Finding 1101499 (2020-007)

Material Weakness Repeat Finding
Requirement
I
Questioned Costs
-
Year
2020
Accepted
2025-02-28

AI Summary

  • Core Issue: CUAHSI did not keep proper records to verify vendor compliance with federal debarment rules, leading to non-compliance with procurement policies.
  • Impacted Requirements: This affects compliance with 2 CFR sections 200.317-200.326 and related procurement regulations, risking potential repayment of funds and reputational damage.
  • Recommended Follow-Up: CUAHSI should enhance its compliance efforts and ensure a competitive procurement process is followed to meet federal requirements.

Finding Text

Federal agency name: U.S. National Science Foundation Federal program title: Geosciences, Computer and Information Science and Engineering, Office of Cyber Infrastructure & Integrative Activities AL No.: 47.050, 47.070, 47.079, 47.080 & 47.083 Federal Award Identification No. & Award Period: EAR-1849458 (06/01/2019-05/31/2024), EAR-2012893 (10/01/2020 – 08/31/2025), EAR-2028793 (05/15/2020 – 04/30/2021), OAC-1931278 (10/1/2019 – 09/30/2022), OAC-1829744 (09/01/2018 – 08/31/2023), OAC-1835592 (01/01/2009 – 12/31/2022), OAC-1835818 (10/01/2018 – 09/30/2022), OISE-1855654 (05/15/2019 – 12/31/2023), OAC-1664061 (10/01/17 – 09/30/2022) & OIA-1937099 (09/01/2020 – 08/31/2021) Pass Through Entity: Utah State University & University of Cincinnati MW2020-007 PROCUREMENT, SUSPENSION AND DEBARMENT Criteria The requirements for this compliance requirement are contained in 2 CFR sections 200.317- 200.326; 48 CFR parts 03, 15, 44, and the clauses at 48 CRF sections 52.244-2, 52.244-5, 52.203-13, 52.203-16 and 52.215-12; agency FAR supplements; 2 CFR part 180; OMB M-18-18; and the terms and conditions of the federal award. There is a requirement to verify that contractors in covered transactions or any of its vendors are not federally debarred, suspended, or excluded. A covered transaction is a nonprocurement or procurement transaction in excess of $25,000 that is subject to the prohibitions noted in 2 CFR part 180. The covered transaction may be at the primary tier, between a federal agency and a person or a lower tier between a participant in a covered transaction and another person. Condition During the completion of the audit, the auditor noted that CUAHSI failed to maintain and provide the proper records and support to document their review of vendor files for covered transactions. Such failure led to non-compliance with the procurement, suspension and debarment policies in accordance with the UG for the year ended December 31, 2020. CUAHSI did not complete the verification of its 2020 vendors until 2024. Based on our testing, no contractors in covered transactions were deemed to be federally debarred, suspended or excluded. Cause & Context CUAHSI has a policy in place to meet the procurement requirements but there was no evidence of compliance with that policy. Effect As a result of noncompliance, there could be possible repayment of funds, loss of reputation and possible suspension or debarment. Questioned Costs None Prior Year Audit Finding Yes, previously reported as MW2019-004. Recommendation It is recommended that CUAHSI strive to prioritize compliance. CUAHSI should ensure that, to the extent practicable, the use of a competitive procurement process in compliance with 2 CFR section 200/317. View of Responsible Official and Planned Corrective Action See accompanying Corrective Action Plan.

