Finding 1163216 (2025-001)

Material Weakness Repeat Finding
Requirement
N
Questioned Costs
-
Year
2025
Accepted
2025-12-01
Audit: 372708
Organization: Mayfield Manor II (FL)

AI Summary

  • Core Issue: The Project failed to submit the PRAC contract renewal on time, violating HUD regulations.
  • Impacted Requirements: Timely submission of PRAC renewals and repayment of loans from the replacement reserve account.
  • Recommended Follow-Up: Implement a monitoring system to ensure timely submissions and loan repayments, with a completion target of 03/31/2026.

Finding Text

FINDING No. 2025-001: Section 202 Supportive Housing for the Elderly, ALN 14.157 Finding Resolution Status: Unresolved. Information on Universe Population Size: PRAC contracts and assistance. Sample Size Information: Monthly PRAC assistance. Identification of Repeat Finding and Finding Reference Number: No. Criteria: As required by HUD regulations, the PRAC contract renewal must be submitted at least 120 days prior to the existing contract expiration date. Additionally, PRAC loans approved from the replacement reserve account must be returned timely, as stipulated in form HUD-9250. Statement of Condition: The Project did not complete the PRAC renewal process timely. As a result, the Project needed to secure funding through a replacement reserve loan that was not repaid upon receipt of the PRAC funds. Cause: The Project did not follow HUD regulations for a timely PRAC contract renewal resulting in the delay of funding. Effect or Potential Effect: The Project is not in compliance with HUD regulations for a timely PRAC contract renewal and repayment provision stipulated in form HUD-9250. Auditor Non-Compliance Code: R – Section 8 Program Administration. Reporting Views of Responsible Officials: The Project agrees with the finding and the auditor's recommendations will be adopted. Recommendation: Ensure the PRAC contract renewal is submitted timely and that all loans taken from the replacement reserve account are repaid upon receipt of PRAC funds, as required by HUD. Response Indicator: Agree. Completion Date: 03/31/2026 Response: New staff has been put in place to monitor and submit all renewals in a timely manner.

Corrective Action Plan

Oversight Agency for Audit, National Steelworkers Oldtimers Community Urban Development Company of Canton Two, Inc. respectfully submits the following corrective action plan for the year ended March 31, 2025. Name and address of independent public accounting firm: Bellows Associates, P.A., 5401 N University Drive, Suite 201, Coral Springs, Florida 33067. Audit period: April 1, 2024 through March 31, 2025 The finding from the March 31, 2025 schedule of findings and questioned costs is discussed below. The finding is numbered consistently with the number in the schedule. SECTION III - FINDINGS AND QUESTIONED COSTS – MAJOR FEDERAL AWARD PROGRAMS AUDIT FINDING NO. 2025-001: Section 202 Supportive Housing for the Elderly, ALN 14.157 Recommendation: Ensure the PRAC contract renewal is submitted timely and that all loans taken from the replacement reserve account are repaid upon receipt of PRAC funds, as required by HUD. Action Taken: New staff has been put in place to monitor and submit all renewals in a timely manner. If the Oversight Agency for Audit has questions regarding these plans, please call Irene Phillips at 954-835-9200. Sincerely yours, Irene Phillips CFO

Categories

HUD Housing Programs Reporting Matching / Level of Effort / Earmarking

Programs in Audit

ALN Program Name Expenditures
14.157 SUPPORTIVE HOUSING FOR THE ELDERLY - CAPITAL ADVANCE $4.27M
14.157 SUPPORTIVE HOUSING FOR THE ELDERLY - PROJECT RENTAL ASSISTANCE CONTRACT (PRAC) $143,695