2 CFR 200 § 200.313

Findings Citing § 200.313

Equipment.

Total Findings
40,693
Across all audits in database
Showing Page
673 of 814
50 findings per page
About this section
Section 200.313 states that equipment acquired with federal funds belongs to the recipient or subrecipient but comes with conditions, including using it for the project's intended purpose and obtaining approval before disposing of it. This section affects recipients like states and Indian Tribes, requiring them to manage and dispose of the equipment according to their laws or the specified federal guidelines.
View full section details →
FY End: 2022-06-30
North Lawrence Community Schools
Compliance Requirement: F
FINDING 2022-016 Subject: COVID-19 - Education Stabilization Fund - Equipment and Real Property Management Federal Agency: Department of Education Federal Program: COVID-19 - Education Stabilization Fund Assistance Listings Number: 84.425D Federal Award Number and Year (or Other Identifying Numbers): S425D210013 Pass-Through Entity: Indiana Department of Education Compliance Requirement: Equipment and Real Property Management Audit Findings: Material Weakness, Modified Opinion Condition and Cont...

FINDING 2022-016 Subject: COVID-19 - Education Stabilization Fund - Equipment and Real Property Management Federal Agency: Department of Education Federal Program: COVID-19 - Education Stabilization Fund Assistance Listings Number: 84.425D Federal Award Number and Year (or Other Identifying Numbers): S425D210013 Pass-Through Entity: Indiana Department of Education Compliance Requirement: Equipment and Real Property Management Audit Findings: Material Weakness, Modified Opinion Condition and Context The School Corporation purchased an All Purpose Laser Machine, totaling $14,523, with Education Stabilization Funds. This asset was not added to a detailed listing of capital assets that would include a description of the property, a serial number or other identification number, the source of funding for the property (including the federal award identification number), who holds title, the acquisition date, cost of the property, percentage of federal participation in the project costs for the federal award under which the property was acquired, the location, and the use and condition of the property. In addition, a physical inventory had not been taken in the past two years and assets were not properly safeguarded and maintained. The lack of internal controls and noncompliance were systemic issues throughout the audit period. Criteria 2 CFR 200.303 states in part: "The non-Federal entity must: (a) Establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with Federal statutes, regulations, and the terms and conditions of the Federal award. These internal controls should be in compliance with guidance in 'Standards for Internal Control in the Federal Government' issued by the Comptroller General of the United States or the 'Internal Control Integrated Framework', issued by the Committee of Sponsoring Organizations of the Treadway Commission (COSO). . . ." 2 CFR 200.313(d) states in part: "Management requirements. Procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, as a minimum, meet the following requirements: (1) Property records must be maintained that include a description of the property, a serial number or other identification number, the source of funding for the property (including the FAIN), who holds title, the acquisition date, and cost of the property, percentage of Federal participation in the project costs for the Federal award under which the property was acquired, the location, use and condition of the property, and any ultimate disposition data including the date of disposal and sale price of the property. (2) A physical inventory of the property must be taken and the results reconciled with the property records at least once every two years. (3) A control system must be developed to ensure adequate safeguards to prevent loss, damage, or theft of the property. Any loss, damage, or theft must be investigated . . ." Cause Management had not designed nor implemented a system of internal controls that would have ensured compliance with the grant agreement and the Equipment and Real Property Management compliance requirement. Effect The failure to establish an effective system of internal controls enabled material noncompliance to go undetected. Noncompliance with the grant agreement and the Equipment and Real Property Management compliance requirement could result in the loss of future federal funds to the School Corporation. Questioned Costs There were no questioned costs identified. Recommendation We recommended that the School Corporation's management establish internal controls to ensure compliance and comply with the grant agreement and the Equipment and Real Property Management compliance requirement. Views of Responsible Officials For the views of responsible officials, refer to the Corrective Action Plan that is part of this report.

FY End: 2022-06-30
South Adams Schools
Compliance Requirement: F
FINDING 2022-006 Information on the federal program: Subject: COVID-19 - Education Stabilization Fund - Equipment and Real Property Management Federal Agency: Department of Education Federal Program: COVID-19 - Education Stabilization Fund Assistance Listings Numbers: 84.425D, 84.425U Federal Award Numbers or Years (or Other Identifying Numbers): S425D200013, S425D2100013, S425U210013 Pass-Through Entity: Indiana Department of Education Compliance Requirement: Equipment and Real Property Managem...

FINDING 2022-006 Information on the federal program: Subject: COVID-19 - Education Stabilization Fund - Equipment and Real Property Management Federal Agency: Department of Education Federal Program: COVID-19 - Education Stabilization Fund Assistance Listings Numbers: 84.425D, 84.425U Federal Award Numbers or Years (or Other Identifying Numbers): S425D200013, S425D2100013, S425U210013 Pass-Through Entity: Indiana Department of Education Compliance Requirement: Equipment and Real Property Management Audit Findings: Significant Deficiency Criteria: 2 CFR 200.303 states in part: "The non-Federal entity must: (a) Establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with Federal statutes, regulations, and the terms and conditions of the Federal award. These internal controls should be in compliance with guidance in 'Standards for Internal Control in the Federal Government' issued by the Comptroller General of the United States or the 'Internal Control Integrated Framework', issued by the Committee of Sponsoring Organizations of the Treadway Commission (COSO). . . ." 2 CFR 200.313(d)(1) states: "Property records must be maintained that include a description of the property, a serial number or other identification number, the source of funding for the property (including the FAIN), who holds title, the acquisition date, and cost of the property, percentage of Federal participation in the project costs for the Federal award under which the property was acquired, the location, use and condition of the property, and any ultimate disposition data including the date of disposal and sale price of the property." Condition: An effective internal control system was not in place at the School Corporation to ensure compliance with requirements related to the grant agreement and the Equipment and Real Property Management compliance requirement. Cause: Management had not developed a system of internal control that would have ensured compliance with the grant agreement and the Equipment and Real Property Management compliance requirement. Effect: The failure to establish an effective internal control system enabled material noncompliance to go undetected. Noncompliance with the grant agreement and the Equipment and Real Property Management compliance requirement could result in the loss of future federal funds to the School Corporation. Questioned Costs: There were no questioned costs identified. Context: During the audit period, the School Corporation expended $1,685,526 in Economic Stabilization Funds (ESSER) for a building project. Although this project was included in the School Corporation?s capital asset records, it was recorded at the estimated total project cost of $6,256,000. In addition, the School Corporation did not designate the amount of the project that was paid with federal grant funds. The lack of internal controls was limited to the building project. Identification as a repeat finding: No. Recommendation: We recommended that the School Corporation's management establish a system of internal control to ensure compliance and comply with the grant agreement and the Equipment and Real Property Management compliance requirement. Views of Responsible Officials and Planned Corrective Actions: Management does not agree with the finding and has prepared a corrective action plan.

FY End: 2022-06-30
South Adams Schools
Compliance Requirement: F
FINDING 2022-006 Information on the federal program: Subject: COVID-19 - Education Stabilization Fund - Equipment and Real Property Management Federal Agency: Department of Education Federal Program: COVID-19 - Education Stabilization Fund Assistance Listings Numbers: 84.425D, 84.425U Federal Award Numbers or Years (or Other Identifying Numbers): S425D200013, S425D2100013, S425U210013 Pass-Through Entity: Indiana Department of Education Compliance Requirement: Equipment and Real Property Managem...

FINDING 2022-006 Information on the federal program: Subject: COVID-19 - Education Stabilization Fund - Equipment and Real Property Management Federal Agency: Department of Education Federal Program: COVID-19 - Education Stabilization Fund Assistance Listings Numbers: 84.425D, 84.425U Federal Award Numbers or Years (or Other Identifying Numbers): S425D200013, S425D2100013, S425U210013 Pass-Through Entity: Indiana Department of Education Compliance Requirement: Equipment and Real Property Management Audit Findings: Significant Deficiency Criteria: 2 CFR 200.303 states in part: "The non-Federal entity must: (a) Establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with Federal statutes, regulations, and the terms and conditions of the Federal award. These internal controls should be in compliance with guidance in 'Standards for Internal Control in the Federal Government' issued by the Comptroller General of the United States or the 'Internal Control Integrated Framework', issued by the Committee of Sponsoring Organizations of the Treadway Commission (COSO). . . ." 2 CFR 200.313(d)(1) states: "Property records must be maintained that include a description of the property, a serial number or other identification number, the source of funding for the property (including the FAIN), who holds title, the acquisition date, and cost of the property, percentage of Federal participation in the project costs for the Federal award under which the property was acquired, the location, use and condition of the property, and any ultimate disposition data including the date of disposal and sale price of the property." Condition: An effective internal control system was not in place at the School Corporation to ensure compliance with requirements related to the grant agreement and the Equipment and Real Property Management compliance requirement. Cause: Management had not developed a system of internal control that would have ensured compliance with the grant agreement and the Equipment and Real Property Management compliance requirement. Effect: The failure to establish an effective internal control system enabled material noncompliance to go undetected. Noncompliance with the grant agreement and the Equipment and Real Property Management compliance requirement could result in the loss of future federal funds to the School Corporation. Questioned Costs: There were no questioned costs identified. Context: During the audit period, the School Corporation expended $1,685,526 in Economic Stabilization Funds (ESSER) for a building project. Although this project was included in the School Corporation?s capital asset records, it was recorded at the estimated total project cost of $6,256,000. In addition, the School Corporation did not designate the amount of the project that was paid with federal grant funds. The lack of internal controls was limited to the building project. Identification as a repeat finding: No. Recommendation: We recommended that the School Corporation's management establish a system of internal control to ensure compliance and comply with the grant agreement and the Equipment and Real Property Management compliance requirement. Views of Responsible Officials and Planned Corrective Actions: Management does not agree with the finding and has prepared a corrective action plan.

FY End: 2022-06-30
Tattnall County Board of Education
Compliance Requirement: F
FA 2022-002 Improve Controls over Equipment Compliance Requirement: Equipment and Real Property Management Internal Control Impact: Material Weakness Compliance Impact: Material Noncompliance Federal Awarding Agency: U.S. Department of Education Pass-Through Entity: Georgia Department of Education AL Numbers and Titles: COVID-19 ? 84.425D ? Elementary and Secondary School Emergency Relief Fund COVID-19 ? 84.425U ? American Rescue Plan Elementary and Secondary School Emergenc...

