Finding 1098450 (2024-004)

Material Weakness
Requirement
I
Questioned Costs
-
Year
2024
Accepted
2025-02-05
Audit: 341278
Organization: City of Lincoln Park, Michigan (MI)

AI Summary

  • Core Issue: The City failed to comply with federal regulations regarding debarment and suspension of contractors.
  • Impacted Requirements: Nonfederal entities must verify that contractors are not debarred or suspended as per 2 CFR 200.214 and 2 CFR part 180.
  • Recommended Follow-up: Implement a process to check contractor eligibility before entering agreements and ensure compliance with federal requirements.

Finding Text

Assistance Listing Number, Federal Agency, and Program Name - ALN 21.027, Department of the Treasury, COVID-19 Coronavirus State and Local Fiscal Recovery Funds Federal Award Identification Number and Year - SLFRP 2024-2001 Pass-through Entity - Not applicable Finding Type - Material weakness and material noncompliance with laws and regulations Repeat Finding - No Criteria - Per 2 CFR 200.214, nonfederal entities are subject to the nonprocurement debarment and suspension regulations implementing Executive Orders 12549 and 12689, as well as 2 CFR part 180. The regulations in 2 CFR part 180.300 restrict making federal awards, subawards, and contracts with certain parties that are debarred, suspended, or otherwise excluded from receiving or participating in federal awards. Condition - The City could not provide evidence that it complied with the above regulations. Questioned Costs - None Identification of How Questioned Costs Were Computed - Not applicable Context - Recipients of federal awards must have procedures in place to verify that a contractor with which they plan to enter into a covered transaction is not debarred, suspended, or otherwise excluded. Cause and Effect - The City did not have a procedure in place to review contractors and entered into covered agreements without knowing whether the contractors were debarred, suspended, or otherwise excluded. Recommendation - We recommend that an additional internal process be put in place to ensure all vendors utilized with federal funds are not suspended or debarred. Views of Responsible Officials and Corrective Action Plan - The City will ensure that all future contracts awarded under this program are in compliance and will have contractors sign to verify that they are in compliance.

Categories

Procurement, Suspension & Debarment Subrecipient Monitoring

Other Findings in this Audit

  • 522008 2024-004
    Material Weakness

Programs in Audit

ALN Program Name Expenditures
21.027 Coronavirus State and Local Fiscal Recovery Funds $6.57M
14.218 Community Development Block Grants/entitlement Grants $1.15M
21.016 Equitable Sharing $6,383