AI Summary

  • Core Issue: HopeSparks lacks adequate internal controls to ensure that personnel costs charged to federal programs are properly documented and supported.
  • Impacted Requirements: Compliance with 2 CFR § 200.430 is at risk, as there are no regular monitoring procedures for personnel activity documentation.
  • Recommended Follow-Up: Establish a regular monitoring process for personnel activities and implement a timely certification system for costs charged to federal awards.

Finding Text

SIGNIFICANT DEFICIENCY U.S. Department of Health And Human Services, ALN 93.493 Congressional Directives, Grant# 1H79FG001321-01; Grant period - September 30, 2024 to September 29, 2025; Pass-through: Substance Abuse and Mental Health Services Administration; Applicable compliance component: Allowable Costs/Cost Principles Finding 2025-001 – HopeSparks did not have adequate internal controls to ensure personnel costs charged to the federal program are supported with records that reflect personnel activity in accordance with federal requirements. Criteria: 2 CFR § 200.430 require grantees to support charges to federal awards for salaries and wages with records that accurately reflect the work performed. These records must be supported by a system of internal control that provides reasonable assurance that the charges are accurate, allowable, and properly allocated, be incorporated into the official records of the recipient or sub-recipient, reasonably reflect the total activity for which the employee is compensated by the recipient or sub-recipient, encompass federally assisted and all other activities compensated by the recipient or sub-recipient, comply with the established accounting policies and procedures of the recipient or sub-recipient, and support the distribution of the employee’s salary or wages among specific activities or cost objectives. Budget estimates alone do not qualify as support for charges to federal awards, but may be used for interim purposes. If the records do not meet the standards described, personnel activity reports may be required, including prescribed certifications, or equivalent documentation supporting the records. Condition: HopeSparks had no regular monitoring procedures to ensure personnel cost charged to the federal program are supported with documentation of the work performed. As a result, certifications were obtained seven (7) months after the close-out period. Cause: HopeSparks did not implement periodic monitoring procedures to ensure payroll expenses charged to the federal award is supported as required on a timely basis. Effect or potential effect: Without monitoring internal controls to support compliance, HopeSparks risks noncompliance to the terms and conditions of the Congressional Directives grant. A grantor may take actions for noncompliance including withholding funds, disallowance of costs, suspension and debarment, terminating the award, and denial of future funding. Identification of a repeat finding: Not a repeat finding Known questioned cost amount: None Recommendation: Implement procedures for regular monitoring of personnel activities and evaluation of work performed as it relates to personnel cost charged to a federal sponsored program. Views of responsible officials and planned corrective actions: HopeSparks acknowledges the auditor's finding that certifications of personnel activity for staff whose compensation was charged in whole or in part to the federal award were not completed on a periodic basis during the grant period, as required by 2 CFR 200.430. Going forward, HopeSparks will establish a periodic, contemporaneous certification process for personnel whose compensation is charged to federal awards, with implementation details to be finalized and incorporated into HopeSparks' written policies and procedures.

Corrective Action Plan

Finding 2025-001 – Major Federal Award Programs Audit Finding, Significant Deficiency, Inadequate internal control to ensure personnel costs charged to the federal program are supported in accordance with federal requirements. HopeSparks acknowledges the auditor's finding that certifications of personnel activity for staff whose compensation was charged in whole or in part to the federal award were not completed on a periodic basis during the grant period, as required by 2 CFR 200.430. During the applicable period, personnel and grant-related costs were monitored on an ongoing basis through HopeSparks' regular weekly budget review process and were charged consistently with the approved award budget; however, the specific certification format required by federal effort-reporting standards was not completed contemporaneously. Following the finding, HopeSparks conducted a thorough review of employee activities during the grant period. This process included documenting all relevant work performed and comparing it directly to personnel costs charged to the program. Our review confirmed that each cost charged to the federal award was allowable, allocable, and adequately supported. Going forward, HopeSparks will establish a periodic, contemporaneous certification process for personnel whose compensation is charged to federal awards, with implementation details to be finalized and incorporated into HopeSparks' written policies and procedures. HopeSparks' Chief Financial Officer, William Bowman, will oversee the development and execution of this process, and the President and CEO, Joseph Le Roy, will be responsible for ensuring it is carried out. If you have any questions or require additional information, please feel free to contact him at 253-565-4484 or jleroy@hopesparks.org.

Categories

Allowable Costs / Cost Principles Procurement, Suspension & Debarment Subrecipient Monitoring

Programs in Audit

ALN Program Name Expenditures
93.493 CONGRESSIONAL DIRECTIVES $1.46M
84.181 SPECIAL EDUCATION-GRANTS FOR INFANTS AND FAMILIES $188,031