FA 2022-002 Improve Controls over Equipment Compliance Requirement: Equipment and Real Property Management Internal Control Impact: Material Weakness Compliance Impact: Material Noncompliance Federal Awarding Agency: U.S. Department of Education Pass-Through Entity: Georgia Department of Education AL Numbers and Titles: COVID-19 ? 84.425D ? Elementary and Secondary School Emergency Relief Fund COVID-19 ? 84.425U ? American Rescue Plan Elementary and Secondary School Emergency Relief Fund COVID-19 ? 84.425W ? American Rescue Plan Elementary and Secondary School Emergency Relief Fund ? Homeless Children and Youth Federal Award Numbers: S425D210012 (Year: 2021), S425U210012 (Year: 2021), S425W210011 (Year: 2021) Questioned Costs: None Identified Description: The policies and procedures of the School District were insufficient to provide adequate internal controls over equipment and real property management as it relates to the Elementary and Secondary School Emergency Relief Fund program. Background: On March 27, 2020, the Coronavirus Aid, Relief, and Economic Security (CARES) Act was signed into law. The CARES Act was designed to mitigate the economic effects of the COVID-19 pandemic in a variety of ways, including providing additional funding for local educational agencies (LEAs) navigating the impact of the COVID-19 outbreak. Provisions included in Title VIII of the CARES Act created the Education Stabilization Fund to provide financial resources to educational entities to prevent, prepare for, and respond to coronavirus. The CARES Act allocated $30.75 billion, the Coronavirus Response and Relief Supplemental Appropriations Act allocated an additional $81.9 billion, and the American Rescue Plan Act added $165.1 billion in funding to the Education Stabilization Fund. Multiple Education Stabilization Fund subprograms were created and allotted funding through the various COVID-19-related legislation. Of these programs, the Elementary and Secondary School Emergency Relief (ESSER) Fund was created to address the impact that COVID-19 has had, and continues to have, on elementary and secondary schools across the nation. ESSER funding was granted to the Georgia Department of Education (GaDOE) by the U.S. Department of Education (ED). GaDOE is responsible for distributing funds to LEAs and overseeing the expenditure of funds by LEAs. ESSER funds totaling $12,214,096 were expended and reported on the Tattnall County Board of Education?s Schedule of Expenditures of Federal Awards (SEFA) for fiscal year 2022. Criteria: As a recipient of federal awards, the School District is required to establish and maintain effective internal control over federal awards that provides reasonable assurance of managing the federal awards in compliance with federal statutes, regulations, and the terms and conditions of the federal awards pursuant to Title 2 U.S. Code of Federal Regulations (CFR) Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance), Section 200.303 ? Internal Controls. Provisions included in the Uniform Guidance, Section 200.313(d)(1) state, ?Property records must be maintained that include a description of the property, a serial number or other identification number, the source of funding for the property (including the FAIN), who holds title, the acquisition date, and cost of the property, percentage of Federal participation in the project costs for the Federal award under which the property was acquired, the location, use and condition of the property, and any ultimate disposition data including the date of disposal and sale price of the property.? In addition, the Uniform Guidance, Section 200.313(d)(2) states, ?A physical inventory of the property must be taken, and the results reconciled with the property records at least once every two years.? Condition: The following deficiencies were noted when reviewing the ESSER program equipment listing and physically locating five equipment items: ? Property records did not include the following required components for all items tested: (1) A description of the property, (2) a serial number or other identification number, (3) the source of funding for the property (including the FAIN), (4) who holds title, (5) percentage of Federal participation in the project costs for the Federal award under which the property was acquired, (6) the location, and (7) use and condition of the property. ? Two pieces of equipment with costs totaling $19,387 could not be physically located based on information included in the property records, and these items reflected serial numbers that did not agree to accounting records. ? The appropriate safeguarding and maintenance of three pieces of equipment with costs totaling $105,674 could not be determined based on the information included within the property records. ? While a physical inventory was performed, the results were not effectively reconciled to the equipment listing. Cause: In discussing these deficiencies with management, they stated that there are multiple inventory lists maintained by various personnel; however, there was no consistency among the listings. Effect: The School District is not in compliance with the Uniform Guidance or GaDOE guidance related to the ESSER program. Failure to maintain a complete and accurate equipment listing and reconcile results of the physical inventory performed to the property records exposes the School District to unnecessary risk of error and misuse of equipment and/or federal funds. Recommendation: The School District should develop and maintain an equipment listing that reflects all required information, including a description, an identifying number, the source of funding, the title holder, the acquisition date, the cost, the percentage of federal participation in the project costs, the location, the use and condition, and any ultimate disposal data for each piece of equipment. In addition, management should implement controls to ensure that a complete physical inventory of equipment is performed, and the results are reconciled back to the equipment listing at least once every two years. Further, management should develop and implement a monitoring process to ensure that control procedures are being followed. Views of Responsible Officials: We concur with this finding. FA 2022-002 Improve Controls over Equipment Compliance Requirement: Equipment and Real Property Management Internal Control Impact: Material Weakness Compliance Impact: Material Noncompliance Federal Awarding Agency: U.S. Department of Education Pass-Through Entity: Georgia Department of Education AL Numbers and Titles: COVID-19 ? 84.425D ? Elementary and Secondary School Emergency Relief Fund COVID-19 ? 84.425U ? American Rescue Plan Elementary and Secondary School Emergency Relief Fund COVID-19 ? 84.425W ? American Rescue Plan Elementary and Secondary School Emergency Relief Fund ? Homeless Children and Youth Federal Award Numbers: S425D210012 (Year: 2021), S425U210012 (Year: 2021), S425W210011 (Year: 2021) Questioned Costs: None Identified Description: The policies and procedures of the School District were insufficient to provide adequate internal controls over equipment and real property management as it relates to the Elementary and Secondary School Emergency Relief Fund program. Background: On March 27, 2020, the Coronavirus Aid, Relief, and Economic Security (CARES) Act was signed into law. The CARES Act was designed to mitigate the economic effects of the COVID-19 pandemic in a variety of ways, including providing additional funding for local educational agencies (LEAs) navigating the impact of the COVID-19 outbreak. Provisions included in Title VIII of the CARES Act created the Education Stabilization Fund to provide financial resources to educational entities to prevent, prepare for, and respond to coronavirus. The CARES Act allocated $30.75 billion, the Coronavirus Response and Relief Supplemental Appropriations Act allocated an additional $81.9 billion, and the American Rescue Plan Act added $165.1 billion in funding to the Education Stabilization Fund. Multiple Education Stabilization Fund subprograms were created and allotted funding through the various COVID-19-related legislation. Of these programs, the Elementary and Secondary School Emergency Relief (ESSER) Fund was created to address the impact that COVID-19 has had, and continues to have, on elementary and secondary schools across the nation. ESSER funding was granted to the Georgia Department of Education (GaDOE) by the U.S. Department of Education (ED). GaDOE is responsible for distributing funds to LEAs and overseeing the expenditure of funds by LEAs. ESSER funds totaling $12,214,096 were expended and reported on the Tattnall County Board of Education?s Schedule of Expenditures of Federal Awards (SEFA) for fiscal year 2022. Criteria: As a recipient of federal awards, the School District is required to establish and maintain effective internal control over federal awards that provides reasonable assurance of managing the federal awards in compliance with federal statutes, regulations, and the terms and conditions of the federal awards pursuant to Title 2 U.S. Code of Federal Regulations (CFR) Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance), Section 200.303 ? Internal Controls. Provisions included in the Uniform Guidance, Section 200.313(d)(1) state, ?Property records must be maintained that include a description of the property, a serial number or other identification number, the source of funding for the property (including the FAIN), who holds title, the acquisition date, and cost of the property, percentage of Federal participation in the project costs for the Federal award under which the property was acquired, the location, use and condition of the property, and any ultimate disposition data including the date of disposal and sale price of the property.? In addition, the Uniform Guidance, Section 200.313(d)(2) states, ?A physical inventory of the property must be taken, and the results reconciled with the property records at least once every two years.? Condition: The following deficiencies were noted when reviewing the ESSER program equipment listing and physically locating five equipment items: ? Property records did not include the following required components for all items tested: (1) A description of the property, (2) a serial number or other identification number, (3) the source of funding for the property (including the FAIN), (4) who holds title, (5) percentage of Federal participation in the project costs for the Federal award under which the property was acquired, (6) the location, and (7) use and condition of the property. ? Two pieces of equipment with costs totaling $19,387 could not be physically located based on information included in the property records, and these items reflected serial numbers that did not agree to accounting records. ? The appropriate safeguarding and maintenance of three pieces of equipment with costs totaling $105,674 could not be determined based on the information included within the property records. ? While a physical inventory was performed, the results were not effectively reconciled to the equipment listing. Cause: In discussing these deficiencies with management, they stated that there are multiple inventory lists maintained by various personnel; however, there was no consistency among the listings. Effect: The School District is not in compliance with the Uniform Guidance or GaDOE guidance related to the ESSER program. Failure to maintain a complete and accurate equipment listing and reconcile results of the physical inventory performed to the property records exposes the School District to unnecessary risk of error and misuse of equipment and/or federal funds. Recommendation: The School District should develop and maintain an equipment listing that reflects all required information, including a description, an identifying number, the source of funding, the title holder, the acquisition date, the cost, the percentage of federal participation in the project costs, the location, the use and condition, and any ultimate disposal data for each piece of equipment. In addition, management should implement controls to ensure that a complete physical inventory of equipment is performed, and the results are reconciled back to the equipment listing at least once every two years. Further, management should develop and implement a monitoring process to ensure that control procedures are being followed. Views of Responsible Officials: We concur with this finding.

FY End: 2022-06-30
Tattnall County Board of Education
Compliance Requirement: F
FA 2022-002 Improve Controls over Equipment Compliance Requirement: Equipment and Real Property Management Internal Control Impact: Material Weakness Compliance Impact: Material Noncompliance Federal Awarding Agency: U.S. Department of Education Pass-Through Entity: Georgia Department of Education AL Numbers and Titles: COVID-19 ? 84.425D ? Elementary and Secondary School Emergency Relief Fund COVID-19 ? 84.425U ? American Rescue Plan Elementary and Secondary School Emergenc...

FA 2022-002 Improve Controls over Equipment Compliance Requirement: Equipment and Real Property Management Internal Control Impact: Material Weakness Compliance Impact: Material Noncompliance Federal Awarding Agency: U.S. Department of Education Pass-Through Entity: Georgia Department of Education AL Numbers and Titles: COVID-19 ? 84.425D ? Elementary and Secondary School Emergency Relief Fund COVID-19 ? 84.425U ? American Rescue Plan Elementary and Secondary School Emergency Relief Fund COVID-19 ? 84.425W ? American Rescue Plan Elementary and Secondary School Emergency Relief Fund ? Homeless Children and Youth Federal Award Numbers: S425D210012 (Year: 2021), S425U210012 (Year: 2021), S425W210011 (Year: 2021) Questioned Costs: None Identified Description: The policies and procedures of the School District were insufficient to provide adequate internal controls over equipment and real property management as it relates to the Elementary and Secondary School Emergency Relief Fund program. Background: On March 27, 2020, the Coronavirus Aid, Relief, and Economic Security (CARES) Act was signed into law. The CARES Act was designed to mitigate the economic effects of the COVID-19 pandemic in a variety of ways, including providing additional funding for local educational agencies (LEAs) navigating the impact of the COVID-19 outbreak. Provisions included in Title VIII of the CARES Act created the Education Stabilization Fund to provide financial resources to educational entities to prevent, prepare for, and respond to coronavirus. The CARES Act allocated $30.75 billion, the Coronavirus Response and Relief Supplemental Appropriations Act allocated an additional $81.9 billion, and the American Rescue Plan Act added $165.1 billion in funding to the Education Stabilization Fund. Multiple Education Stabilization Fund subprograms were created and allotted funding through the various COVID-19-related legislation. Of these programs, the Elementary and Secondary School Emergency Relief (ESSER) Fund was created to address the impact that COVID-19 has had, and continues to have, on elementary and secondary schools across the nation. ESSER funding was granted to the Georgia Department of Education (GaDOE) by the U.S. Department of Education (ED). GaDOE is responsible for distributing funds to LEAs and overseeing the expenditure of funds by LEAs. ESSER funds totaling $12,214,096 were expended and reported on the Tattnall County Board of Education?s Schedule of Expenditures of Federal Awards (SEFA) for fiscal year 2022. Criteria: As a recipient of federal awards, the School District is required to establish and maintain effective internal control over federal awards that provides reasonable assurance of managing the federal awards in compliance with federal statutes, regulations, and the terms and conditions of the federal awards pursuant to Title 2 U.S. Code of Federal Regulations (CFR) Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance), Section 200.303 ? Internal Controls. Provisions included in the Uniform Guidance, Section 200.313(d)(1) state, ?Property records must be maintained that include a description of the property, a serial number or other identification number, the source of funding for the property (including the FAIN), who holds title, the acquisition date, and cost of the property, percentage of Federal participation in the project costs for the Federal award under which the property was acquired, the location, use and condition of the property, and any ultimate disposition data including the date of disposal and sale price of the property.? In addition, the Uniform Guidance, Section 200.313(d)(2) states, ?A physical inventory of the property must be taken, and the results reconciled with the property records at least once every two years.? Condition: The following deficiencies were noted when reviewing the ESSER program equipment listing and physically locating five equipment items: ? Property records did not include the following required components for all items tested: (1) A description of the property, (2) a serial number or other identification number, (3) the source of funding for the property (including the FAIN), (4) who holds title, (5) percentage of Federal participation in the project costs for the Federal award under which the property was acquired, (6) the location, and (7) use and condition of the property. ? Two pieces of equipment with costs totaling $19,387 could not be physically located based on information included in the property records, and these items reflected serial numbers that did not agree to accounting records. ? The appropriate safeguarding and maintenance of three pieces of equipment with costs totaling $105,674 could not be determined based on the information included within the property records. ? While a physical inventory was performed, the results were not effectively reconciled to the equipment listing. Cause: In discussing these deficiencies with management, they stated that there are multiple inventory lists maintained by various personnel; however, there was no consistency among the listings. Effect: The School District is not in compliance with the Uniform Guidance or GaDOE guidance related to the ESSER program. Failure to maintain a complete and accurate equipment listing and reconcile results of the physical inventory performed to the property records exposes the School District to unnecessary risk of error and misuse of equipment and/or federal funds. Recommendation: The School District should develop and maintain an equipment listing that reflects all required information, including a description, an identifying number, the source of funding, the title holder, the acquisition date, the cost, the percentage of federal participation in the project costs, the location, the use and condition, and any ultimate disposal data for each piece of equipment. In addition, management should implement controls to ensure that a complete physical inventory of equipment is performed, and the results are reconciled back to the equipment listing at least once every two years. Further, management should develop and implement a monitoring process to ensure that control procedures are being followed. Views of Responsible Officials: We concur with this finding. FA 2022-002 Improve Controls over Equipment Compliance Requirement: Equipment and Real Property Management Internal Control Impact: Material Weakness Compliance Impact: Material Noncompliance Federal Awarding Agency: U.S. Department of Education Pass-Through Entity: Georgia Department of Education AL Numbers and Titles: COVID-19 ? 84.425D ? Elementary and Secondary School Emergency Relief Fund COVID-19 ? 84.425U ? American Rescue Plan Elementary and Secondary School Emergency Relief Fund COVID-19 ? 84.425W ? American Rescue Plan Elementary and Secondary School Emergency Relief Fund ? Homeless Children and Youth Federal Award Numbers: S425D210012 (Year: 2021), S425U210012 (Year: 2021), S425W210011 (Year: 2021) Questioned Costs: None Identified Description: The policies and procedures of the School District were insufficient to provide adequate internal controls over equipment and real property management as it relates to the Elementary and Secondary School Emergency Relief Fund program. Background: On March 27, 2020, the Coronavirus Aid, Relief, and Economic Security (CARES) Act was signed into law. The CARES Act was designed to mitigate the economic effects of the COVID-19 pandemic in a variety of ways, including providing additional funding for local educational agencies (LEAs) navigating the impact of the COVID-19 outbreak. Provisions included in Title VIII of the CARES Act created the Education Stabilization Fund to provide financial resources to educational entities to prevent, prepare for, and respond to coronavirus. The CARES Act allocated $30.75 billion, the Coronavirus Response and Relief Supplemental Appropriations Act allocated an additional $81.9 billion, and the American Rescue Plan Act added $165.1 billion in funding to the Education Stabilization Fund. Multiple Education Stabilization Fund subprograms were created and allotted funding through the various COVID-19-related legislation. Of these programs, the Elementary and Secondary School Emergency Relief (ESSER) Fund was created to address the impact that COVID-19 has had, and continues to have, on elementary and secondary schools across the nation. ESSER funding was granted to the Georgia Department of Education (GaDOE) by the U.S. Department of Education (ED). GaDOE is responsible for distributing funds to LEAs and overseeing the expenditure of funds by LEAs. ESSER funds totaling $12,214,096 were expended and reported on the Tattnall County Board of Education?s Schedule of Expenditures of Federal Awards (SEFA) for fiscal year 2022. Criteria: As a recipient of federal awards, the School District is required to establish and maintain effective internal control over federal awards that provides reasonable assurance of managing the federal awards in compliance with federal statutes, regulations, and the terms and conditions of the federal awards pursuant to Title 2 U.S. Code of Federal Regulations (CFR) Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance), Section 200.303 ? Internal Controls. Provisions included in the Uniform Guidance, Section 200.313(d)(1) state, ?Property records must be maintained that include a description of the property, a serial number or other identification number, the source of funding for the property (including the FAIN), who holds title, the acquisition date, and cost of the property, percentage of Federal participation in the project costs for the Federal award under which the property was acquired, the location, use and condition of the property, and any ultimate disposition data including the date of disposal and sale price of the property.? In addition, the Uniform Guidance, Section 200.313(d)(2) states, ?A physical inventory of the property must be taken, and the results reconciled with the property records at least once every two years.? Condition: The following deficiencies were noted when reviewing the ESSER program equipment listing and physically locating five equipment items: ? Property records did not include the following required components for all items tested: (1) A description of the property, (2) a serial number or other identification number, (3) the source of funding for the property (including the FAIN), (4) who holds title, (5) percentage of Federal participation in the project costs for the Federal award under which the property was acquired, (6) the location, and (7) use and condition of the property. ? Two pieces of equipment with costs totaling $19,387 could not be physically located based on information included in the property records, and these items reflected serial numbers that did not agree to accounting records. ? The appropriate safeguarding and maintenance of three pieces of equipment with costs totaling $105,674 could not be determined based on the information included within the property records. ? While a physical inventory was performed, the results were not effectively reconciled to the equipment listing. Cause: In discussing these deficiencies with management, they stated that there are multiple inventory lists maintained by various personnel; however, there was no consistency among the listings. Effect: The School District is not in compliance with the Uniform Guidance or GaDOE guidance related to the ESSER program. Failure to maintain a complete and accurate equipment listing and reconcile results of the physical inventory performed to the property records exposes the School District to unnecessary risk of error and misuse of equipment and/or federal funds. Recommendation: The School District should develop and maintain an equipment listing that reflects all required information, including a description, an identifying number, the source of funding, the title holder, the acquisition date, the cost, the percentage of federal participation in the project costs, the location, the use and condition, and any ultimate disposal data for each piece of equipment. In addition, management should implement controls to ensure that a complete physical inventory of equipment is performed, and the results are reconciled back to the equipment listing at least once every two years. Further, management should develop and implement a monitoring process to ensure that control procedures are being followed. Views of Responsible Officials: We concur with this finding.

