Finding 1223023 (2024-005)

Material Weakness Repeat Finding
Requirement
I
Questioned Costs
-
Year
2024
Accepted
2026-07-07

AI Summary

  • Core Issue: The auditee failed to perform and document required suspension and debarment checks for vendors in the American Rescue Plan program.
  • Impacted Requirements: Compliance with federal procurement rules, specifically verifying that contractors are not suspended or debarred from federal business.
  • Recommended Follow-Up: Implement a formal process to ensure suspension and debarment checks are conducted and documented for all procurement transactions.

Finding Text

Finding No: 2024-005 Type: Compliance: Procurement, Suspension, and Debarment Major Program Affected: Agency: U.S. Department of Agriculture Program Name: American Rescue Plan Technical Assistance Investment Program Assistance Listing No.: 10.234 Award No.: 2023-70417-39226 Compliance Requirement: Procurement and Suspension and Debarment I Condition: During our testing of procurement transactions charged to ALN 10.234, we noted that the auditee did not perform or document required suspension and debarment procedures for vendors selected under this program. For the items tested, there was no evidence that the auditee (1) checked the System for Award Management (SAM.gov), or (2) obtained certifications from vendors. As result, the auditee did not demonstrate compliance with federal requirements designed to prevent awards to suspended or debarred parties. Criteria: Federal procurement requirements for this program require the auditee to verify that contractors and certain other parties are not suspended or debarred from doing business with the federal government, generally by checking SAM.gov, obtaining a vendor certification, or including a suspension and debarment clause in the contract. These procedures are intended to ensure that federal funds are not expended with ineligible parties. Amount: Not applicable Cause: Management did not implement a formal process or control to perform and document suspension and debarment checks as part of the procurement process for federally funded purchases. Effect or Potential Effect: Because suspension and debarment procedures were not performed or documented, there is a risk that federal funds could be, or could have been, expended with vendors who are suspended or debarred, which could result in questioned costs and potential repayment obligations, as well as increased scrutiny of the auditee’s procurement practices. Repeat Audit Finding: No

Corrective Action Plan

Planned Corrective Action: We will add an updated section about suspension and debarment checks via SAM.gov to be included as part of the Procurement Authorization Form that is submitted to the Board of Trustees for approval for all vendors with contracts that exceed $50,000 annually. Contact Name and Title Responsible for Corrective Action Kwabena Sika, Founding Director Status: Completed

Categories

Procurement, Suspension & Debarment

Other Findings in this Audit

  • 1223019 2024-001
    Material Weakness Repeat
  • 1223020 2024-002
    Material Weakness Repeat
  • 1223021 2024-003
    Material Weakness Repeat
  • 1223022 2024-004
    Material Weakness Repeat

Programs in Audit

ALN Program Name Expenditures
10.234 AMERICAN RESCUE PLAN TECHNICAL ASSISTANCE INVESTMENT PROGRAM $712,373
10.328 FOOD SAFETY OUTREACH PROGRAM $124,014