evaluate its procurement policy and procurement documentation for compliance with Uniform Guidance requirements, including required contract provisions, documentation of procurement decisions, and suspension and debarment verification procedures. Effect: Failure to maintain effective controls over procurement activities increases the risk of noncompliance with federal procurement requirements. As a result, the Cooperative may enter into contracts that do not contain required federal provisions, fail to adequately document procurement decisions, or engage in covered transactions with vendors that are suspended or debarred from participation in federally funded programs. Questioned Costs: None reported. Context/Sampling: Sampling was not used. Repeat Finding from Prior Year: No Recommendation: We recommend that the Cooperative update its procurement policy to incorporate all applicable Uniform Guidance requirements. Management should also establish and implement procedures to: • Verify and document suspension and debarment reviews for all applicable covered transactions. • Review contracts prior to execution to ensure all required Uniform Guidance contract provisions are included. • Maintain documentation evidencing compliance with federal procurement requirements. Views of Responsible Officials: Management agrees with the finding.

Corrective Action Plan

Federal Agency Name: Department of Energy Assistance Listing Number: 81.254 Program Name: Grid Infrastructure Deployment and Resilience Finding Summary: The Cooperative's documented procurement policy did not include several elements required by Uniform Guidance. One contract tested did not contain all applicable Uniform Guidance contract provisions. In one instance involving contracts exceeding $25,000, the Cooperative did not document a review to verify that the vendor was not suspended or debarred from participation in federal programs. Corrective Action Plan: KCEC will update its procurement procedures to incorporate applicable Uniform Guidance requirements. Debarment checks will be completed and documented for all vendors prior to contract execution while also ensuring that contracts contain attestation that the vendor affirms they are not disbarred. Contracts will be reviewed to ensure all required federal provisions are included. KCEC's Grant and Compliance accountant will strengthen its contract review process to ensure federal guidelines and language is present and included in contract verbiage by actively participating in contract negotiations between the vendor and KCEC. Responsible Individuals: Isaac Gonzales, Grant & Compliance Accountant and Cletus Stoflet, CFO Anticipated Completion Date: December 31, 2026

Categories

Procurement, Suspension & Debarment

Other Findings in this Audit

  • 1239021 2025-003
    Material Weakness Repeat
  • 1239022 2025-004
    Material Weakness Repeat

Programs in Audit

ALN Program Name Expenditures
81.254 GRID INFRASTRUCTURE DEPLOYMENT AND RESILIENCE $2.40M
10.752 RURAL ECONNECTIVITY PILOT PROGRAM $396,052
81.087 RENEWABLE ENERGY RESEARCH AND DEVELOPMENT $220,770