Finding 1155314 (2024-002)

Material Weakness Repeat Finding
Requirement
B
Questioned Costs
-
Year
2024
Accepted
2025-09-25

AI Summary

  • Core Issue: The Authority failed to provide necessary documentation for 19 cost allocations in the Section 8 Housing Voucher Program.
  • Impacted Requirements: Costs must adhere to HUD's allowable costs/cost principles, which were not met due to lack of documentation.
  • Recommended Follow-Up: Implement stronger internal controls to ensure proper documentation is maintained for all cost allocations.

Finding Text

Federal Program – Section 8 Housing Choice Voucher Program AL #14.871 – Allowable Costs/Cost Principles Federal Program Section 8 Housing Choice Vouchers AL #14.871 – Material Weakness Criteria Amounts paid under the Section 8 Vouchers Program must meet allowable costs/cost principles per HUD’s annual guidance. Condition During our testing of disbursements, we noted 19 instances of the Authority not having documentation to support an allocation of costs to the vouchers program. Questioned Costs Undeterminable. Context We reviewed a random sample of twenty-four disbursements from the Section 8 Vouchers Program. Effect The allocated costs to the Section 8 Vouchers Program were undeterminable due to the fact that no documentation support for the allocation was provided. Cause The Authority experienced turnover in the Section 8 program. As a result, allocation documentations were not saved as the previous year allocations were used. Repeat Finding This is a repeat of finding 2023-002. Recommendation We recommend that the Authority implement proper internal controls to ensure the Authority’s compliance with adequate documentation. Views of Responsible Officials We are aware of the issue and have taken subsequent steps to ensure compliance with this requirement.

Corrective Action Plan

Correcting Plan CHEDA staff are aware of allowable cost proper documentations, and will implement an internal control process. 2. Explanation of Disagreement with the Audit Finding There is essentially no disagreement with the finding. 3. Official Responsible for Ensuring CAP Karie Kirschbaum – Executive Director 4. Planned Completion Date for CAP Immediately. 5. Plan to Monitor Completion of CAP The Executive Director will monitor completion of the CAP.

Categories

Allowable Costs / Cost Principles HUD Housing Programs

Other Findings in this Audit

  • 1155315 2024-003
    Material Weakness Repeat
  • 1155316 2024-004
    Material Weakness Repeat

Programs in Audit

ALN Program Name Expenditures
14.871 Section 8 Housing Choice Vouchers $1.01M
14.850 Public Housing Operating Fund $193,771
14.872 Public Housing Capital Fund $99,753