FY End: 2022-06-30
Tattnall County Board of Education
Compliance Requirement: F
FA 2022-002 Improve Controls over Equipment Compliance Requirement: Equipment and Real Property Management Internal Control Impact: Material Weakness Compliance Impact: Material Noncompliance Federal Awarding Agency: U.S. Department of Education Pass-Through Entity: Georgia Department of Education AL Numbers and Titles: COVID-19 ? 84.425D ? Elementary and Secondary School Emergency Relief Fund COVID-19 ? 84.425U ? American Rescue Plan Elementary and Secondary School Emergenc...

FA 2022-002 Improve Controls over Equipment Compliance Requirement: Equipment and Real Property Management Internal Control Impact: Material Weakness Compliance Impact: Material Noncompliance Federal Awarding Agency: U.S. Department of Education Pass-Through Entity: Georgia Department of Education AL Numbers and Titles: COVID-19 ? 84.425D ? Elementary and Secondary School Emergency Relief Fund COVID-19 ? 84.425U ? American Rescue Plan Elementary and Secondary School Emergency Relief Fund COVID-19 ? 84.425W ? American Rescue Plan Elementary and Secondary School Emergency Relief Fund ? Homeless Children and Youth Federal Award Numbers: S425D210012 (Year: 2021), S425U210012 (Year: 2021), S425W210011 (Year: 2021) Questioned Costs: None Identified Description: The policies and procedures of the School District were insufficient to provide adequate internal controls over equipment and real property management as it relates to the Elementary and Secondary School Emergency Relief Fund program. Background: On March 27, 2020, the Coronavirus Aid, Relief, and Economic Security (CARES) Act was signed into law. The CARES Act was designed to mitigate the economic effects of the COVID-19 pandemic in a variety of ways, including providing additional funding for local educational agencies (LEAs) navigating the impact of the COVID-19 outbreak. Provisions included in Title VIII of the CARES Act created the Education Stabilization Fund to provide financial resources to educational entities to prevent, prepare for, and respond to coronavirus. The CARES Act allocated $30.75 billion, the Coronavirus Response and Relief Supplemental Appropriations Act allocated an additional $81.9 billion, and the American Rescue Plan Act added $165.1 billion in funding to the Education Stabilization Fund. Multiple Education Stabilization Fund subprograms were created and allotted funding through the various COVID-19-related legislation. Of these programs, the Elementary and Secondary School Emergency Relief (ESSER) Fund was created to address the impact that COVID-19 has had, and continues to have, on elementary and secondary schools across the nation. ESSER funding was granted to the Georgia Department of Education (GaDOE) by the U.S. Department of Education (ED). GaDOE is responsible for distributing funds to LEAs and overseeing the expenditure of funds by LEAs. ESSER funds totaling $12,214,096 were expended and reported on the Tattnall County Board of Education?s Schedule of Expenditures of Federal Awards (SEFA) for fiscal year 2022. Criteria: As a recipient of federal awards, the School District is required to establish and maintain effective internal control over federal awards that provides reasonable assurance of managing the federal awards in compliance with federal statutes, regulations, and the terms and conditions of the federal awards pursuant to Title 2 U.S. Code of Federal Regulations (CFR) Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance), Section 200.303 ? Internal Controls. Provisions included in the Uniform Guidance, Section 200.313(d)(1) state, ?Property records must be maintained that include a description of the property, a serial number or other identification number, the source of funding for the property (including the FAIN), who holds title, the acquisition date, and cost of the property, percentage of Federal participation in the project costs for the Federal award under which the property was acquired, the location, use and condition of the property, and any ultimate disposition data including the date of disposal and sale price of the property.? In addition, the Uniform Guidance, Section 200.313(d)(2) states, ?A physical inventory of the property must be taken, and the results reconciled with the property records at least once every two years.? Condition: The following deficiencies were noted when reviewing the ESSER program equipment listing and physically locating five equipment items: ? Property records did not include the following required components for all items tested: (1) A description of the property, (2) a serial number or other identification number, (3) the source of funding for the property (including the FAIN), (4) who holds title, (5) percentage of Federal participation in the project costs for the Federal award under which the property was acquired, (6) the location, and (7) use and condition of the property. ? Two pieces of equipment with costs totaling $19,387 could not be physically located based on information included in the property records, and these items reflected serial numbers that did not agree to accounting records. ? The appropriate safeguarding and maintenance of three pieces of equipment with costs totaling $105,674 could not be determined based on the information included within the property records. ? While a physical inventory was performed, the results were not effectively reconciled to the equipment listing. Cause: In discussing these deficiencies with management, they stated that there are multiple inventory lists maintained by various personnel; however, there was no consistency among the listings. Effect: The School District is not in compliance with the Uniform Guidance or GaDOE guidance related to the ESSER program. Failure to maintain a complete and accurate equipment listing and reconcile results of the physical inventory performed to the property records exposes the School District to unnecessary risk of error and misuse of equipment and/or federal funds. Recommendation: The School District should develop and maintain an equipment listing that reflects all required information, including a description, an identifying number, the source of funding, the title holder, the acquisition date, the cost, the percentage of federal participation in the project costs, the location, the use and condition, and any ultimate disposal data for each piece of equipment. In addition, management should implement controls to ensure that a complete physical inventory of equipment is performed, and the results are reconciled back to the equipment listing at least once every two years. Further, management should develop and implement a monitoring process to ensure that control procedures are being followed. Views of Responsible Officials: We concur with this finding. FA 2022-002 Improve Controls over Equipment Compliance Requirement: Equipment and Real Property Management Internal Control Impact: Material Weakness Compliance Impact: Material Noncompliance Federal Awarding Agency: U.S. Department of Education Pass-Through Entity: Georgia Department of Education AL Numbers and Titles: COVID-19 ? 84.425D ? Elementary and Secondary School Emergency Relief Fund COVID-19 ? 84.425U ? American Rescue Plan Elementary and Secondary School Emergency Relief Fund COVID-19 ? 84.425W ? American Rescue Plan Elementary and Secondary School Emergency Relief Fund ? Homeless Children and Youth Federal Award Numbers: S425D210012 (Year: 2021), S425U210012 (Year: 2021), S425W210011 (Year: 2021) Questioned Costs: None Identified Description: The policies and procedures of the School District were insufficient to provide adequate internal controls over equipment and real property management as it relates to the Elementary and Secondary School Emergency Relief Fund program. Background: On March 27, 2020, the Coronavirus Aid, Relief, and Economic Security (CARES) Act was signed into law. The CARES Act was designed to mitigate the economic effects of the COVID-19 pandemic in a variety of ways, including providing additional funding for local educational agencies (LEAs) navigating the impact of the COVID-19 outbreak. Provisions included in Title VIII of the CARES Act created the Education Stabilization Fund to provide financial resources to educational entities to prevent, prepare for, and respond to coronavirus. The CARES Act allocated $30.75 billion, the Coronavirus Response and Relief Supplemental Appropriations Act allocated an additional $81.9 billion, and the American Rescue Plan Act added $165.1 billion in funding to the Education Stabilization Fund. Multiple Education Stabilization Fund subprograms were created and allotted funding through the various COVID-19-related legislation. Of these programs, the Elementary and Secondary School Emergency Relief (ESSER) Fund was created to address the impact that COVID-19 has had, and continues to have, on elementary and secondary schools across the nation. ESSER funding was granted to the Georgia Department of Education (GaDOE) by the U.S. Department of Education (ED). GaDOE is responsible for distributing funds to LEAs and overseeing the expenditure of funds by LEAs. ESSER funds totaling $12,214,096 were expended and reported on the Tattnall County Board of Education?s Schedule of Expenditures of Federal Awards (SEFA) for fiscal year 2022. Criteria: As a recipient of federal awards, the School District is required to establish and maintain effective internal control over federal awards that provides reasonable assurance of managing the federal awards in compliance with federal statutes, regulations, and the terms and conditions of the federal awards pursuant to Title 2 U.S. Code of Federal Regulations (CFR) Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance), Section 200.303 ? Internal Controls. Provisions included in the Uniform Guidance, Section 200.313(d)(1) state, ?Property records must be maintained that include a description of the property, a serial number or other identification number, the source of funding for the property (including the FAIN), who holds title, the acquisition date, and cost of the property, percentage of Federal participation in the project costs for the Federal award under which the property was acquired, the location, use and condition of the property, and any ultimate disposition data including the date of disposal and sale price of the property.? In addition, the Uniform Guidance, Section 200.313(d)(2) states, ?A physical inventory of the property must be taken, and the results reconciled with the property records at least once every two years.? Condition: The following deficiencies were noted when reviewing the ESSER program equipment listing and physically locating five equipment items: ? Property records did not include the following required components for all items tested: (1) A description of the property, (2) a serial number or other identification number, (3) the source of funding for the property (including the FAIN), (4) who holds title, (5) percentage of Federal participation in the project costs for the Federal award under which the property was acquired, (6) the location, and (7) use and condition of the property. ? Two pieces of equipment with costs totaling $19,387 could not be physically located based on information included in the property records, and these items reflected serial numbers that did not agree to accounting records. ? The appropriate safeguarding and maintenance of three pieces of equipment with costs totaling $105,674 could not be determined based on the information included within the property records. ? While a physical inventory was performed, the results were not effectively reconciled to the equipment listing. Cause: In discussing these deficiencies with management, they stated that there are multiple inventory lists maintained by various personnel; however, there was no consistency among the listings. Effect: The School District is not in compliance with the Uniform Guidance or GaDOE guidance related to the ESSER program. Failure to maintain a complete and accurate equipment listing and reconcile results of the physical inventory performed to the property records exposes the School District to unnecessary risk of error and misuse of equipment and/or federal funds. Recommendation: The School District should develop and maintain an equipment listing that reflects all required information, including a description, an identifying number, the source of funding, the title holder, the acquisition date, the cost, the percentage of federal participation in the project costs, the location, the use and condition, and any ultimate disposal data for each piece of equipment. In addition, management should implement controls to ensure that a complete physical inventory of equipment is performed, and the results are reconciled back to the equipment listing at least once every two years. Further, management should develop and implement a monitoring process to ensure that control procedures are being followed. Views of Responsible Officials: We concur with this finding.

FY End: 2022-06-30
Dartmouth-Hitchcock Health and Subsidiaries
Compliance Requirement: F
Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records...

Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records must be maintained that include a description of the property, a serial number or other identification number, the source of funding for the property (including the FAIN), who holds title, the acquisition date, and cost of the property, percentage of Federal participation in the project costs for the Federal award under which the property was acquired, the location, use and condition of the property, and any ultimate disposition data including the date of disposal and sale price of the property. (2) A physical inventory of the property must be taken and the results reconciled with the property records at least once every two years. (3) A control system must be developed to ensure adequate safeguards to prevent loss, damage, or theft of the property. Any loss, damage, or theft must be investigated. (4) Adequate maintenance procedures must be developed to keep the property in good condition. (5) If the non-Federal entity is authorized or required to sell the property, proper sales procedures must be established to ensure the highest possible return. Condition The Health System did not perform a physical inventory of federally purchased fixed assets at least once during the last two years. Additionally, the federal asset listing did not specify all of the details required by 2 CFR section 200.313 (d) (1) such as asset locations, tag numbers, use and condition. The full population of equipment funded with federal research and development dollars, as provided by the Health System, consisted of 9 items with a total historical cost of $105k. Cause The Health System lacks a process to ensure that policies and procedures related to identifying and managing its federally purchased fixed assets in accordance with 2 CFR section 200.313 are followed, including updating property records to include all required data elements and the performance of a physical inventory at least once every two years. Effect The Health System's accounting records for its federally purchased fixed assets could be inaccurate as the Health System has not formally verified the existence, current utilization and continued need for the equipment through this physical inventory process. Additionally, without maintaining tag numbers and records of asset locations, safeguarding of assets could be impacted. Questioned Costs None noted. Recommendation We recommend that the Health System implement a process to ensure its policies and procedures over equipment management are followed, including the performance of a physical inventory of federally purchased fixed assets at least once every two years in accordance with 2 CFR section 200.313(d)(2), and updating its property records to include all details required by 2 CFR section 200.313(d)(1). Management?s Views and Corrective Action Plan Management?s Views and Corrective Action Plan is included at the end of this report after the summary schedule of prior audit findings and status.

FY End: 2022-06-30
Dartmouth-Hitchcock Health and Subsidiaries
Compliance Requirement: F
Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records...

Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records must be maintained that include a description of the property, a serial number or other identification number, the source of funding for the property (including the FAIN), who holds title, the acquisition date, and cost of the property, percentage of Federal participation in the project costs for the Federal award under which the property was acquired, the location, use and condition of the property, and any ultimate disposition data including the date of disposal and sale price of the property. (2) A physical inventory of the property must be taken and the results reconciled with the property records at least once every two years. (3) A control system must be developed to ensure adequate safeguards to prevent loss, damage, or theft of the property. Any loss, damage, or theft must be investigated. (4) Adequate maintenance procedures must be developed to keep the property in good condition. (5) If the non-Federal entity is authorized or required to sell the property, proper sales procedures must be established to ensure the highest possible return. Condition The Health System did not perform a physical inventory of federally purchased fixed assets at least once during the last two years. Additionally, the federal asset listing did not specify all of the details required by 2 CFR section 200.313 (d) (1) such as asset locations, tag numbers, use and condition. The full population of equipment funded with federal research and development dollars, as provided by the Health System, consisted of 9 items with a total historical cost of $105k. Cause The Health System lacks a process to ensure that policies and procedures related to identifying and managing its federally purchased fixed assets in accordance with 2 CFR section 200.313 are followed, including updating property records to include all required data elements and the performance of a physical inventory at least once every two years. Effect The Health System's accounting records for its federally purchased fixed assets could be inaccurate as the Health System has not formally verified the existence, current utilization and continued need for the equipment through this physical inventory process. Additionally, without maintaining tag numbers and records of asset locations, safeguarding of assets could be impacted. Questioned Costs None noted. Recommendation We recommend that the Health System implement a process to ensure its policies and procedures over equipment management are followed, including the performance of a physical inventory of federally purchased fixed assets at least once every two years in accordance with 2 CFR section 200.313(d)(2), and updating its property records to include all details required by 2 CFR section 200.313(d)(1). Management?s Views and Corrective Action Plan Management?s Views and Corrective Action Plan is included at the end of this report after the summary schedule of prior audit findings and status.

FY End: 2022-06-30
Dartmouth-Hitchcock Health and Subsidiaries
Compliance Requirement: F
Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records...

Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records must be maintained that include a description of the property, a serial number or other identification number, the source of funding for the property (including the FAIN), who holds title, the acquisition date, and cost of the property, percentage of Federal participation in the project costs for the Federal award under which the property was acquired, the location, use and condition of the property, and any ultimate disposition data including the date of disposal and sale price of the property. (2) A physical inventory of the property must be taken and the results reconciled with the property records at least once every two years. (3) A control system must be developed to ensure adequate safeguards to prevent loss, damage, or theft of the property. Any loss, damage, or theft must be investigated. (4) Adequate maintenance procedures must be developed to keep the property in good condition. (5) If the non-Federal entity is authorized or required to sell the property, proper sales procedures must be established to ensure the highest possible return. Condition The Health System did not perform a physical inventory of federally purchased fixed assets at least once during the last two years. Additionally, the federal asset listing did not specify all of the details required by 2 CFR section 200.313 (d) (1) such as asset locations, tag numbers, use and condition. The full population of equipment funded with federal research and development dollars, as provided by the Health System, consisted of 9 items with a total historical cost of $105k. Cause The Health System lacks a process to ensure that policies and procedures related to identifying and managing its federally purchased fixed assets in accordance with 2 CFR section 200.313 are followed, including updating property records to include all required data elements and the performance of a physical inventory at least once every two years. Effect The Health System's accounting records for its federally purchased fixed assets could be inaccurate as the Health System has not formally verified the existence, current utilization and continued need for the equipment through this physical inventory process. Additionally, without maintaining tag numbers and records of asset locations, safeguarding of assets could be impacted. Questioned Costs None noted. Recommendation We recommend that the Health System implement a process to ensure its policies and procedures over equipment management are followed, including the performance of a physical inventory of federally purchased fixed assets at least once every two years in accordance with 2 CFR section 200.313(d)(2), and updating its property records to include all details required by 2 CFR section 200.313(d)(1). Management?s Views and Corrective Action Plan Management?s Views and Corrective Action Plan is included at the end of this report after the summary schedule of prior audit findings and status.

FY End: 2022-06-30
Dartmouth-Hitchcock Health and Subsidiaries
Compliance Requirement: F
Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records...

Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records must be maintained that include a description of the property, a serial number or other identification number, the source of funding for the property (including the FAIN), who holds title, the acquisition date, and cost of the property, percentage of Federal participation in the project costs for the Federal award under which the property was acquired, the location, use and condition of the property, and any ultimate disposition data including the date of disposal and sale price of the property. (2) A physical inventory of the property must be taken and the results reconciled with the property records at least once every two years. (3) A control system must be developed to ensure adequate safeguards to prevent loss, damage, or theft of the property. Any loss, damage, or theft must be investigated. (4) Adequate maintenance procedures must be developed to keep the property in good condition. (5) If the non-Federal entity is authorized or required to sell the property, proper sales procedures must be established to ensure the highest possible return. Condition The Health System did not perform a physical inventory of federally purchased fixed assets at least once during the last two years. Additionally, the federal asset listing did not specify all of the details required by 2 CFR section 200.313 (d) (1) such as asset locations, tag numbers, use and condition. The full population of equipment funded with federal research and development dollars, as provided by the Health System, consisted of 9 items with a total historical cost of $105k. Cause The Health System lacks a process to ensure that policies and procedures related to identifying and managing its federally purchased fixed assets in accordance with 2 CFR section 200.313 are followed, including updating property records to include all required data elements and the performance of a physical inventory at least once every two years. Effect The Health System's accounting records for its federally purchased fixed assets could be inaccurate as the Health System has not formally verified the existence, current utilization and continued need for the equipment through this physical inventory process. Additionally, without maintaining tag numbers and records of asset locations, safeguarding of assets could be impacted. Questioned Costs None noted. Recommendation We recommend that the Health System implement a process to ensure its policies and procedures over equipment management are followed, including the performance of a physical inventory of federally purchased fixed assets at least once every two years in accordance with 2 CFR section 200.313(d)(2), and updating its property records to include all details required by 2 CFR section 200.313(d)(1). Management?s Views and Corrective Action Plan Management?s Views and Corrective Action Plan is included at the end of this report after the summary schedule of prior audit findings and status.

FY End: 2022-06-30
Dartmouth-Hitchcock Health and Subsidiaries
Compliance Requirement: F
Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records...

Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records must be maintained that include a description of the property, a serial number or other identification number, the source of funding for the property (including the FAIN), who holds title, the acquisition date, and cost of the property, percentage of Federal participation in the project costs for the Federal award under which the property was acquired, the location, use and condition of the property, and any ultimate disposition data including the date of disposal and sale price of the property. (2) A physical inventory of the property must be taken and the results reconciled with the property records at least once every two years. (3) A control system must be developed to ensure adequate safeguards to prevent loss, damage, or theft of the property. Any loss, damage, or theft must be investigated. (4) Adequate maintenance procedures must be developed to keep the property in good condition. (5) If the non-Federal entity is authorized or required to sell the property, proper sales procedures must be established to ensure the highest possible return. Condition The Health System did not perform a physical inventory of federally purchased fixed assets at least once during the last two years. Additionally, the federal asset listing did not specify all of the details required by 2 CFR section 200.313 (d) (1) such as asset locations, tag numbers, use and condition. The full population of equipment funded with federal research and development dollars, as provided by the Health System, consisted of 9 items with a total historical cost of $105k. Cause The Health System lacks a process to ensure that policies and procedures related to identifying and managing its federally purchased fixed assets in accordance with 2 CFR section 200.313 are followed, including updating property records to include all required data elements and the performance of a physical inventory at least once every two years. Effect The Health System's accounting records for its federally purchased fixed assets could be inaccurate as the Health System has not formally verified the existence, current utilization and continued need for the equipment through this physical inventory process. Additionally, without maintaining tag numbers and records of asset locations, safeguarding of assets could be impacted. Questioned Costs None noted. Recommendation We recommend that the Health System implement a process to ensure its policies and procedures over equipment management are followed, including the performance of a physical inventory of federally purchased fixed assets at least once every two years in accordance with 2 CFR section 200.313(d)(2), and updating its property records to include all details required by 2 CFR section 200.313(d)(1). Management?s Views and Corrective Action Plan Management?s Views and Corrective Action Plan is included at the end of this report after the summary schedule of prior audit findings and status.

FY End: 2022-06-30
Dartmouth-Hitchcock Health and Subsidiaries
Compliance Requirement: F
Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records...

Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records must be maintained that include a description of the property, a serial number or other identification number, the source of funding for the property (including the FAIN), who holds title, the acquisition date, and cost of the property, percentage of Federal participation in the project costs for the Federal award under which the property was acquired, the location, use and condition of the property, and any ultimate disposition data including the date of disposal and sale price of the property. (2) A physical inventory of the property must be taken and the results reconciled with the property records at least once every two years. (3) A control system must be developed to ensure adequate safeguards to prevent loss, damage, or theft of the property. Any loss, damage, or theft must be investigated. (4) Adequate maintenance procedures must be developed to keep the property in good condition. (5) If the non-Federal entity is authorized or required to sell the property, proper sales procedures must be established to ensure the highest possible return. Condition The Health System did not perform a physical inventory of federally purchased fixed assets at least once during the last two years. Additionally, the federal asset listing did not specify all of the details required by 2 CFR section 200.313 (d) (1) such as asset locations, tag numbers, use and condition. The full population of equipment funded with federal research and development dollars, as provided by the Health System, consisted of 9 items with a total historical cost of $105k. Cause The Health System lacks a process to ensure that policies and procedures related to identifying and managing its federally purchased fixed assets in accordance with 2 CFR section 200.313 are followed, including updating property records to include all required data elements and the performance of a physical inventory at least once every two years. Effect The Health System's accounting records for its federally purchased fixed assets could be inaccurate as the Health System has not formally verified the existence, current utilization and continued need for the equipment through this physical inventory process. Additionally, without maintaining tag numbers and records of asset locations, safeguarding of assets could be impacted. Questioned Costs None noted. Recommendation We recommend that the Health System implement a process to ensure its policies and procedures over equipment management are followed, including the performance of a physical inventory of federally purchased fixed assets at least once every two years in accordance with 2 CFR section 200.313(d)(2), and updating its property records to include all details required by 2 CFR section 200.313(d)(1). Management?s Views and Corrective Action Plan Management?s Views and Corrective Action Plan is included at the end of this report after the summary schedule of prior audit findings and status.

FY End: 2022-06-30
Dartmouth-Hitchcock Health and Subsidiaries
Compliance Requirement: F
Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records...

Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records must be maintained that include a description of the property, a serial number or other identification number, the source of funding for the property (including the FAIN), who holds title, the acquisition date, and cost of the property, percentage of Federal participation in the project costs for the Federal award under which the property was acquired, the location, use and condition of the property, and any ultimate disposition data including the date of disposal and sale price of the property. (2) A physical inventory of the property must be taken and the results reconciled with the property records at least once every two years. (3) A control system must be developed to ensure adequate safeguards to prevent loss, damage, or theft of the property. Any loss, damage, or theft must be investigated. (4) Adequate maintenance procedures must be developed to keep the property in good condition. (5) If the non-Federal entity is authorized or required to sell the property, proper sales procedures must be established to ensure the highest possible return. Condition The Health System did not perform a physical inventory of federally purchased fixed assets at least once during the last two years. Additionally, the federal asset listing did not specify all of the details required by 2 CFR section 200.313 (d) (1) such as asset locations, tag numbers, use and condition. The full population of equipment funded with federal research and development dollars, as provided by the Health System, consisted of 9 items with a total historical cost of $105k. Cause The Health System lacks a process to ensure that policies and procedures related to identifying and managing its federally purchased fixed assets in accordance with 2 CFR section 200.313 are followed, including updating property records to include all required data elements and the performance of a physical inventory at least once every two years. Effect The Health System's accounting records for its federally purchased fixed assets could be inaccurate as the Health System has not formally verified the existence, current utilization and continued need for the equipment through this physical inventory process. Additionally, without maintaining tag numbers and records of asset locations, safeguarding of assets could be impacted. Questioned Costs None noted. Recommendation We recommend that the Health System implement a process to ensure its policies and procedures over equipment management are followed, including the performance of a physical inventory of federally purchased fixed assets at least once every two years in accordance with 2 CFR section 200.313(d)(2), and updating its property records to include all details required by 2 CFR section 200.313(d)(1). Management?s Views and Corrective Action Plan Management?s Views and Corrective Action Plan is included at the end of this report after the summary schedule of prior audit findings and status.

