Finding Text
2024-002 Twenty-First Century Community Learning Centers – Assistance Listing No. 84.287
Significant Deficiency in Internal Control Over Compliance and Noncompliance – Appropriate Review of Expenditures Claimed
B. Allowable Costs/Cost Principles and C. Cash Management
Criteria: In accordance with 2 CFR § 200.403(e), expenses must be determined under generally accepted accounting principles (GAAP) to be considered allowable unless otherwise noted in 2 CFR 200. In accordance with 2 CFR § 200.305(b), the draws under reimbursable grants must be limited to the minimum amount needed and drawn down after expenses have incurred.
Condition and Context: During our testing of expenses charged to the federal program, we identified one transaction which the Organization prepaid for services to be rendered in 2025. The prepaid expense were charged to the SEFA in 2024 which does not match when they should be recognized as expenses under GAAP. The expenses were claimed for reimbursement prior to being incurred based on GAAP. Total questioned costs for this instance were $8,750. The population was considered the month of December as these were went the prepayments were made. The error rate for the defined population was 93.85% resulting in likely questioned costs of $14,393. Our sample was not statistically valid.
Cause and Effect: The issue appears to have resulted from a lack of adequate review procedures to ensure that expenses charged to the federal award align with recognition under GAAP. As a result, the entity claimed expenditures which may be unallowable. Claimed expenditures which may be unallowable and drawn prior to being incurred.
Recommendation: We recommend that management strengthen its review procedures over expense cutoff to ensure that expenditures are recognized on the SEFA in alignment with GAAP and are drawn down appropriately under the cost reimbursement method. Additionally, training should be provided to accounting personnel on Uniform Guidance compliance and GAAP requirements related to expense recognition.
Views of Responsible Officials and Planned Corrective Action: We agree with the recommendation and plan to have the corrective action implemented by August 2025.