Finding 1091601 (2024-001)

Significant Deficiency
Requirement
I
Questioned Costs
-
Year
2024
Accepted
2024-12-17

AI Summary

  • Issue: A vendor search for suspensions and debarments was not conducted before awarding a federal construction contract.
  • Requirements Impacted: This oversight violates procurement compliance related to suspension and debarment checks.
  • Follow-Up: Management should ensure vendor checks are performed using SAM.gov and retain documentation of these searches.

Finding Text

Finding No. 2024-001: Suspension and Debarment Federal Program Affected: Coronavirus State and Local Fiscal Recovery Funds AL #21.027 Compliance Requirement: Procurement, Suspension, and Debarment Questioned Costs: None Condition and Cause: A search for suspended and debarred vendors was not performed prior to awarding a construction contract with federal funding. The construction contractor was not suspended or debarred. Criteria and Effect: Not performing a search could result in the System contracting with a vendor that is suspended or debarred from doing business with the federal government, resulting in noncompliance. Repeat Finding from Prior Year: No Recommendation: Management should adhere to their written procurement policies and verify all vendors are not suspended or disbarred by searching SAM.gov, or other methods. Additionally, documentation should be retained that the search was performed. Response/Correction Action Plan: Management agrees with the above finding. See Corrective Action Plan.

Categories

Procurement, Suspension & Debarment

Other Findings in this Audit

  • 515159 2024-001
    Significant Deficiency

Programs in Audit

ALN Program Name Expenditures
21.027 Coronavirus State and Local Fiscal Recovery Funds $878,457