Finding 1228107 (2024-003)

Material Weakness Repeat Finding
Requirement
L
Questioned Costs
-
Year
2024
Accepted
2026-08-27
Audit: 409939
Organization: Gfh Continental Homes LLC (ND)
Auditor: BRADY MARTZ PLLC

AI Summary

  • Core Issue: The Project failed to file audited financial statements on time, missing both the nine-month and 90-day deadlines.
  • Impacted Requirements: Non-compliance with Uniform Guidance and HUD regulations regarding timely financial reporting.
  • Recommended Follow-Up: Review and strengthen internal controls to ensure future compliance with reporting deadlines.

Finding Text

Material Weakness – Reporting The Uniform Guidance requires that all entities that expend in excess of $750,000 to file audited financial statements and Data Collection Form within 9 months of year-end. (2 CFR Section 200.512). Entities are required to submit timely GAAP-based audited financial information to HUD’s Financial Assessment Subsystem within 90 days of year end. (24 CFR Section 5.801(c)(2) and HUD Handbook 4065.1 REV-1, paragraph 2-1 (D)(1)(b)). Condition The Project’s December 31, 2024 audited financial statements were not filed with the Federal Audit Clearinghouse within nine months of year-end. The audited financial statements were not reported to HUD’s Financial Assessment Subsystem within 90 days of year end. Cause Turnover in staffing and lack of oversight led to information not being ready for audit in a timely manner. Questioned Costs Not Applicable. Context We reviewed all report submissions for compliance and internal controls. Effect The Project could have had federal funding delayed or reduced. Repeat Finding This is not a repeat finding. Recommendation We recommend the Project review its internal control policies and procedures to ensure timely reporting. Response The Project agrees with the finding and will implement controls to ensure timely reporting for future submissions.

Corrective Action Plan

Contact Person – Matt Bakke, Executive Director Corrective Action Plan – The Project will review its policies and procedures over monthly reconciliations. Completion Date – 12/31/26

Categories

HUD Housing Programs Internal Control / Segregation of Duties Material Weakness Reporting

Other Findings in this Audit

  • 1228108 2024-004
    Material Weakness Repeat
  • 1228109 2024-005
    Material Weakness Repeat

Programs in Audit

ALN Program Name Expenditures
14.155 MORTGAGE INSURANCE FOR THE PURCHASE OR REFINANCING OF EXISTING MULTIFAMILY HOUSING PROJECTS $512,130