FY End: 2022-06-30
Dartmouth-Hitchcock Health and Subsidiaries
Compliance Requirement: F
Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records...

Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records must be maintained that include a description of the property, a serial number or other identification number, the source of funding for the property (including the FAIN), who holds title, the acquisition date, and cost of the property, percentage of Federal participation in the project costs for the Federal award under which the property was acquired, the location, use and condition of the property, and any ultimate disposition data including the date of disposal and sale price of the property. (2) A physical inventory of the property must be taken and the results reconciled with the property records at least once every two years. (3) A control system must be developed to ensure adequate safeguards to prevent loss, damage, or theft of the property. Any loss, damage, or theft must be investigated. (4) Adequate maintenance procedures must be developed to keep the property in good condition. (5) If the non-Federal entity is authorized or required to sell the property, proper sales procedures must be established to ensure the highest possible return. Condition The Health System did not perform a physical inventory of federally purchased fixed assets at least once during the last two years. Additionally, the federal asset listing did not specify all of the details required by 2 CFR section 200.313 (d) (1) such as asset locations, tag numbers, use and condition. The full population of equipment funded with federal research and development dollars, as provided by the Health System, consisted of 9 items with a total historical cost of $105k. Cause The Health System lacks a process to ensure that policies and procedures related to identifying and managing its federally purchased fixed assets in accordance with 2 CFR section 200.313 are followed, including updating property records to include all required data elements and the performance of a physical inventory at least once every two years. Effect The Health System's accounting records for its federally purchased fixed assets could be inaccurate as the Health System has not formally verified the existence, current utilization and continued need for the equipment through this physical inventory process. Additionally, without maintaining tag numbers and records of asset locations, safeguarding of assets could be impacted. Questioned Costs None noted. Recommendation We recommend that the Health System implement a process to ensure its policies and procedures over equipment management are followed, including the performance of a physical inventory of federally purchased fixed assets at least once every two years in accordance with 2 CFR section 200.313(d)(2), and updating its property records to include all details required by 2 CFR section 200.313(d)(1). Management?s Views and Corrective Action Plan Management?s Views and Corrective Action Plan is included at the end of this report after the summary schedule of prior audit findings and status.

FY End: 2022-06-30
Dartmouth-Hitchcock Health and Subsidiaries
Compliance Requirement: F
Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records...

Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records must be maintained that include a description of the property, a serial number or other identification number, the source of funding for the property (including the FAIN), who holds title, the acquisition date, and cost of the property, percentage of Federal participation in the project costs for the Federal award under which the property was acquired, the location, use and condition of the property, and any ultimate disposition data including the date of disposal and sale price of the property. (2) A physical inventory of the property must be taken and the results reconciled with the property records at least once every two years. (3) A control system must be developed to ensure adequate safeguards to prevent loss, damage, or theft of the property. Any loss, damage, or theft must be investigated. (4) Adequate maintenance procedures must be developed to keep the property in good condition. (5) If the non-Federal entity is authorized or required to sell the property, proper sales procedures must be established to ensure the highest possible return. Condition The Health System did not perform a physical inventory of federally purchased fixed assets at least once during the last two years. Additionally, the federal asset listing did not specify all of the details required by 2 CFR section 200.313 (d) (1) such as asset locations, tag numbers, use and condition. The full population of equipment funded with federal research and development dollars, as provided by the Health System, consisted of 9 items with a total historical cost of $105k. Cause The Health System lacks a process to ensure that policies and procedures related to identifying and managing its federally purchased fixed assets in accordance with 2 CFR section 200.313 are followed, including updating property records to include all required data elements and the performance of a physical inventory at least once every two years. Effect The Health System's accounting records for its federally purchased fixed assets could be inaccurate as the Health System has not formally verified the existence, current utilization and continued need for the equipment through this physical inventory process. Additionally, without maintaining tag numbers and records of asset locations, safeguarding of assets could be impacted. Questioned Costs None noted. Recommendation We recommend that the Health System implement a process to ensure its policies and procedures over equipment management are followed, including the performance of a physical inventory of federally purchased fixed assets at least once every two years in accordance with 2 CFR section 200.313(d)(2), and updating its property records to include all details required by 2 CFR section 200.313(d)(1). Management?s Views and Corrective Action Plan Management?s Views and Corrective Action Plan is included at the end of this report after the summary schedule of prior audit findings and status.

FY End: 2022-06-30
Dartmouth-Hitchcock Health and Subsidiaries
Compliance Requirement: F
Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records...

Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records must be maintained that include a description of the property, a serial number or other identification number, the source of funding for the property (including the FAIN), who holds title, the acquisition date, and cost of the property, percentage of Federal participation in the project costs for the Federal award under which the property was acquired, the location, use and condition of the property, and any ultimate disposition data including the date of disposal and sale price of the property. (2) A physical inventory of the property must be taken and the results reconciled with the property records at least once every two years. (3) A control system must be developed to ensure adequate safeguards to prevent loss, damage, or theft of the property. Any loss, damage, or theft must be investigated. (4) Adequate maintenance procedures must be developed to keep the property in good condition. (5) If the non-Federal entity is authorized or required to sell the property, proper sales procedures must be established to ensure the highest possible return. Condition The Health System did not perform a physical inventory of federally purchased fixed assets at least once during the last two years. Additionally, the federal asset listing did not specify all of the details required by 2 CFR section 200.313 (d) (1) such as asset locations, tag numbers, use and condition. The full population of equipment funded with federal research and development dollars, as provided by the Health System, consisted of 9 items with a total historical cost of $105k. Cause The Health System lacks a process to ensure that policies and procedures related to identifying and managing its federally purchased fixed assets in accordance with 2 CFR section 200.313 are followed, including updating property records to include all required data elements and the performance of a physical inventory at least once every two years. Effect The Health System's accounting records for its federally purchased fixed assets could be inaccurate as the Health System has not formally verified the existence, current utilization and continued need for the equipment through this physical inventory process. Additionally, without maintaining tag numbers and records of asset locations, safeguarding of assets could be impacted. Questioned Costs None noted. Recommendation We recommend that the Health System implement a process to ensure its policies and procedures over equipment management are followed, including the performance of a physical inventory of federally purchased fixed assets at least once every two years in accordance with 2 CFR section 200.313(d)(2), and updating its property records to include all details required by 2 CFR section 200.313(d)(1). Management?s Views and Corrective Action Plan Management?s Views and Corrective Action Plan is included at the end of this report after the summary schedule of prior audit findings and status.

FY End: 2022-06-30
Dartmouth-Hitchcock Health and Subsidiaries
Compliance Requirement: F
Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records...

Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records must be maintained that include a description of the property, a serial number or other identification number, the source of funding for the property (including the FAIN), who holds title, the acquisition date, and cost of the property, percentage of Federal participation in the project costs for the Federal award under which the property was acquired, the location, use and condition of the property, and any ultimate disposition data including the date of disposal and sale price of the property. (2) A physical inventory of the property must be taken and the results reconciled with the property records at least once every two years. (3) A control system must be developed to ensure adequate safeguards to prevent loss, damage, or theft of the property. Any loss, damage, or theft must be investigated. (4) Adequate maintenance procedures must be developed to keep the property in good condition. (5) If the non-Federal entity is authorized or required to sell the property, proper sales procedures must be established to ensure the highest possible return. Condition The Health System did not perform a physical inventory of federally purchased fixed assets at least once during the last two years. Additionally, the federal asset listing did not specify all of the details required by 2 CFR section 200.313 (d) (1) such as asset locations, tag numbers, use and condition. The full population of equipment funded with federal research and development dollars, as provided by the Health System, consisted of 9 items with a total historical cost of $105k. Cause The Health System lacks a process to ensure that policies and procedures related to identifying and managing its federally purchased fixed assets in accordance with 2 CFR section 200.313 are followed, including updating property records to include all required data elements and the performance of a physical inventory at least once every two years. Effect The Health System's accounting records for its federally purchased fixed assets could be inaccurate as the Health System has not formally verified the existence, current utilization and continued need for the equipment through this physical inventory process. Additionally, without maintaining tag numbers and records of asset locations, safeguarding of assets could be impacted. Questioned Costs None noted. Recommendation We recommend that the Health System implement a process to ensure its policies and procedures over equipment management are followed, including the performance of a physical inventory of federally purchased fixed assets at least once every two years in accordance with 2 CFR section 200.313(d)(2), and updating its property records to include all details required by 2 CFR section 200.313(d)(1). Management?s Views and Corrective Action Plan Management?s Views and Corrective Action Plan is included at the end of this report after the summary schedule of prior audit findings and status.

FY End: 2022-06-30
Dartmouth-Hitchcock Health and Subsidiaries
Compliance Requirement: F
Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records...

Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records must be maintained that include a description of the property, a serial number or other identification number, the source of funding for the property (including the FAIN), who holds title, the acquisition date, and cost of the property, percentage of Federal participation in the project costs for the Federal award under which the property was acquired, the location, use and condition of the property, and any ultimate disposition data including the date of disposal and sale price of the property. (2) A physical inventory of the property must be taken and the results reconciled with the property records at least once every two years. (3) A control system must be developed to ensure adequate safeguards to prevent loss, damage, or theft of the property. Any loss, damage, or theft must be investigated. (4) Adequate maintenance procedures must be developed to keep the property in good condition. (5) If the non-Federal entity is authorized or required to sell the property, proper sales procedures must be established to ensure the highest possible return. Condition The Health System did not perform a physical inventory of federally purchased fixed assets at least once during the last two years. Additionally, the federal asset listing did not specify all of the details required by 2 CFR section 200.313 (d) (1) such as asset locations, tag numbers, use and condition. The full population of equipment funded with federal research and development dollars, as provided by the Health System, consisted of 9 items with a total historical cost of $105k. Cause The Health System lacks a process to ensure that policies and procedures related to identifying and managing its federally purchased fixed assets in accordance with 2 CFR section 200.313 are followed, including updating property records to include all required data elements and the performance of a physical inventory at least once every two years. Effect The Health System's accounting records for its federally purchased fixed assets could be inaccurate as the Health System has not formally verified the existence, current utilization and continued need for the equipment through this physical inventory process. Additionally, without maintaining tag numbers and records of asset locations, safeguarding of assets could be impacted. Questioned Costs None noted. Recommendation We recommend that the Health System implement a process to ensure its policies and procedures over equipment management are followed, including the performance of a physical inventory of federally purchased fixed assets at least once every two years in accordance with 2 CFR section 200.313(d)(2), and updating its property records to include all details required by 2 CFR section 200.313(d)(1). Management?s Views and Corrective Action Plan Management?s Views and Corrective Action Plan is included at the end of this report after the summary schedule of prior audit findings and status.

FY End: 2022-06-30
Dartmouth-Hitchcock Health and Subsidiaries
Compliance Requirement: F
Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records...

Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records must be maintained that include a description of the property, a serial number or other identification number, the source of funding for the property (including the FAIN), who holds title, the acquisition date, and cost of the property, percentage of Federal participation in the project costs for the Federal award under which the property was acquired, the location, use and condition of the property, and any ultimate disposition data including the date of disposal and sale price of the property. (2) A physical inventory of the property must be taken and the results reconciled with the property records at least once every two years. (3) A control system must be developed to ensure adequate safeguards to prevent loss, damage, or theft of the property. Any loss, damage, or theft must be investigated. (4) Adequate maintenance procedures must be developed to keep the property in good condition. (5) If the non-Federal entity is authorized or required to sell the property, proper sales procedures must be established to ensure the highest possible return. Condition The Health System did not perform a physical inventory of federally purchased fixed assets at least once during the last two years. Additionally, the federal asset listing did not specify all of the details required by 2 CFR section 200.313 (d) (1) such as asset locations, tag numbers, use and condition. The full population of equipment funded with federal research and development dollars, as provided by the Health System, consisted of 9 items with a total historical cost of $105k. Cause The Health System lacks a process to ensure that policies and procedures related to identifying and managing its federally purchased fixed assets in accordance with 2 CFR section 200.313 are followed, including updating property records to include all required data elements and the performance of a physical inventory at least once every two years. Effect The Health System's accounting records for its federally purchased fixed assets could be inaccurate as the Health System has not formally verified the existence, current utilization and continued need for the equipment through this physical inventory process. Additionally, without maintaining tag numbers and records of asset locations, safeguarding of assets could be impacted. Questioned Costs None noted. Recommendation We recommend that the Health System implement a process to ensure its policies and procedures over equipment management are followed, including the performance of a physical inventory of federally purchased fixed assets at least once every two years in accordance with 2 CFR section 200.313(d)(2), and updating its property records to include all details required by 2 CFR section 200.313(d)(1). Management?s Views and Corrective Action Plan Management?s Views and Corrective Action Plan is included at the end of this report after the summary schedule of prior audit findings and status.

FY End: 2022-06-30
Dartmouth-Hitchcock Health and Subsidiaries
Compliance Requirement: F
Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records...

Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records must be maintained that include a description of the property, a serial number or other identification number, the source of funding for the property (including the FAIN), who holds title, the acquisition date, and cost of the property, percentage of Federal participation in the project costs for the Federal award under which the property was acquired, the location, use and condition of the property, and any ultimate disposition data including the date of disposal and sale price of the property. (2) A physical inventory of the property must be taken and the results reconciled with the property records at least once every two years. (3) A control system must be developed to ensure adequate safeguards to prevent loss, damage, or theft of the property. Any loss, damage, or theft must be investigated. (4) Adequate maintenance procedures must be developed to keep the property in good condition. (5) If the non-Federal entity is authorized or required to sell the property, proper sales procedures must be established to ensure the highest possible return. Condition The Health System did not perform a physical inventory of federally purchased fixed assets at least once during the last two years. Additionally, the federal asset listing did not specify all of the details required by 2 CFR section 200.313 (d) (1) such as asset locations, tag numbers, use and condition. The full population of equipment funded with federal research and development dollars, as provided by the Health System, consisted of 9 items with a total historical cost of $105k. Cause The Health System lacks a process to ensure that policies and procedures related to identifying and managing its federally purchased fixed assets in accordance with 2 CFR section 200.313 are followed, including updating property records to include all required data elements and the performance of a physical inventory at least once every two years. Effect The Health System's accounting records for its federally purchased fixed assets could be inaccurate as the Health System has not formally verified the existence, current utilization and continued need for the equipment through this physical inventory process. Additionally, without maintaining tag numbers and records of asset locations, safeguarding of assets could be impacted. Questioned Costs None noted. Recommendation We recommend that the Health System implement a process to ensure its policies and procedures over equipment management are followed, including the performance of a physical inventory of federally purchased fixed assets at least once every two years in accordance with 2 CFR section 200.313(d)(2), and updating its property records to include all details required by 2 CFR section 200.313(d)(1). Management?s Views and Corrective Action Plan Management?s Views and Corrective Action Plan is included at the end of this report after the summary schedule of prior audit findings and status.

FY End: 2022-06-30
Dartmouth-Hitchcock Health and Subsidiaries
Compliance Requirement: F
Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records...

Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records must be maintained that include a description of the property, a serial number or other identification number, the source of funding for the property (including the FAIN), who holds title, the acquisition date, and cost of the property, percentage of Federal participation in the project costs for the Federal award under which the property was acquired, the location, use and condition of the property, and any ultimate disposition data including the date of disposal and sale price of the property. (2) A physical inventory of the property must be taken and the results reconciled with the property records at least once every two years. (3) A control system must be developed to ensure adequate safeguards to prevent loss, damage, or theft of the property. Any loss, damage, or theft must be investigated. (4) Adequate maintenance procedures must be developed to keep the property in good condition. (5) If the non-Federal entity is authorized or required to sell the property, proper sales procedures must be established to ensure the highest possible return. Condition The Health System did not perform a physical inventory of federally purchased fixed assets at least once during the last two years. Additionally, the federal asset listing did not specify all of the details required by 2 CFR section 200.313 (d) (1) such as asset locations, tag numbers, use and condition. The full population of equipment funded with federal research and development dollars, as provided by the Health System, consisted of 9 items with a total historical cost of $105k. Cause The Health System lacks a process to ensure that policies and procedures related to identifying and managing its federally purchased fixed assets in accordance with 2 CFR section 200.313 are followed, including updating property records to include all required data elements and the performance of a physical inventory at least once every two years. Effect The Health System's accounting records for its federally purchased fixed assets could be inaccurate as the Health System has not formally verified the existence, current utilization and continued need for the equipment through this physical inventory process. Additionally, without maintaining tag numbers and records of asset locations, safeguarding of assets could be impacted. Questioned Costs None noted. Recommendation We recommend that the Health System implement a process to ensure its policies and procedures over equipment management are followed, including the performance of a physical inventory of federally purchased fixed assets at least once every two years in accordance with 2 CFR section 200.313(d)(2), and updating its property records to include all details required by 2 CFR section 200.313(d)(1). Management?s Views and Corrective Action Plan Management?s Views and Corrective Action Plan is included at the end of this report after the summary schedule of prior audit findings and status.

FY End: 2022-06-30
Dartmouth-Hitchcock Health and Subsidiaries
Compliance Requirement: F
Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records...

Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records must be maintained that include a description of the property, a serial number or other identification number, the source of funding for the property (including the FAIN), who holds title, the acquisition date, and cost of the property, percentage of Federal participation in the project costs for the Federal award under which the property was acquired, the location, use and condition of the property, and any ultimate disposition data including the date of disposal and sale price of the property. (2) A physical inventory of the property must be taken and the results reconciled with the property records at least once every two years. (3) A control system must be developed to ensure adequate safeguards to prevent loss, damage, or theft of the property. Any loss, damage, or theft must be investigated. (4) Adequate maintenance procedures must be developed to keep the property in good condition. (5) If the non-Federal entity is authorized or required to sell the property, proper sales procedures must be established to ensure the highest possible return. Condition The Health System did not perform a physical inventory of federally purchased fixed assets at least once during the last two years. Additionally, the federal asset listing did not specify all of the details required by 2 CFR section 200.313 (d) (1) such as asset locations, tag numbers, use and condition. The full population of equipment funded with federal research and development dollars, as provided by the Health System, consisted of 9 items with a total historical cost of $105k. Cause The Health System lacks a process to ensure that policies and procedures related to identifying and managing its federally purchased fixed assets in accordance with 2 CFR section 200.313 are followed, including updating property records to include all required data elements and the performance of a physical inventory at least once every two years. Effect The Health System's accounting records for its federally purchased fixed assets could be inaccurate as the Health System has not formally verified the existence, current utilization and continued need for the equipment through this physical inventory process. Additionally, without maintaining tag numbers and records of asset locations, safeguarding of assets could be impacted. Questioned Costs None noted. Recommendation We recommend that the Health System implement a process to ensure its policies and procedures over equipment management are followed, including the performance of a physical inventory of federally purchased fixed assets at least once every two years in accordance with 2 CFR section 200.313(d)(2), and updating its property records to include all details required by 2 CFR section 200.313(d)(1). Management?s Views and Corrective Action Plan Management?s Views and Corrective Action Plan is included at the end of this report after the summary schedule of prior audit findings and status.

FY End: 2022-06-30
Dartmouth-Hitchcock Health and Subsidiaries
Compliance Requirement: F
Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records...

Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records must be maintained that include a description of the property, a serial number or other identification number, the source of funding for the property (including the FAIN), who holds title, the acquisition date, and cost of the property, percentage of Federal participation in the project costs for the Federal award under which the property was acquired, the location, use and condition of the property, and any ultimate disposition data including the date of disposal and sale price of the property. (2) A physical inventory of the property must be taken and the results reconciled with the property records at least once every two years. (3) A control system must be developed to ensure adequate safeguards to prevent loss, damage, or theft of the property. Any loss, damage, or theft must be investigated. (4) Adequate maintenance procedures must be developed to keep the property in good condition. (5) If the non-Federal entity is authorized or required to sell the property, proper sales procedures must be established to ensure the highest possible return. Condition The Health System did not perform a physical inventory of federally purchased fixed assets at least once during the last two years. Additionally, the federal asset listing did not specify all of the details required by 2 CFR section 200.313 (d) (1) such as asset locations, tag numbers, use and condition. The full population of equipment funded with federal research and development dollars, as provided by the Health System, consisted of 9 items with a total historical cost of $105k. Cause The Health System lacks a process to ensure that policies and procedures related to identifying and managing its federally purchased fixed assets in accordance with 2 CFR section 200.313 are followed, including updating property records to include all required data elements and the performance of a physical inventory at least once every two years. Effect The Health System's accounting records for its federally purchased fixed assets could be inaccurate as the Health System has not formally verified the existence, current utilization and continued need for the equipment through this physical inventory process. Additionally, without maintaining tag numbers and records of asset locations, safeguarding of assets could be impacted. Questioned Costs None noted. Recommendation We recommend that the Health System implement a process to ensure its policies and procedures over equipment management are followed, including the performance of a physical inventory of federally purchased fixed assets at least once every two years in accordance with 2 CFR section 200.313(d)(2), and updating its property records to include all details required by 2 CFR section 200.313(d)(1). Management?s Views and Corrective Action Plan Management?s Views and Corrective Action Plan is included at the end of this report after the summary schedule of prior audit findings and status.

FY End: 2022-06-30
Dartmouth-Hitchcock Health and Subsidiaries
Compliance Requirement: F
Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records...

Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records must be maintained that include a description of the property, a serial number or other identification number, the source of funding for the property (including the FAIN), who holds title, the acquisition date, and cost of the property, percentage of Federal participation in the project costs for the Federal award under which the property was acquired, the location, use and condition of the property, and any ultimate disposition data including the date of disposal and sale price of the property. (2) A physical inventory of the property must be taken and the results reconciled with the property records at least once every two years. (3) A control system must be developed to ensure adequate safeguards to prevent loss, damage, or theft of the property. Any loss, damage, or theft must be investigated. (4) Adequate maintenance procedures must be developed to keep the property in good condition. (5) If the non-Federal entity is authorized or required to sell the property, proper sales procedures must be established to ensure the highest possible return. Condition The Health System did not perform a physical inventory of federally purchased fixed assets at least once during the last two years. Additionally, the federal asset listing did not specify all of the details required by 2 CFR section 200.313 (d) (1) such as asset locations, tag numbers, use and condition. The full population of equipment funded with federal research and development dollars, as provided by the Health System, consisted of 9 items with a total historical cost of $105k. Cause The Health System lacks a process to ensure that policies and procedures related to identifying and managing its federally purchased fixed assets in accordance with 2 CFR section 200.313 are followed, including updating property records to include all required data elements and the performance of a physical inventory at least once every two years. Effect The Health System's accounting records for its federally purchased fixed assets could be inaccurate as the Health System has not formally verified the existence, current utilization and continued need for the equipment through this physical inventory process. Additionally, without maintaining tag numbers and records of asset locations, safeguarding of assets could be impacted. Questioned Costs None noted. Recommendation We recommend that the Health System implement a process to ensure its policies and procedures over equipment management are followed, including the performance of a physical inventory of federally purchased fixed assets at least once every two years in accordance with 2 CFR section 200.313(d)(2), and updating its property records to include all details required by 2 CFR section 200.313(d)(1). Management?s Views and Corrective Action Plan Management?s Views and Corrective Action Plan is included at the end of this report after the summary schedule of prior audit findings and status.

FY End: 2022-06-30
Dartmouth-Hitchcock Health and Subsidiaries
Compliance Requirement: F
Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records...

Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records must be maintained that include a description of the property, a serial number or other identification number, the source of funding for the property (including the FAIN), who holds title, the acquisition date, and cost of the property, percentage of Federal participation in the project costs for the Federal award under which the property was acquired, the location, use and condition of the property, and any ultimate disposition data including the date of disposal and sale price of the property. (2) A physical inventory of the property must be taken and the results reconciled with the property records at least once every two years. (3) A control system must be developed to ensure adequate safeguards to prevent loss, damage, or theft of the property. Any loss, damage, or theft must be investigated. (4) Adequate maintenance procedures must be developed to keep the property in good condition. (5) If the non-Federal entity is authorized or required to sell the property, proper sales procedures must be established to ensure the highest possible return. Condition The Health System did not perform a physical inventory of federally purchased fixed assets at least once during the last two years. Additionally, the federal asset listing did not specify all of the details required by 2 CFR section 200.313 (d) (1) such as asset locations, tag numbers, use and condition. The full population of equipment funded with federal research and development dollars, as provided by the Health System, consisted of 9 items with a total historical cost of $105k. Cause The Health System lacks a process to ensure that policies and procedures related to identifying and managing its federally purchased fixed assets in accordance with 2 CFR section 200.313 are followed, including updating property records to include all required data elements and the performance of a physical inventory at least once every two years. Effect The Health System's accounting records for its federally purchased fixed assets could be inaccurate as the Health System has not formally verified the existence, current utilization and continued need for the equipment through this physical inventory process. Additionally, without maintaining tag numbers and records of asset locations, safeguarding of assets could be impacted. Questioned Costs None noted. Recommendation We recommend that the Health System implement a process to ensure its policies and procedures over equipment management are followed, including the performance of a physical inventory of federally purchased fixed assets at least once every two years in accordance with 2 CFR section 200.313(d)(2), and updating its property records to include all details required by 2 CFR section 200.313(d)(1). Management?s Views and Corrective Action Plan Management?s Views and Corrective Action Plan is included at the end of this report after the summary schedule of prior audit findings and status.

FY End: 2022-06-30
Dartmouth-Hitchcock Health and Subsidiaries
Compliance Requirement: F
Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records...

Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records must be maintained that include a description of the property, a serial number or other identification number, the source of funding for the property (including the FAIN), who holds title, the acquisition date, and cost of the property, percentage of Federal participation in the project costs for the Federal award under which the property was acquired, the location, use and condition of the property, and any ultimate disposition data including the date of disposal and sale price of the property. (2) A physical inventory of the property must be taken and the results reconciled with the property records at least once every two years. (3) A control system must be developed to ensure adequate safeguards to prevent loss, damage, or theft of the property. Any loss, damage, or theft must be investigated. (4) Adequate maintenance procedures must be developed to keep the property in good condition. (5) If the non-Federal entity is authorized or required to sell the property, proper sales procedures must be established to ensure the highest possible return. Condition The Health System did not perform a physical inventory of federally purchased fixed assets at least once during the last two years. Additionally, the federal asset listing did not specify all of the details required by 2 CFR section 200.313 (d) (1) such as asset locations, tag numbers, use and condition. The full population of equipment funded with federal research and development dollars, as provided by the Health System, consisted of 9 items with a total historical cost of $105k. Cause The Health System lacks a process to ensure that policies and procedures related to identifying and managing its federally purchased fixed assets in accordance with 2 CFR section 200.313 are followed, including updating property records to include all required data elements and the performance of a physical inventory at least once every two years. Effect The Health System's accounting records for its federally purchased fixed assets could be inaccurate as the Health System has not formally verified the existence, current utilization and continued need for the equipment through this physical inventory process. Additionally, without maintaining tag numbers and records of asset locations, safeguarding of assets could be impacted. Questioned Costs None noted. Recommendation We recommend that the Health System implement a process to ensure its policies and procedures over equipment management are followed, including the performance of a physical inventory of federally purchased fixed assets at least once every two years in accordance with 2 CFR section 200.313(d)(2), and updating its property records to include all details required by 2 CFR section 200.313(d)(1). Management?s Views and Corrective Action Plan Management?s Views and Corrective Action Plan is included at the end of this report after the summary schedule of prior audit findings and status.

