Finding 1221765 (2025-001)

Material Weakness Repeat Finding
Requirement
N
Questioned Costs
-
Year
2025
Accepted
2026-06-30

AI Summary

  • Core Issue: The Project failed to provide the required utility allowance analysis, making it impossible to verify the accuracy of the current utility allowance.
  • Impacted Requirements: Compliance with HUD regulations regarding annual reviews and documentation of utility allowances is not being met.
  • Recommended Follow-Up: Ensure procedures are in place for regular utility allowance reviews and maintain all supporting documents to meet HUD record-keeping standards by September 30, 2026.

Finding Text

FINDING No. 2025-001:Section 202 – Supportive Housing for the Elderly, ALN 14.157 Finding Resolution Status: Unresolved. Information on Universe Population Size: Utility costs. Sample Size Information: Annual utility allowance analysis. Identification of Repeat Finding and Finding Reference Number: No. Criteria: HUD regulations require the owner to submit an analysis of any utility allowances with supporting documentation, make an annual review of tenant utility allowances to determine their reasonableness, and adjust the allowances, when appropriate. Statement of Condition: The Project was unable to provide the utility allowance analysis performed supporting the current utility allowance amount. Cause: The Project was not able to locate the utility allowance analysis performed. Effect or Potential Effect: Unable to verify the accuracy and reasonableness of the utility allowance amount. Auditor Non-Compliance Code: R – Section 8 Program Administration Reporting Views of Responsible Officials: The Project agrees with the finding and the auditor’s recommendations will be adopted. Recommendation: The Project should implement procedures for compliance with all HUD regulations and ensure that all supporting documents are appropriately retained. Response Indicator: Agree. Completion Date: 9/30/2026 Response:Management has implemented procedures to ensure compliance with HUD requirements related to utility allowances and document retention. The Project will perform and document an annual utility allowance review and analysis in accordance with HUD regulations. Supporting documentation used in the analysis, including utility rate information and calculation worksheets, will be maintained in the Project's compliance files and retained in accordance with HUD record-retention requirements. Management has also established procedures to ensure that all compliance-related documentation is properly organized, reviewed, and retained to support future audits and monitoring reviews. Responsibility for maintaining the utility allowance analysis and related supporting documentation has been assigned to designated management personnel, and periodic reviews will be performed to verify that required records are complete and accessible. These corrective actions are expected to be fully implemented by September 30, 2026.

Corrective Action Plan

Oversight Agency for Audit, Senior Citizens Housing Development Corporation of Ville Platte respectfully submits the following corrective action plan for the year ended September 30, 2025. Name and address of independent public accounting firm: Bellows Associates, P.A., 5401 N University Drive, Suite 201, Coral Springs, Florida 33067 Audit period: October 1, 2024 through September 30, 2025 The finding from the September 30, 2025 schedule of findings and questioned costs is discussed below. The finding is numbered consistently with the number assigned in the schedule. SECTION III – FINDINGS AND QUESTIONED COSTS – MAJOR FEDERAL AWARD PROGRAMS AUDIT FINDING No. 2025-001:Section 202 Supportive Housing for the Elderly, ALN 14.157 Recommendation: The Project should implement procedures for compliance with all HUD regulations and ensure that all supporting documents are appropriately retained. Action Taken: Management has implemented procedures to ensure compliance with HUD requirements related to utility allowances and document retention. The Project will perform and document an annual utility allowance review and analysis in accordance with HUD regulations. Supporting documentation used in the analysis, including utility rate information and calculation worksheets, will be maintained in the Project's compliance files and retained in accordance with HUD record-retention requirements. Management has also established procedures to ensure that all compliance-related documentation is properly organized, reviewed, and retained to support future audits and monitoring reviews. Responsibility for maintaining the utility allowance analysis and related supporting documentation has been assigned to designated management personnel, and periodic reviews will be performed to verify that required records are complete and accessible. These corrective actions are expected to be fully implemented by September 30, 2026. If the Oversight Agency for Audit has questions regarding this plan, please call Irene Phillips at 954-835-9200. Sincerely yours, Irene Phillips CFO

Categories

HUD Housing Programs Subrecipient Monitoring Reporting

Programs in Audit

ALN Program Name Expenditures
14.157 Section 202 Supportive Housing for the Elderly - Capital Advance $2.06M
14.157 Project Rental Assistance Contract $438,025