Finding 1093760 (2023-006)

Material Weakness
Requirement
I
Questioned Costs
-
Year
2023
Accepted
2024-12-31

AI Summary

  • Core Issue: The Organization failed to verify that vendors were not suspended or debarred before contracts over $25,000, leading to a material weakness and noncompliance.
  • Impacted Requirements: Compliance with 2 CFR Section 180.300, which mandates verification of vendor eligibility prior to contract engagement.
  • Recommended Follow-Up: Implement internal controls to ensure verification is performed, documented, and reviewed by a supervisor before vendor contracts are finalized.

Finding Text

Assistance Listing, Federal Agency, and Program Name - 20.500, 20.507, 20.525, 20.526, U.S. Department of Transportation, Federal Transit Cluster Federal Award Identification Number and Year - All, including COVID 19 Pass through Entity - Not applicable Finding Type - Material weakness and material noncompliance with laws and regulations Repeat Finding - No Criteria - The Organization should ensure there is a process in place, prior to entering into contracts with vendors in excess of $25,000, to verify such contractors are not suspended debarred, or otherwise excluded pursuant to 2 CFR Section 180.300. Condition - There was no evidence to support that the Organization performed procedures to verify that the vendors were not suspended, debarred or otherwise excluded prior to entering into contracts in all instances. Questioned Costs - None Identification of How Questioned Costs Were Computed - Not applicable Context - Of the 60 procurements selected for testing, not all of the procurements contained evidence of either (1) a search performed on Sam.gov to determine if the vendor was suspended, debarred, or otherwise excluded; (2) a certification from the contractor attesting that they are not suspended, debarred, or otherwise excluded; or (3) adding a clause or condition to the covered transaction with that vendor. Cause and Effect - The Organization has experienced turnover that resulted in the Authority being unable to locate documentation to support compliance. Recommendation - We recommend that internal controls be put in place to ensure that the required verification is performed, documented and reviewed by a supervisor prior to entering into contracts with vendors. Views of Responsible Officials and Planned Corrective Actions - Procurement manager is assigned responsibility for verifying and documenting that vendors were not suspended, debarred or otherwise excluded through Sam.gov. This has also been added to our current document checklist and will be part of the new accounting ERP automated procurement workflow and review process.

Categories

Procurement, Suspension & Debarment

Other Findings in this Audit

  • 517313 2023-005
    Material Weakness
  • 517314 2023-005
    Material Weakness
  • 517315 2023-005
    Material Weakness
  • 517316 2023-006
    Material Weakness
  • 517317 2023-006
    Material Weakness
  • 517318 2023-006
    Material Weakness
  • 1093755 2023-005
    Material Weakness
  • 1093756 2023-005
    Material Weakness
  • 1093757 2023-005
    Material Weakness
  • 1093758 2023-006
    Material Weakness
  • 1093759 2023-006
    Material Weakness

Programs in Audit

ALN Program Name Expenditures
20.507 Federal Transit Formula Grants $6.77M
20.507 Covid-19 - Federal Transit Formula Grants $2.18M
20.526 Buses and Bus Facilities Formula, Competitive, and Low Or No Emissions Programs $1.12M
20.530 Public Transportation Innovation $21,429
20.513 Enhanced Mobility of Seniors and Individuals with Disabilities $12,264