FY End: 2022-06-30
Dartmouth-Hitchcock Health and Subsidiaries
Compliance Requirement: F
Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records...

Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records must be maintained that include a description of the property, a serial number or other identification number, the source of funding for the property (including the FAIN), who holds title, the acquisition date, and cost of the property, percentage of Federal participation in the project costs for the Federal award under which the property was acquired, the location, use and condition of the property, and any ultimate disposition data including the date of disposal and sale price of the property. (2) A physical inventory of the property must be taken and the results reconciled with the property records at least once every two years. (3) A control system must be developed to ensure adequate safeguards to prevent loss, damage, or theft of the property. Any loss, damage, or theft must be investigated. (4) Adequate maintenance procedures must be developed to keep the property in good condition. (5) If the non-Federal entity is authorized or required to sell the property, proper sales procedures must be established to ensure the highest possible return. Condition The Health System did not perform a physical inventory of federally purchased fixed assets at least once during the last two years. Additionally, the federal asset listing did not specify all of the details required by 2 CFR section 200.313 (d) (1) such as asset locations, tag numbers, use and condition. The full population of equipment funded with federal research and development dollars, as provided by the Health System, consisted of 9 items with a total historical cost of $105k. Cause The Health System lacks a process to ensure that policies and procedures related to identifying and managing its federally purchased fixed assets in accordance with 2 CFR section 200.313 are followed, including updating property records to include all required data elements and the performance of a physical inventory at least once every two years. Effect The Health System's accounting records for its federally purchased fixed assets could be inaccurate as the Health System has not formally verified the existence, current utilization and continued need for the equipment through this physical inventory process. Additionally, without maintaining tag numbers and records of asset locations, safeguarding of assets could be impacted. Questioned Costs None noted. Recommendation We recommend that the Health System implement a process to ensure its policies and procedures over equipment management are followed, including the performance of a physical inventory of federally purchased fixed assets at least once every two years in accordance with 2 CFR section 200.313(d)(2), and updating its property records to include all details required by 2 CFR section 200.313(d)(1). Management?s Views and Corrective Action Plan Management?s Views and Corrective Action Plan is included at the end of this report after the summary schedule of prior audit findings and status.

FY End: 2022-06-30
Stevens Institute of Technology
Compliance Requirement: F
Finding No. 2022-003 Research and Development Cluster: U.S. Department of Defense: Improved Ventilation of the Edematous Lung, Assistance Listing 93.838 (award number: 1R01HL113577-01A1) Statistically valid sample: No and it was not intended to be. Repeat finding: This is a repeat finding from the prior year single audit report (finding no. 2021-002). Compliance Requirement ? Equipment and Real Property ? Significant Deficiency and Noncompliance Criteria Per guidance included in 2 CFR part 200.3...

Finding No. 2022-003 Research and Development Cluster: U.S. Department of Defense: Improved Ventilation of the Edematous Lung, Assistance Listing 93.838 (award number: 1R01HL113577-01A1) Statistically valid sample: No and it was not intended to be. Repeat finding: This is a repeat finding from the prior year single audit report (finding no. 2021-002). Compliance Requirement ? Equipment and Real Property ? Significant Deficiency and Noncompliance Criteria Per guidance included in 2 CFR part 200.313, non-Federal entities other than States must follow regulations which require that: Property records must be maintained that include a description of the property, a serial number or other identification number, the source of funding for the property (including the Federal award identification number), who holds title, the acquisition date, cost of the property, percentage of Federal participation in the project costs for the Federal award under which the property was acquired, the location, use and condition of the property, and any ultimate disposition data including the date of disposal and sales price of the property. Further, the non-Federal entity must establish and maintain an effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with Federal statutes, regulations, and terms and conditions of the Federal award (2 CFR 200.303). Condition and Context Utilizing the listing of equipment additions provided by the Plant Fund manager, the Fixed Asset Specialist schedules a visit with the asset custodian to identify and tag the equipment. This process consists of affixing a barcode asset tag to the equipment. After tagging the equipment, the Fixed Asset Specialist will create an entry in Kuali. This entry will automatically generate a unique asset number in Kuali, for which, the Fixed Asset Specialist will then add all the required data related to that asset, including the tag number. We selected twenty-five pieces of equipment and noted for one selection, the asset?s tag was not included in the Kuali Asset Management System, therefore the property records were not accurate. Cause Management did not properly ensure that the tag number was included within fixed asset management system. Effect The University may not be able to properly identify equipment funded with federal awards to ensure proper inventorying, safeguarding, and maintenance. Questioned Costs There are no questioned costs associated with this finding as the equipment was within the University?s possession. Recommendation The University should strengthen its policies and procedures related to maintaining property records and tagging equipment. Views of Responsible Official Management agrees with the recommendation. The University will ensure that each individual fixed asset is appropriately tagged and that the information for the asset reconciles to the information reported in the Stevens Kuali Financial System. The Division of Finance has instituted an additional procedure to generate monthly asset tagging reports to address this issue and ensure that all assets are tagged in a timely manner. In addition, the Staff Accountant takes a picture of the asset tag for new assets which is attached to the supporting documentation in the Kuali Financial System. The Senior Accountant reviews the documentation for each asset and ensures that the appropriate asset tag is reflected in the Kuali Financial System. The Division of Finance engages an outside firm to conduct a complete physical inventory every two years. The Executive Director of Finance and Controller, the Senior Accountant and the Staff Accountant will ensure that all asset records are properly reflected in the Kuali Financial System.

FY End: 2022-06-30
Madison Consolidated Schools
Compliance Requirement: F
FINDING 2022-007 Subject: COVID-19 - Education Stabilization Fund - Equipment and Real Property Management Federal Agency: Department of Education Federal Program: COVID-19 - Education Stabilization Fund Assistance Listings Number: 84.425U Federal Award Number and Year (or Other Identifying Number): S425U210013 Pass-Through Entity: Indiana Department of Education Compliance Requirement: Equipment and Real Property Management Audit Findings: Material Weakness, Other Matters Condition and Context ...

FINDING 2022-007 Subject: COVID-19 - Education Stabilization Fund - Equipment and Real Property Management Federal Agency: Department of Education Federal Program: COVID-19 - Education Stabilization Fund Assistance Listings Number: 84.425U Federal Award Number and Year (or Other Identifying Number): S425U210013 Pass-Through Entity: Indiana Department of Education Compliance Requirement: Equipment and Real Property Management Audit Findings: Material Weakness, Other Matters Condition and Context An effective internal control system was not in place at the School Corporation to ensure compliance with requirements related to the grant agreement and the Equipment and Real Property Management compliance requirement. The School Corporation had not designed, nor implemented a system of internal control over the addition of assets to the capital asset ledger. One employee was responsible for the preparation of the capital asset ledger, and the maintenance of the property records and required information, without a documented review or oversight process in place to detect and allow correction of errors. Three construction projects initiated in the audit period were paid with ESSER grant funds. These projects were all partially completed during the audit period and pay applications were paid on all three projects. However, two of the three projects were not included in Construction in Progress on the School Corporation's capital asset ledger. Additionally, the School Corporation did not have a control process in place to ensure that a physical inventory was performed at least biannually. The School Corporation's last physical asset inventory was taken in 2018. The lack of internal controls and noncompliance were systemic issues throughout the audit period. Criteria 2 CFR 200.303 states in part: "The non-Federal entity must: (a) Establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with Federal statutes, regulations, and the terms and conditions of the Federal award. These internal controls should be in compliance with guidance in 'Standards for Internal Control in the Federal Government' issued by the Comptroller General of the United States or the 'Internal Control Integrated Framework', issued by the Committee of Sponsoring Organizations of the Treadway Commission (COSO). . . ." 2 CFR 200.313(d) states in part: "Management requirements. Procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, as a minimum, meet the following requirements: (1) Property records must be maintained that include a description of the property, a serial number or other identification number, the source of funding for the property (including the FAIN), who holds title, the acquisition date, and cost of the property, percentage of Federal participation in the project costs for the Federal award under which the property was acquired, the location, use and condition of the property, and any ultimate disposition data including the date of disposal and sale price of the property. (2) A physical inventory of the property must be taken and the results reconciled with the property records at least once every two years. (3) A control system must be developed to ensure adequate safeguards to prevent loss, damage, or theft of the property. Any loss, damage, or theft must be investigated. . . ." Cause Management had not developed, nor implemented a system of internal control that would have ensured compliance with the grant agreement and the Equipment and Real Property Management compliance requirement. Effect The failure to establish an effective internal control system enabled material noncompliance to go undetected. Noncompliance with the grant agreement and the Equipment and Real Property Management compliance requirement could result in the loss of future federal funds to the School Corporation. Questioned Costs There were no questioned costs identified. Recommendation We recommended that the School Corporation's management establish a system of internal control related to the grant agreement and the Equipment and Real Property Management compliance. Views of Responsible Officials For the views of responsible officials, refer to the Corrective Action Plan that is part of this report.

FY End: 2022-06-30
Dartmouth-Hitchcock Health and Subsidiaries
Compliance Requirement: F
Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records...

Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records must be maintained that include a description of the property, a serial number or other identification number, the source of funding for the property (including the FAIN), who holds title, the acquisition date, and cost of the property, percentage of Federal participation in the project costs for the Federal award under which the property was acquired, the location, use and condition of the property, and any ultimate disposition data including the date of disposal and sale price of the property. (2) A physical inventory of the property must be taken and the results reconciled with the property records at least once every two years. (3) A control system must be developed to ensure adequate safeguards to prevent loss, damage, or theft of the property. Any loss, damage, or theft must be investigated. (4) Adequate maintenance procedures must be developed to keep the property in good condition. (5) If the non-Federal entity is authorized or required to sell the property, proper sales procedures must be established to ensure the highest possible return. Condition The Health System did not perform a physical inventory of federally purchased fixed assets at least once during the last two years. Additionally, the federal asset listing did not specify all of the details required by 2 CFR section 200.313 (d) (1) such as asset locations, tag numbers, use and condition. The full population of equipment funded with federal research and development dollars, as provided by the Health System, consisted of 9 items with a total historical cost of $105k. Cause The Health System lacks a process to ensure that policies and procedures related to identifying and managing its federally purchased fixed assets in accordance with 2 CFR section 200.313 are followed, including updating property records to include all required data elements and the performance of a physical inventory at least once every two years. Effect The Health System's accounting records for its federally purchased fixed assets could be inaccurate as the Health System has not formally verified the existence, current utilization and continued need for the equipment through this physical inventory process. Additionally, without maintaining tag numbers and records of asset locations, safeguarding of assets could be impacted. Questioned Costs None noted. Recommendation We recommend that the Health System implement a process to ensure its policies and procedures over equipment management are followed, including the performance of a physical inventory of federally purchased fixed assets at least once every two years in accordance with 2 CFR section 200.313(d)(2), and updating its property records to include all details required by 2 CFR section 200.313(d)(1). Management?s Views and Corrective Action Plan Management?s Views and Corrective Action Plan is included at the end of this report after the summary schedule of prior audit findings and status.

FY End: 2022-06-30
Dartmouth-Hitchcock Health and Subsidiaries
Compliance Requirement: F
Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records...

Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records must be maintained that include a description of the property, a serial number or other identification number, the source of funding for the property (including the FAIN), who holds title, the acquisition date, and cost of the property, percentage of Federal participation in the project costs for the Federal award under which the property was acquired, the location, use and condition of the property, and any ultimate disposition data including the date of disposal and sale price of the property. (2) A physical inventory of the property must be taken and the results reconciled with the property records at least once every two years. (3) A control system must be developed to ensure adequate safeguards to prevent loss, damage, or theft of the property. Any loss, damage, or theft must be investigated. (4) Adequate maintenance procedures must be developed to keep the property in good condition. (5) If the non-Federal entity is authorized or required to sell the property, proper sales procedures must be established to ensure the highest possible return. Condition The Health System did not perform a physical inventory of federally purchased fixed assets at least once during the last two years. Additionally, the federal asset listing did not specify all of the details required by 2 CFR section 200.313 (d) (1) such as asset locations, tag numbers, use and condition. The full population of equipment funded with federal research and development dollars, as provided by the Health System, consisted of 9 items with a total historical cost of $105k. Cause The Health System lacks a process to ensure that policies and procedures related to identifying and managing its federally purchased fixed assets in accordance with 2 CFR section 200.313 are followed, including updating property records to include all required data elements and the performance of a physical inventory at least once every two years. Effect The Health System's accounting records for its federally purchased fixed assets could be inaccurate as the Health System has not formally verified the existence, current utilization and continued need for the equipment through this physical inventory process. Additionally, without maintaining tag numbers and records of asset locations, safeguarding of assets could be impacted. Questioned Costs None noted. Recommendation We recommend that the Health System implement a process to ensure its policies and procedures over equipment management are followed, including the performance of a physical inventory of federally purchased fixed assets at least once every two years in accordance with 2 CFR section 200.313(d)(2), and updating its property records to include all details required by 2 CFR section 200.313(d)(1). Management?s Views and Corrective Action Plan Management?s Views and Corrective Action Plan is included at the end of this report after the summary schedule of prior audit findings and status.

