Finding 1168654 (2025-004)

Material Weakness Repeat Finding
Requirement
FI
Questioned Costs
-
Year
2025
Accepted
2026-01-09
Audit: 380616
Organization: Village of Beverly Hills (MI)

AI Summary

  • Core Issue: The Village lacks written federal policies and procedures required by Uniform Guidance 2 CFR 200.
  • Impacted Requirements: This affects compliance with procurement, suspension/debarment, and equipment management regulations.
  • Recommended Follow-Up: Draft and approve necessary federal policies and procedures to ensure compliance with laws and regulations.

Finding Text

Finding 2025-004 - Significant Deficiency and Noncompliance – Written Federal Policies and Procedures Program Information: Congressionally Mandated Projects, U.S. Environmental Protection Agency, 00E04067, 2025, ALN #66.202 Criteria: The Village is required to have in place written federal policies and procedures in compliance with Uniform Guidance 2 CFR 200, which include procurement and suspension/debarment and equipment and real property management. Condition: The Village is lacking written federal policies and procedures in compliance with Uniform Guidance 2 CFR 200. Questioned Costs: None Cause and Effect: The Village has not historically received significant federal funding and therefore federal policies and procedures in compliance with Uniform Guidance 2 CFR 200 were not drafted and approved. This results in noncompliance that is considered a significant deficiency. Recommendation: We recommend that the Village draft and approve federal policies and procedures in compliance with Uniform Guidance 2 CFR 200 to ensure that they are in compliance with laws and regulations related to federal programs. Views of Responsible Officials: Management agrees with the finding. Corrective Action Plan: See attached corrective action plan.

Corrective Action Plan

2025-004 - Significant Deficiency and Noncompliance - Written Federal Policies and Procedures Condition: The Village is required to have in place written federal policies and procedures in compliance with Uniform Guidance 2 CFR 200, which include procurement and suspension/debarment and equipment and real property management. Corrective Action Plan: The Village has drafted a Federal Policy/Procedure document which will be approved by the Village Council in early 2026.

Categories

Procurement, Suspension & Debarment Equipment & Real Property Management

Other Findings in this Audit

  • 1168655 2025-005
    Material Weakness Repeat

Programs in Audit

ALN Program Name Expenditures
66.202 CONGRESSIONALLY MANDATED PROJECTS $445,608
21.027 CORONAVIRUS STATE AND LOCAL FISCAL RECOVERY FUNDS $22,500