Finding 1161838 (2020-006)

Material Weakness Repeat Finding
Requirement
L
Questioned Costs
-
Year
2020
Accepted
2025-11-04
Audit: 371774
Organization: City of Mount Vernon (NY)

AI Summary

  • Core Issue: The City failed to submit the Data Collection Form and reporting package on time, violating federal reporting requirements.
  • Impacted Requirements: Compliance with the Uniform Guidance mandates timely submission within 30 days of receiving audit reports or nine months post-audit period.
  • Recommended Follow-Up: Ensure timely completion of year-end processes and submit required reports promptly to avoid future deficiencies.

Finding Text

Finding 2020-006 - Significant Deficiency - Untimely Submissions CFDA Number and Title: 84.287 Twenty-First Century Community Learning Centers Applicable Compliance Requirements: Reporting Criteria: Per the Uniform Guidance, states, local governments, and nonprofit organizations (“the auditee”) that annually spend $750,000 or more in federal awards must perform a Single Audit and complete Form SF-SAC (“Data Collection Form”) and submit both to the Federal Audit Clearinghouse (“FAC”). The auditee should submit the Data Collection Form and the reporting package to the FAC within the earlier of 30 days after the receipt of the auditors’ reports or nine months after the end of the audit period, unless a longer period is agreed to in advance by the cognizant or oversight agency for audit. Condition: The City did not submit the Data Collection Form and the reporting package for 2020 to the FAC by the due date in accordance with Uniform Guidance requirements. Cause: The year end closing of the general ledger and preparation for audit were not completed by management in a timely manner. Context: During our audit we noted that significant reconciliations, analyses and information were not available on a timely basis to complete the audit. Effect: The City did not comply with the Uniform Guidance reporting requirements. Recommendation: We recommend that the City submit the reports referred to above on a timely basis as required. Management’s Responses: See corrective action plan.

Corrective Action Plan

Management Response: This issue is tied to the multi-year delay in completing audits. The City has implemented stricter internal controls to ensure timely submission of the Data Collection Form and reporting package to the Federal Audit Clearinghouse immediately after each year’s audit is finalized. These improvements will be evident in the 2023 audit cycle.

Categories

Reporting Significant Deficiency

Other Findings in this Audit

  • 1161837 2020-005
    Material Weakness Repeat

Programs in Audit

ALN Program Name Expenditures
14.267 CONTINUUM OF CARE PROGRAM $1.34M
14.218 COMMUNITY DEVELOPMENT BLOCK GRANTS/ENTITLEMENT GRANTS $905,996
84.287 TWENTY-FIRST CENTURY COMMUNITY LEARNING CENTERS $779,795
93.045 SPECIAL PROGRAMS FOR THE AGING, TITLE III, PART C, NUTRITION SERVICES $257,762
14.239 HOME INVESTMENT PARTNERSHIPS PROGRAM $233,413
93.778 MEDICAL ASSISTANCE PROGRAM $127,397
16.609 PROJECT SAFE NEIGHBORHOODS $81,854
17.259 WIOA YOUTH ACTIVITIES $76,300
93.053 NUTRITION SERVICES INCENTIVE PROGRAM $69,947
93.044 SPECIAL PROGRAMS FOR THE AGING, TITLE III, PART B, GRANTS FOR SUPPORTIVE SERVICES AND SENIOR CENTERS $36,507
93.994 MATERNAL AND CHILD HEALTH SERVICES BLOCK GRANT TO THE STATES $16,528