FINDING 2023-005
Subject: COVID-19 - Coronavirus State and Local Fiscal Recovery Funds - Reporting
Federal Agency: Department of the Treasury
Federal Program: COVID-19 - Coronavirus State and Local Fiscal Recovery Funds
Assistance Listings Number: 21.027
Federal Award Number and Year (or Other Identifying Number): FY23
Compliance Requirement: Reporting
Audit Findings: Material Weakness, Other Matters
Condition and Context
Recipients are required to submit quarterly or annually Project and Expenditure (P&E) reports to
the U.S. Department of the Treasury (Treasury). The reporting periods, as well as the respective due dates,
are based upon type of recipient and its population, as well as the recipient's allocation amount. Information
to be reported includes projects funded, expenditures, and contracts for the appropriate reporting period.
The County was classified as a metropolitan county with a population below 250,000 residents that
received an allocation of less than $10 million in COVID-19 - Coronavirus State and Local Fiscal Recovery
Funds (SLFRF) award funds. As such, the initial P&E report, covering the period from March 3, 2021 to
March 31, 2022, was required to be submitted to the Treasury by April 30, 2022. The subsequent annual
reports are to cover one calendar year and must be submitted to the Treasury by April 30 each year.
The County submitted one P&E report during the audit period; however, internal controls were not
in place to prevent, or detect and correct, errors. As a result, the following errors were noted:
The current period expenditures for 8 of 16 projects were understated by $635,748. In
addition, current period expenditures for 1 of 16 projects was overstated by $29,767.
The cumulative expenditures for 6 of 16 projects were understated by $285,748. In
addition, cumulative expenditures for 1 of 16 projects was overstated by $29,767.
The lack of internal controls and noncompliance were systemic issues throughout the audit period.
INDIANA STATE BOARD OF ACCOUNTS 23
DECATUR COUNTY
SCHEDULE OF FINDINGS AND QUESTIONED COSTS
(Continued)
Criteria
2 CFR 200.303 states in part:
"The non-Federal entity must:
(a) Establish and maintain effective internal control over the Federal award that provides
reasonable assurance that the non-Federal entity is managing the Federal award in
compliance with Federal statutes, regulations, and the terms and conditions of the Federal
award. These internal controls should be in compliance with guidance in 'Standards for
Internal Control in the Federal Government' issued by the Comptroller General of the
United States or the 'Internal Control Integrated Framework,' issued by the Committee of
Sponsoring Organizations of the Treadway Commission (COSO) . . . ."
Coronavirus State and Local Fiscal Recovery Funds Compliance and Reporting Guidance, page
10, states in part:
". . . 10. Reporting. All recipients of federal funds must complete financial, performance, and
compliance reporting as required and outlined in Part 2 of this guidance. Expenditures may be
reported on a cash or accrual basis, as long as the methodology is disclosed and consistently
applied. Reporting must be consistent with the definition of expenditures pursuant to 2 CFR
200.1. Your organization should appropriately maintain accounting records for compiling and
reporting accurate, compliant financial data, in accordance with appropriate accounting
standards and principles. . . ."
31 CFR 35.4(c) states in part: "Reporting and requests for other information. During the period of
performance, recipients shall provide to the Secretary periodic reports providing detailed accounting of the
uses of funds. . . ."
Cause
A proper system of internal controls was not designed or implemented by management of the
County to prevent and detect errors on the P&E report prior to submission.
Effect
Without the proper implementation of an effectively designed system of internal controls, including
policies and procedures that provide segregation of duties and additional oversight as needed, the internal
control system cannot be capable of effectively preventing, or detecting and correcting, material noncompliance.
As such, the County did not report current period expenditures and cumulative expenditures
properly when filing the P&E report for the period April 1, 2022 to March 31, 2023.
Noncompliance with the provisions of federal statutes, regulations, and the terms and conditions of
the federal award could result in the loss of future federal funding to the County. In addition, not meeting
the SLFRF reporting requirements increases the likelihood that the public will not have access to
transparent and accurate information regarding expenditures of federal awards.
Questioned Costs
There were no questioned costs identified.
INDIANA STATE BOARD OF ACCOUNTS
24
DECATUR COUNTY
SCHEDULE OF FINDINGS AND QUESTIONED COSTS
(Continued)
Recommendation
We recommended that management of the County strengthen its system of internal controls to
provide for a segregation of duties in the preparation and review of federal reports to ensure appropriate
reviews, approvals, and oversight are taking place. We also recommended the development of policies
and procedures to ensure the County provides the Treasury with complete and accurate information for the
P&E report.