Finding 1237687 (2024-004)

Material Weakness Repeat Finding
Requirement
P
Questioned Costs
-
Year
2024
Accepted
2026-09-28

AI Summary

  • Core Issue: The Medical Center lacks a proper internal control system for preparing the Schedule of Expenditures of Federal Awards, leading to potential inaccuracies.
  • Impacted Requirements: Compliance with financial reporting standards is at risk, as the Schedule must be complete and accurate to meet federal guidelines.
  • Recommended Follow-Up: Management should enhance awareness of financial reporting requirements and strengthen internal controls related to the Schedule preparation process.

Finding Text

Department of Agriculture Federal Financial Assistance Listing #10.766 Community Facilities Loans and Grants Preparation of the Schedule of Expenditures of Federal Awards Material Weakness in Internal Control Over Compliance - Other Criteria Proper controls over financial reporting include the ability to prepare the Consolidated Schedule of Expenditures of Federal Awards (Schedule) and accompanying notes to the Schedule. Condition The Medical Center does not have an internal control system designed to provide for a complete and accurate schedule of expenditures of federal awards being audited. We were requested to draft the Schedule. Cause Auditor assistance with preparation of the Schedule is not unusual, as the Schedule has unique and specialized requirements and preparation is only required when the Medical Center meets a specified threshold of federal expenditures. Effect There is a reasonable possibility that the Medical Center would not be able to draft a Schedule that is correct without assistance of the auditors. Questioned Costs None reported. Context Sampling was not used. Repeat Finding from Prior Years Yes Recommendation While we recognize that this condition is not unusual for an organization with limited staffing, we recommend management be aware of the financial reporting requirements relating to the Medical Center’s Consolidated Schedule of Expenditures of Federal Awards and internal controls that impact financial reporting. Views of Responsible Officials Management agrees with the finding.

Corrective Action Plan

Federal Agency Name Department of Agriculture Federal Assistance Listing #10.766 Program Name Community Facilities Loan and Grants Cluster Finding Summary Eide Bailly assisted in the preparation of our draft consolidated schedule of expenditures and federal awards and accompanying notes to the consolidated schedule of expenditures and federal awards. Corrective Action Plan It is not cost effective to have an internal control system designed to provide for a complete and accurate schedule of expenditures and federal awards. We requested that our auditors, Eide Bailly LLP, assist in the preparation of the schedule of expenditures. We have designated a member of management to review the drafted schedule of expenditures. Responsible Individuals Judy Monson, CFO; Nikki Lindsey, CEO Anticipated Completion Date Ongoing

Categories

Reporting Material Weakness Matching / Level of Effort / Earmarking

Other Findings in this Audit

  • 1237688 2024-005
    Material Weakness Repeat

Programs in Audit

ALN Program Name Expenditures
10.766 COMMUNITY FACILITIES LOANS AND GRANTS $22.76M
10.766 COVID-19 COMMUNITY FACILITIES LOANS AND GRANTS $400,000
93.301 COVID-19 SMALL RURAL HOSPITAL IMPROVEMENT GRANT PROGRAM $10,986