Categories

Procurement, Suspension & Debarment

Other Findings in this Audit

  • 525039 2020-002
    Material Weakness Repeat
  • 525040 2020-004
    Material Weakness Repeat
  • 525041 2020-005
    Material Weakness Repeat
  • 525042 2020-006
    Material Weakness Repeat
  • 525043 2020-007
    Material Weakness Repeat
  • 525044 2020-008
    Material Weakness Repeat
  • 525045 2020-009
    Material Weakness Repeat
  • 525046 2020-002
    Material Weakness Repeat
  • 525047 2020-004
    Material Weakness Repeat
  • 525048 2020-005
    Material Weakness Repeat
  • 525049 2020-006
    Material Weakness Repeat
  • 525050 2020-007
    Material Weakness Repeat
  • 525051 2020-008
    Material Weakness Repeat
  • 525052 2020-009
    Material Weakness Repeat
  • 525053 2020-002
    Material Weakness Repeat
  • 525054 2020-004
    Material Weakness Repeat
  • 525055 2020-005
    Material Weakness Repeat
  • 525056 2020-006
    Material Weakness Repeat
  • 525057 2020-007
    Material Weakness Repeat
  • 525058 2020-008
    Material Weakness Repeat
  • 525059 2020-009
    Material Weakness Repeat
  • 525060 2020-002
    Material Weakness Repeat
  • 525061 2020-004
    Material Weakness Repeat
  • 525062 2020-005
    Material Weakness Repeat
  • 525063 2020-006
    Material Weakness Repeat
  • 525064 2020-007
    Material Weakness Repeat
  • 525065 2020-008
    Material Weakness Repeat
  • 525066 2020-009
    Material Weakness Repeat
  • 525067 2020-002
    Material Weakness Repeat
  • 525068 2020-004
    Material Weakness Repeat
  • 525069 2020-005
    Material Weakness Repeat
  • 525070 2020-006
    Material Weakness Repeat
  • 525071 2020-007
    Material Weakness Repeat
  • 525072 2020-008
    Material Weakness Repeat
  • 525073 2020-009
    Material Weakness Repeat
  • 525074 2020-002
    Material Weakness Repeat
  • 525075 2020-004
    Material Weakness Repeat
  • 1101481 2020-002
    Material Weakness Repeat
  • 1101482 2020-004
    Material Weakness Repeat
  • 1101483 2020-005
    Material Weakness Repeat
  • 1101484 2020-006
    Material Weakness Repeat
  • 1101485 2020-007
    Material Weakness Repeat
  • 1101486 2020-008
    Material Weakness Repeat
  • 1101487 2020-009
    Material Weakness Repeat
  • 1101488 2020-002
    Material Weakness Repeat
  • 1101489 2020-004
    Material Weakness Repeat
  • 1101490 2020-005
    Material Weakness Repeat
  • 1101491 2020-006
    Material Weakness Repeat
  • 1101492 2020-007
    Material Weakness Repeat
  • 1101493 2020-008
    Material Weakness Repeat
  • 1101494 2020-009
    Material Weakness Repeat
  • 1101495 2020-002
    Material Weakness Repeat
  • 1101496 2020-004
    Material Weakness Repeat
  • 1101497 2020-005
    Material Weakness Repeat
  • 1101498 2020-006
    Material Weakness Repeat
  • 1101500 2020-008
    Material Weakness Repeat
  • 1101501 2020-009
    Material Weakness Repeat
  • 1101502 2020-002
    Material Weakness Repeat
  • 1101503 2020-004
    Material Weakness Repeat
  • 1101504 2020-005
    Material Weakness Repeat
  • 1101505 2020-006
    Material Weakness Repeat
  • 1101506 2020-007
    Material Weakness Repeat
  • 1101507 2020-008
    Material Weakness Repeat
  • 1101508 2020-009
    Material Weakness Repeat
  • 1101509 2020-002
    Material Weakness Repeat
  • 1101510 2020-004
    Material Weakness Repeat
  • 1101511 2020-005
    Material Weakness Repeat
  • 1101512 2020-006
    Material Weakness Repeat
  • 1101513 2020-007
    Material Weakness Repeat
  • 1101514 2020-008
    Material Weakness Repeat
  • 1101515 2020-009
    Material Weakness Repeat
  • 1101516 2020-002
    Material Weakness Repeat
  • 1101517 2020-004
    Material Weakness Repeat

Programs in Audit

ALN Program Name Expenditures
47.050 Geosciences $2.31M
47.080 Office of Cyberinfrastructure $127,911
47.070 Computer and Information Science and Engineering $70,695
47.083 Integrative Activities $14,635
47.079 Office of International Science and Engineering $3,306
10.652 Forestry Research $2,401