Finding 1238424 (2025-001)

Material Weakness Repeat Finding
Requirement
I
Questioned Costs
-
Year
2025
Accepted
2026-09-29

AI Summary

  • Core Issue: Naknek Electric Association did not follow federal procurement rules, risking contracts with suspended or debarred vendors and noncompliance with the Build America, Buy America Act.
  • Impacted Requirements: The Association failed to verify vendor eligibility, document required BABA provisions, and ensure competitive procurement for transactions over $250,000.
  • Recommended Follow-Up: Implement a formal review process for procurement that includes vendor verification, BABA compliance, and proper documentation for noncompetitive procurements.

Finding Text

Finding 2025-001 Identification of the federal program: 90.100 – Denali Commission Program Noncompliance and material weakness in internal controls over procurement, and suspension and debarment Criteria: Non-Federal entities are required to maintain and follow documented procurement procedures that are consistent with applicable federal procurement requirements. Procurement transactions must be conducted using the appropriate procurement method and provide for full and open competition unless the circumstances supporting a noncompetitive procurement are met and appropriately documented at the time of entering the procurement. Additionally, for applicable covered transactions, non-Federal entities are required to verify that contractors are not suspended, debarred, or otherwise excluded from participation in federal programs prior to entering into the transaction. Finally, the award stipulates that projects subject to the Build America, Buy America Act (BABA Act) have applicable award requirements included as part of any entered procurement contracts. Condition: During our testing of four procurement transactions charged to the federal program, we identified the following exceptions: When testing compliance with Suspension and Debarment, we noted for all four transactions tested, the Association did not perform or document verification that the applicable vendors were not suspended, debarred, or otherwise excluded from participation in federal programs prior to entering into the transactions. When testing compliance with the Build America, Buy America Act, we noted two of the four transactions tested did not have applicable procurement and contract documentation including the required BABA Act provisions. When testing compliance with Procurement, we noted one of the four transactions tested exceeded $250,000 and was not competitively procured. The Association did not retain documentation for sole source justification from the time the contract was procured. Cause: Naknek Electric Association, Inc's procurement process did not ensure that suspension and debarment verification was performed and retained, applicable BABA Act requirements were incorporated into procurement and contract documentation, and procurements requiring competition were appropriately completed or supported by documented justification for noncompetitive procurement at the time of procurement. Effect: The lack of effective processes over federally funded procurements increases the risk that Naknek Electric Association, Inc, could enter into transactions with suspended or debarred parties, procure goods or services without the required competition, or fail to comply with applicable BABA Act requirements. Questioned Costs: $321,345 Recommendations: We recommend that the Association strengthen its internal controls over federally funded procurements by implementing a formal review process to ensure applicable federal requirements are identified and complied with when contracts or purchase commitments are executed. The review should include, as applicable, verification and documentation of vendor suspension and debarment status prior to entering into the contract, identification of procurements subject to BABA Act and incorporation of applicable BABA Act requirements into procurement and contract documents, determination of the appropriate procurement method and required level of competition and documentation of the circumstances and justification supporting any allowable noncompetitive procurement. We further recommend that the Association retain documentation supporting these procedures as part of its procurement records. Views of responsible officials: Management generally concurs with this audit finding and will strengthen internal controls over federally funded procurement by developing and implementing a procurement policy that outlines applicable federal requirements and how they will be incorporated into the procurement process. As noted in the finding, federal procurement requirements were not followed for significant portions of project's major procurement. The construction project was initially undertaken without federal funding, and the federal award was incorporated midway through the project to provide adequate funding through the completion of the project. Consequently, the majority of the major procurement activities occurred before federal funding was introduced and the applicable federal procurement requirements would have applied. Management recognizes, however, that the subsequent incorporation of federal funds does not eliminate its responsibility to comply with applicable federal requirements and will implement procedures to ensure procurement activities comply with federal standards when the possibility of the use of federal funds may arise.

Corrective Action Plan

Federal Finding 2025-001 – Procurement, Suspension, and Debarment Name of Contact Person: Dianne King, CEO/GM Corrective Action: NEA will develop and implement a procurement policy and procedure. This policy/procedure will outline the required procurement actions for federal and state awards. This includes investigation of a potential vendor’s debarment/suspension status, situations where competitive procurement processes would be required and how to complete the competitive process, and receiving and retaining documentation from potential vendors to ensure compliance with any applicable federal regulations (Build America Buy America act, etc.). The policy/procedure will outline the responsible parties for each process, the conditions for any potential exceptions to the policy, and how any exceptions will be appropriately handled. Proposed Completion Date: March 31, 2027

Categories

Procurement, Suspension & Debarment

Other Findings in this Audit

  • 1238425 2025-002
    Material Weakness Repeat

Programs in Audit

ALN Program Name Expenditures
90.100 DENALI COMMISSION PROGRAM $1.44M
81.254 GRID INFRASTRUCTURE DEPLOYMENT AND RESILIENCE $688,628