Finding 1131395 (2024-005)

Material Weakness
Requirement
I
Questioned Costs
$1
Year
2024
Accepted
2025-04-14
Audit: 353554
Organization: Village of Richfield (WI)
Auditor: Kerberrose Sc

AI Summary

  • Core Issue: The Village lacks formal controls to ensure contractors are not on the federal suspended and debarred list.
  • Impacted Requirements: This oversight leads to noncompliance with procurement regulations for federal funds.
  • Recommended Follow-Up: Management should create procedures to verify contractor eligibility for federally funded projects.

Finding Text

2024-005 Coronavirus State and Local Fiscal Recovery Funds – Procurement, Suspended, Debarred Federal Agency: U.S Department of Treasury Federal Program Title: Coronavirus State and Local Fiscal Recovery Funds Assistance Listing Number: 21.027 Pass-Through Agency: Direct Program Award Period: January 1, 2024 – December 31, 2024 Type of Finding: Significant Deficiency in Internal Control Over Compliance and Other Matter Condition: The Village has not implemented formal controls related to ensuring contractor vendors are not on the Federal suspended and debarred listing. Criteria: Having staff with expertise in federal award requirements review and verify eligibility of contractors ability to work on Federal contracts is an internal control intended to prevent, detect and correct potential noncompliance with Federal awards. Cause: The additional costs associated with hiring staff sufficiently experienced to prepare the Village’s single audit report, including the additional training time, outweigh the derived benefits. Effect: The procurement, suspended and debarred requirements applicable to the grant were not met. Recommendation: We recommend management and the Village Board establish procedures to verify that all vendors contracted for federally funding project are not on the suspended and debarred listing. Management’s Response: The Village is aware of the requirements and will attempt to verify all information in the future Responsible Official: James Healy – Administrator Anticipated Completion Date: The Village intends to establish a policy to work towards resolving this finding in the future.

Categories

Questioned Costs Procurement, Suspension & Debarment Eligibility Significant Deficiency

Other Findings in this Audit

  • 554953 2024-005
    Material Weakness

Programs in Audit

ALN Program Name Expenditures
21.027 Coronavirus State and Local Fiscal Recovery Funds $940,473