  • Core Issue: The reserve account is underfunded by about $20,000.
  • Impacted Requirements: The reserve account must be fully funded and maintained separately.
  • Recommended Follow-Up: Implement a process to ensure all monthly budgeted transfers are made.

Finding Text

Finding No. 2025-001 – Reserve Account Funding – Other Matter Criteria: The Project’s reserve account must be fully funded and maintained in a separate bank account. Condition: The Project maintained a separate bank account for the reserves, however the account was not fully funded. Effect: The reserve bank account is underfunded by approximately $20,000. Cause: Not all monthly budgeted transfers were made to ensure the account is fully funded. Recommendation: The Project should implement a process to ensure the reserve bank account is fully funded. Reporting Views of Responsible Officials: Management agrees with the finding, see the Corrective Action Plan.

Corrective Action Plan

The project will fund the reserve account when operating funds are available to do so.

Categories

Reporting

Other Findings in this Audit

  • 1238987 2025-001
    Material Weakness Repeat

Programs in Audit

ALN Program Name Expenditures
10.427 RURAL RENTAL ASSISTANCE PAYMENTS $95,540
10.415 RURAL RENTAL HOUSING LOANS $56,253