Finding 1238704 (2025-003)

Material Weakness Repeat Finding
Requirement
N
Questioned Costs
-
Year
2025
Accepted
2026-09-30

AI Summary

  • Core Issue: The Authority failed to conduct timely Housing Quality Standards (HQS) inspections for one unit, violating compliance requirements.
  • Impacted Requirements: The PHA must perform inspections at least biennially and prepare inspection reports as mandated by 24 CFR section 982.405(b).
  • Recommended Follow-Up: Ensure annual HQS inspections are completed on time and implement controls to maintain compliance moving forward.

Finding Text

Federal Agency: U.S. Department of Housing and Urban Development Federal Program Name: Housing Voucher Cluster Assistance Listing Number: 14.871/14.879 Federal Award Identification Number and Year: MO002VO - 2025 Award Period: January 1, 2025 – December 31, 2025 Compliance Requirement: Special Tests and Provisions – Housing Quality Standards – Annual Inspections Type of Finding: • Significant Deficiency in Internal Control over Compliance • Other Matters Criteria or specific requirement: The PHA must inspect the unit leased to a family at least biennially to determine if the unit meets Housing Quality Standards (HQS). The PHA must prepare a unit inspection report (24 CFR section 982.405(b)). Condition: The Authority was unable to demonstrate timely HQS inspections were performed on all units. Questioned costs: None identified. The Authority did not complete the annual HQS inspection within the required timeframe for 1 of the units tested. While this represents noncompliance with program requirements, we did not perform procedures to determine whether the unit failed to meet HQS. As a result, we did not determine whether HAP payments made during the period of noncompliance were unallowable. Accordingly, no questioned costs were identified. Context: Exception noted in 1 out of 60 units tested for HQS inspections. The annual HQS inspection was not completed timely. Cause: The Authority did not perform annual HQS inspections timely. Effect: The Authority is not in compliance with annual HQS inspection requirements. Repeat Finding: No. Recommendation: We recommend that the Authority completes HQS inspections on an annual basis and implements a control to ensure compliance with annual HQS inspection requirements. Views of responsible officials: There is no disagreement with the audit finding.

Corrective Action Plan

Housing Voucher Cluster - Assistance Listing No. No. 14.871 and 14.879 Recommendation: We recommend that the Authority completes HQS inspections on an annual basis and implements a control to ensure compliance with annual HQS inspection requirements. Explanation of disagreement with audit finding: There is no disagreement with the audit finding. Action taken in response to finding: HAKC has reviewed its inspection procedures and implemented enhanced controls to ensure required inspections are scheduled, completed, documented, and monitored on an annual basis. HAKC is utilizing inspection tracking reports to identify units approaching or exceeding their required inspection dates. Inspection staff and supervisors are responsible for monitoring outstanding inspections and taking corrective action when an inspection is approaching its due date or becomes delinquent. Additional controls include: • Monitoring inspection due dates through recurring inspection reports; • Supervisory review of outstanding and delinquent inspections; • Tracking of inspection scheduling and completion; • Management review of inspection reports to identify overdue inspections; • Escalation of inspection deficiencies requiring corrective action; and • Staff training regarding annual inspection requirements and applicable HCV inspection procedures. HAKC will continue to perform periodic management reviews of inspection activity to ensure annual inspection requirements are being met and to identify potential delays before they become compliance deficiencies. Name(s) of the contact person(s) responsible for corrective action: Director of HCV, Assistant Directors of HCV, HCV staff, and HCV Inspection Manager. Planned completion date for corrective action plan: 12/31/2026

Categories

Special Tests & Provisions Allowable Costs / Cost Principles HUD Housing Programs Significant Deficiency Internal Control / Segregation of Duties

Other Findings in this Audit

  • 1238696 2025-001
    Material Weakness Repeat
  • 1238697 2025-001
    Material Weakness Repeat
  • 1238698 2025-001
    Material Weakness Repeat
  • 1238699 2025-002
    Material Weakness Repeat
  • 1238700 2025-002
    Material Weakness Repeat
  • 1238701 2025-002
    Material Weakness Repeat
  • 1238702 2025-003
    Material Weakness Repeat
  • 1238703 2025-003
    Material Weakness Repeat
  • 1238705 2025-004
    Material Weakness Repeat
  • 1238706 2025-004
    Material Weakness Repeat
  • 1238707 2025-004
    Material Weakness Repeat
  • 1238708 2025-005
    Material Weakness Repeat
  • 1238709 2025-005
    Material Weakness Repeat
  • 1238710 2025-005
    Material Weakness Repeat

Programs in Audit

ALN Program Name Expenditures
14.850 PUBLIC HOUSING OPERATING FUND $7.74M
14.872 PUBLIC HOUSING CAPITAL FUND $5.79M
14.879 MAINSTREAM VOUCHERS $1.27M
14.871 SECTION 8 HOUSING CHOICE VOUCHERS $1.03M
14.896 FAMILY SELF-SUFFICIENCY PROGRAM $304,313
14.870 RESIDENT OPPORTUNITY AND SUPPORTIVE SERVICES - SERVICE COORDINATORS $171,060
14.892 CHOICE NEIGHBORHOODS PLANNING GRANTS $95,816
14.889 CHOICE NEIGHBORHOODS IMPLEMENTATION GRANTS $90,609