Finding 1136384 (2023-004)

Material Weakness
Requirement
N
Questioned Costs
-
Year
2023
Accepted
2025-05-08

AI Summary

  • Core Issue: The Authority did not have an annual budget for the fiscal year ending September 30, 2023, violating the Budget and Fiscal Control Act.
  • Impacted Requirements: Without an approved budget, expenditures were uncontrolled, leading to potential financial mismanagement.
  • Recommended Follow-Up: The Authority should ensure an annual budget is adopted before each fiscal year to maintain compliance and improve oversight.

Finding Text

Criteria:As required by the Budget and Fiscal Control Act and the terms of the annual contributions contract with HUD, the Authority is required to have an annual budget for all enterprise funds.Condition:For the year ended September 30, 2023 the Authority was unable to locate an annual budget in the accounting records.Effect:Expenditures were not controlled as they were not budget approved.Cause:Lack of oversight by management and the Board.Recommendation:The Authority should adopt an annual budget prior to each fiscal year.Views of Responsible Officials and Planned Corrective Actions:We agree with the auditors’ comment, and the following action will be taken to improve the situation. This situation was created when the previous administration removed all records and were not made available to the auditors after several requests. KMHA has taken the following actions.A budget for FYE 9/30/25 was approved by the Board in the October 2024 meeting.

Categories

HUD Housing Programs Internal Control / Segregation of Duties

Other Findings in this Audit

  • 559939 2023-001
    Material Weakness
  • 559940 2023-002
    Material Weakness
  • 559941 2023-003
    Material Weakness
  • 559942 2023-004
    Material Weakness
  • 559943 2023-005
    Material Weakness
  • 559944 2023-006
    Material Weakness
  • 559945 2023-007
    Material Weakness
  • 1136381 2023-001
    Material Weakness
  • 1136382 2023-002
    Material Weakness
  • 1136383 2023-003
    Material Weakness
  • 1136385 2023-005
    Material Weakness
  • 1136386 2023-006
    Material Weakness
  • 1136387 2023-007
    Material Weakness

Programs in Audit

ALN Program Name Expenditures
14.872 Public Housing Capital Fund $1.59M
14.850 Public Housing Operating Fund $566,741