Material Weakness Repeat Finding
Requirement
L
Questioned Costs
-
Year
2025
Accepted
2026-06-27
Audit: 405188
Organization: Glens Falls Housing Authority (NY)
Auditor: BUEL CPA PC

AI Summary

  • Core Issue: The Glens Falls Housing Authority did not file its reporting package and data collection form on time due to audit delays.
  • Impacted Requirements: This violates Sec. 200.512 of the Uniform Guidance, which mandates timely submission to the Federal Audit Clearinghouse.
  • Recommended Follow-Up: Management should continue efforts to complete the March 31, 2026 audit by the December 31, 2026 deadline to regain "Low Risk Auditee" status.

Finding Text

Finding #2025-001 Prior Year Reporting Package and Data Collection Form Not Filed Timely: Statement of Condition – The Glens Falls Housing Authority’s March 31, 2024 reporting package and data collection form was not filed with the Federal Audit Clearinghouse on time due to delays in completing the audit. Criteria – Sec. 200.512 of the Uniform Guidance requires the reporting package and data collection form to be submitted to the Federal Audit Clearinghouse the earlier of 30 days after the reports are received from the auditors or nine months after the end of the audit period, unless a longer period of time was agreed to in advance by the cognizant or oversight agency for audit. Cause – Late filing of the Authority’s Unaudited REAC submission due to RAD conversion issues, and the relocation of the authority office, caused delays in the preparation of the financial statements. This was further complicated by on-going construction work related to the RAD conversion. Accordingly, the audit and corresponding reporting package filing was not completed timely. Effect – The effect is that the Housing Authority would not be considered a “Low Risk Auditee” for at least the fiscal years ending March 31, 2025 and March 31, 2026. This designation will require the auditor to audit at least 40% of the Housing Authority’s programs as Major programs until such time that the Housing Authority may be considered a “Low Risk Auditee” again. Recommendation – Although this finding technically stands on it’s own merit, it is a replacement of prior year finding #2024-001. The Authority continues to make progress in getting the March 31, 2025 audit completed, and is making every effort to have the March 31, 2026 audit completed by the December 31, 2026 deadline. We recommend that management continue their efforts to get their March 31, 2026 audit completed by the December 31, 2026 deadline.

Corrective Action Plan

CORRECTIVE ACTION: Management is in agreement with the auditor’s recommendations. We are confident that our March 31, 2026 audit will be completed by the December 31, 2026 deadline. If there are questions regarding this corrective action plan, please contact Ms. Stephanie Nasr, Executive Director at (518) 793-2583.

Categories

Reporting Internal Control / Segregation of Duties

Other Findings in this Audit

  • 1219646 2025-001
    Material Weakness Repeat

Programs in Audit

ALN Program Name Expenditures
14.871 SECTION 8 HOUSING CHOICE VOUCHERS $9.03M