  • Issue: The auditee submitted the reporting package late, missing the deadline set by federal regulations.
  • Impact: This delay could lead to noncompliance, affecting future federal funding and increasing oversight.
  • Follow-up: Management has agreed to a new compliance tracking system to ensure timely submissions, with a completion date of November 11, 2025.

Finding Text

Criteria: Per 2 CFR §200.512(a), the auditee must submit the data collection form and reporting package to the Federal Audit Clearinghouse ("FAC") within the earlier of thirty calendar days after receipt of the auditors' report, or nine months after the end of the audit period. Condition: The auditee submitted the required reporting package to the FAC past the regulatory deadline. Cause: The delay was due to a combination of staff/management turnover in the finance department and late start of the audit. Effect: Late submission may result in noncompliance with federal regulations, potentially affecting the auditee’s eligibility for future federal funding and triggering additional oversight or sanctions. Recommendation: Management should implement a compliance calendar and assign responsibility to a specific staff member to track and ensure timely submission of audit reports. Views of Responsible Officials and Planned Corrective Actions: Management concurs with the finding and has already implemented a compliance tracking system. A new policy was adopted during FY 2025 to ensure timely submissions moving forward. Contact Person: Brett Metzger, Outside Consultant Completion date: November 11, 2025

Corrective Action Plan

Management concurs with the finding and has already implemented a compliance tracking system. A new policy was adopted during FY 2025 to ensure timely submissions moving forward. Contract Person: Brett Metzger, Outside Consultant Completion Date: November 11, 2025

Categories

Eligibility Reporting Internal Control / Segregation of Duties

Other Findings in this Audit

  • 1162259 2024-001
    Material Weakness Repeat
  • 1162260 2024-001
    Material Weakness Repeat

Programs in Audit

ALN Program Name Expenditures
43.001 ECLIPSE AMBASSADORS $748,431
43.001 NASA NIGHT SKY NETWORK $534,540
47.076 ECLIPSE STARS $483,794