Finding 1220310 (2025-001)

Material Weakness Repeat Finding
Requirement
I
Questioned Costs
-
Year
2025
Accepted
2026-06-29
Audit: 405374
Organization: Houlton Water Company (ME)

AI Summary

  • Core Issue: The Company lacks a formal Procurement Policy, leading to inadequate procurement documentation.
  • Impacted Requirements: This deficiency violates federal procurement standards outlined in 2 CFR 200.200.318(a)(i).
  • Recommended Follow-Up: Implement a Procurement Policy to establish proper internal controls and ensure compliance with federal requirements.

Finding Text

SIGNIFICANT DEFICIENCY 2025-001 - Procurement Federal Program Information: US Department of Agriculture – Rural Development ALN - 10.770 - Water and Waste Facility Loans and Grants to Alleviate Health Risks on Tribal Lands Criteria: The following CFR(s) apply to this finding: 2 CFR 200.200.318(a)(i) Condition: During audit procedures, it was identified that the Company did not have a Procurement Policy. Cause: The Company does not have the necessary internal controls over compliance. This is due to the lack of knowledge of federal procurement requirements. Effect: The Company did not have the necessary method of procurement documentation for the bid process and hiring of the engineer to oversee and manage the project. Identification of Questioned Costs: None identified. Context: No approved procurement policy which resulted in one of the two contracts not have the necessary method of procurement documentation. Repeat Finding: This is not a repeat finding. Recommendation: It is recommended that the Company implement a Procurement Policy to ensure that internal control processes and procedures meet the federal procurement requirements. Views of Responsible Officials and Corrective Action Plan: Please see the Corrective Action Plan.

Corrective Action Plan

Finding 2025-001 - Procurement Policy Contact Person Responsible for Corrective Action: Gregory F. Sherman, General Manager Houlton Water Company Corrective Action To address Finding 2025-001 regardingthe absence of a formal Procurement Policy, the Houlton Water Company will implement the following corrective measures: Houlton Water Company is actively developing a comprehensive Procurement Policy to remedy the deficiency identified in the audit. Management is currently drafting the policy, ensuring it aligns with applicable regulatory requirements, industry standards, and internal operational needs. Upon completion of the internal draft, the policy will be presented to the HWC Board of Directors at the May 19, 2026 Board Meeting for review and preliminary approvaL. Should the Board request revisions, management will incorporate the necessary changes and resubmit the updated policy for final approval at the June 16, 2026 Board Meeting. Anticipated Completion Date: June 17, 2026

Categories

Procurement, Suspension & Debarment Significant Deficiency

Programs in Audit

ALN Program Name Expenditures
66.468 CAPITALIZATION GRANTS FOR DRINKING WATER STATE REVOLVING FUNDS $1.34M
10.770 WATER AND WASTE DISPOSAL LOANS AND GRANTS (SECTION 306C) $1.29M
21.027 CORONAVIRUS STATE AND LOCAL FISCAL RECOVERY FUNDS $500,473
66.202 CONGRESSIONALLY MANDATED PROJECTS $85,955