FY End: 2022-06-30
Dartmouth-Hitchcock Health and Subsidiaries
Compliance Requirement: F
Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records...

Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records must be maintained that include a description of the property, a serial number or other identification number, the source of funding for the property (including the FAIN), who holds title, the acquisition date, and cost of the property, percentage of Federal participation in the project costs for the Federal award under which the property was acquired, the location, use and condition of the property, and any ultimate disposition data including the date of disposal and sale price of the property. (2) A physical inventory of the property must be taken and the results reconciled with the property records at least once every two years. (3) A control system must be developed to ensure adequate safeguards to prevent loss, damage, or theft of the property. Any loss, damage, or theft must be investigated. (4) Adequate maintenance procedures must be developed to keep the property in good condition. (5) If the non-Federal entity is authorized or required to sell the property, proper sales procedures must be established to ensure the highest possible return. Condition The Health System did not perform a physical inventory of federally purchased fixed assets at least once during the last two years. Additionally, the federal asset listing did not specify all of the details required by 2 CFR section 200.313 (d) (1) such as asset locations, tag numbers, use and condition. The full population of equipment funded with federal research and development dollars, as provided by the Health System, consisted of 9 items with a total historical cost of $105k. Cause The Health System lacks a process to ensure that policies and procedures related to identifying and managing its federally purchased fixed assets in accordance with 2 CFR section 200.313 are followed, including updating property records to include all required data elements and the performance of a physical inventory at least once every two years. Effect The Health System's accounting records for its federally purchased fixed assets could be inaccurate as the Health System has not formally verified the existence, current utilization and continued need for the equipment through this physical inventory process. Additionally, without maintaining tag numbers and records of asset locations, safeguarding of assets could be impacted. Questioned Costs None noted. Recommendation We recommend that the Health System implement a process to ensure its policies and procedures over equipment management are followed, including the performance of a physical inventory of federally purchased fixed assets at least once every two years in accordance with 2 CFR section 200.313(d)(2), and updating its property records to include all details required by 2 CFR section 200.313(d)(1). Management?s Views and Corrective Action Plan Management?s Views and Corrective Action Plan is included at the end of this report after the summary schedule of prior audit findings and status.

FY End: 2022-06-30
Dartmouth-Hitchcock Health and Subsidiaries
Compliance Requirement: F
Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records...

Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records must be maintained that include a description of the property, a serial number or other identification number, the source of funding for the property (including the FAIN), who holds title, the acquisition date, and cost of the property, percentage of Federal participation in the project costs for the Federal award under which the property was acquired, the location, use and condition of the property, and any ultimate disposition data including the date of disposal and sale price of the property. (2) A physical inventory of the property must be taken and the results reconciled with the property records at least once every two years. (3) A control system must be developed to ensure adequate safeguards to prevent loss, damage, or theft of the property. Any loss, damage, or theft must be investigated. (4) Adequate maintenance procedures must be developed to keep the property in good condition. (5) If the non-Federal entity is authorized or required to sell the property, proper sales procedures must be established to ensure the highest possible return. Condition The Health System did not perform a physical inventory of federally purchased fixed assets at least once during the last two years. Additionally, the federal asset listing did not specify all of the details required by 2 CFR section 200.313 (d) (1) such as asset locations, tag numbers, use and condition. The full population of equipment funded with federal research and development dollars, as provided by the Health System, consisted of 9 items with a total historical cost of $105k. Cause The Health System lacks a process to ensure that policies and procedures related to identifying and managing its federally purchased fixed assets in accordance with 2 CFR section 200.313 are followed, including updating property records to include all required data elements and the performance of a physical inventory at least once every two years. Effect The Health System's accounting records for its federally purchased fixed assets could be inaccurate as the Health System has not formally verified the existence, current utilization and continued need for the equipment through this physical inventory process. Additionally, without maintaining tag numbers and records of asset locations, safeguarding of assets could be impacted. Questioned Costs None noted. Recommendation We recommend that the Health System implement a process to ensure its policies and procedures over equipment management are followed, including the performance of a physical inventory of federally purchased fixed assets at least once every two years in accordance with 2 CFR section 200.313(d)(2), and updating its property records to include all details required by 2 CFR section 200.313(d)(1). Management?s Views and Corrective Action Plan Management?s Views and Corrective Action Plan is included at the end of this report after the summary schedule of prior audit findings and status.

FY End: 2022-06-30
Dartmouth-Hitchcock Health and Subsidiaries
Compliance Requirement: F
Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records...

Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records must be maintained that include a description of the property, a serial number or other identification number, the source of funding for the property (including the FAIN), who holds title, the acquisition date, and cost of the property, percentage of Federal participation in the project costs for the Federal award under which the property was acquired, the location, use and condition of the property, and any ultimate disposition data including the date of disposal and sale price of the property. (2) A physical inventory of the property must be taken and the results reconciled with the property records at least once every two years. (3) A control system must be developed to ensure adequate safeguards to prevent loss, damage, or theft of the property. Any loss, damage, or theft must be investigated. (4) Adequate maintenance procedures must be developed to keep the property in good condition. (5) If the non-Federal entity is authorized or required to sell the property, proper sales procedures must be established to ensure the highest possible return. Condition The Health System did not perform a physical inventory of federally purchased fixed assets at least once during the last two years. Additionally, the federal asset listing did not specify all of the details required by 2 CFR section 200.313 (d) (1) such as asset locations, tag numbers, use and condition. The full population of equipment funded with federal research and development dollars, as provided by the Health System, consisted of 9 items with a total historical cost of $105k. Cause The Health System lacks a process to ensure that policies and procedures related to identifying and managing its federally purchased fixed assets in accordance with 2 CFR section 200.313 are followed, including updating property records to include all required data elements and the performance of a physical inventory at least once every two years. Effect The Health System's accounting records for its federally purchased fixed assets could be inaccurate as the Health System has not formally verified the existence, current utilization and continued need for the equipment through this physical inventory process. Additionally, without maintaining tag numbers and records of asset locations, safeguarding of assets could be impacted. Questioned Costs None noted. Recommendation We recommend that the Health System implement a process to ensure its policies and procedures over equipment management are followed, including the performance of a physical inventory of federally purchased fixed assets at least once every two years in accordance with 2 CFR section 200.313(d)(2), and updating its property records to include all details required by 2 CFR section 200.313(d)(1). Management?s Views and Corrective Action Plan Management?s Views and Corrective Action Plan is included at the end of this report after the summary schedule of prior audit findings and status.

FY End: 2022-06-30
Dartmouth-Hitchcock Health and Subsidiaries
Compliance Requirement: F
Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records...

Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records must be maintained that include a description of the property, a serial number or other identification number, the source of funding for the property (including the FAIN), who holds title, the acquisition date, and cost of the property, percentage of Federal participation in the project costs for the Federal award under which the property was acquired, the location, use and condition of the property, and any ultimate disposition data including the date of disposal and sale price of the property. (2) A physical inventory of the property must be taken and the results reconciled with the property records at least once every two years. (3) A control system must be developed to ensure adequate safeguards to prevent loss, damage, or theft of the property. Any loss, damage, or theft must be investigated. (4) Adequate maintenance procedures must be developed to keep the property in good condition. (5) If the non-Federal entity is authorized or required to sell the property, proper sales procedures must be established to ensure the highest possible return. Condition The Health System did not perform a physical inventory of federally purchased fixed assets at least once during the last two years. Additionally, the federal asset listing did not specify all of the details required by 2 CFR section 200.313 (d) (1) such as asset locations, tag numbers, use and condition. The full population of equipment funded with federal research and development dollars, as provided by the Health System, consisted of 9 items with a total historical cost of $105k. Cause The Health System lacks a process to ensure that policies and procedures related to identifying and managing its federally purchased fixed assets in accordance with 2 CFR section 200.313 are followed, including updating property records to include all required data elements and the performance of a physical inventory at least once every two years. Effect The Health System's accounting records for its federally purchased fixed assets could be inaccurate as the Health System has not formally verified the existence, current utilization and continued need for the equipment through this physical inventory process. Additionally, without maintaining tag numbers and records of asset locations, safeguarding of assets could be impacted. Questioned Costs None noted. Recommendation We recommend that the Health System implement a process to ensure its policies and procedures over equipment management are followed, including the performance of a physical inventory of federally purchased fixed assets at least once every two years in accordance with 2 CFR section 200.313(d)(2), and updating its property records to include all details required by 2 CFR section 200.313(d)(1). Management?s Views and Corrective Action Plan Management?s Views and Corrective Action Plan is included at the end of this report after the summary schedule of prior audit findings and status.

FY End: 2022-06-30
Dartmouth-Hitchcock Health and Subsidiaries
Compliance Requirement: F
Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records...

Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records must be maintained that include a description of the property, a serial number or other identification number, the source of funding for the property (including the FAIN), who holds title, the acquisition date, and cost of the property, percentage of Federal participation in the project costs for the Federal award under which the property was acquired, the location, use and condition of the property, and any ultimate disposition data including the date of disposal and sale price of the property. (2) A physical inventory of the property must be taken and the results reconciled with the property records at least once every two years. (3) A control system must be developed to ensure adequate safeguards to prevent loss, damage, or theft of the property. Any loss, damage, or theft must be investigated. (4) Adequate maintenance procedures must be developed to keep the property in good condition. (5) If the non-Federal entity is authorized or required to sell the property, proper sales procedures must be established to ensure the highest possible return. Condition The Health System did not perform a physical inventory of federally purchased fixed assets at least once during the last two years. Additionally, the federal asset listing did not specify all of the details required by 2 CFR section 200.313 (d) (1) such as asset locations, tag numbers, use and condition. The full population of equipment funded with federal research and development dollars, as provided by the Health System, consisted of 9 items with a total historical cost of $105k. Cause The Health System lacks a process to ensure that policies and procedures related to identifying and managing its federally purchased fixed assets in accordance with 2 CFR section 200.313 are followed, including updating property records to include all required data elements and the performance of a physical inventory at least once every two years. Effect The Health System's accounting records for its federally purchased fixed assets could be inaccurate as the Health System has not formally verified the existence, current utilization and continued need for the equipment through this physical inventory process. Additionally, without maintaining tag numbers and records of asset locations, safeguarding of assets could be impacted. Questioned Costs None noted. Recommendation We recommend that the Health System implement a process to ensure its policies and procedures over equipment management are followed, including the performance of a physical inventory of federally purchased fixed assets at least once every two years in accordance with 2 CFR section 200.313(d)(2), and updating its property records to include all details required by 2 CFR section 200.313(d)(1). Management?s Views and Corrective Action Plan Management?s Views and Corrective Action Plan is included at the end of this report after the summary schedule of prior audit findings and status.

FY End: 2022-06-30
Dartmouth-Hitchcock Health and Subsidiaries
Compliance Requirement: F
Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records...

Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records must be maintained that include a description of the property, a serial number or other identification number, the source of funding for the property (including the FAIN), who holds title, the acquisition date, and cost of the property, percentage of Federal participation in the project costs for the Federal award under which the property was acquired, the location, use and condition of the property, and any ultimate disposition data including the date of disposal and sale price of the property. (2) A physical inventory of the property must be taken and the results reconciled with the property records at least once every two years. (3) A control system must be developed to ensure adequate safeguards to prevent loss, damage, or theft of the property. Any loss, damage, or theft must be investigated. (4) Adequate maintenance procedures must be developed to keep the property in good condition. (5) If the non-Federal entity is authorized or required to sell the property, proper sales procedures must be established to ensure the highest possible return. Condition The Health System did not perform a physical inventory of federally purchased fixed assets at least once during the last two years. Additionally, the federal asset listing did not specify all of the details required by 2 CFR section 200.313 (d) (1) such as asset locations, tag numbers, use and condition. The full population of equipment funded with federal research and development dollars, as provided by the Health System, consisted of 9 items with a total historical cost of $105k. Cause The Health System lacks a process to ensure that policies and procedures related to identifying and managing its federally purchased fixed assets in accordance with 2 CFR section 200.313 are followed, including updating property records to include all required data elements and the performance of a physical inventory at least once every two years. Effect The Health System's accounting records for its federally purchased fixed assets could be inaccurate as the Health System has not formally verified the existence, current utilization and continued need for the equipment through this physical inventory process. Additionally, without maintaining tag numbers and records of asset locations, safeguarding of assets could be impacted. Questioned Costs None noted. Recommendation We recommend that the Health System implement a process to ensure its policies and procedures over equipment management are followed, including the performance of a physical inventory of federally purchased fixed assets at least once every two years in accordance with 2 CFR section 200.313(d)(2), and updating its property records to include all details required by 2 CFR section 200.313(d)(1). Management?s Views and Corrective Action Plan Management?s Views and Corrective Action Plan is included at the end of this report after the summary schedule of prior audit findings and status.

FY End: 2022-06-30
Dartmouth-Hitchcock Health and Subsidiaries
Compliance Requirement: F
Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records...

Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records must be maintained that include a description of the property, a serial number or other identification number, the source of funding for the property (including the FAIN), who holds title, the acquisition date, and cost of the property, percentage of Federal participation in the project costs for the Federal award under which the property was acquired, the location, use and condition of the property, and any ultimate disposition data including the date of disposal and sale price of the property. (2) A physical inventory of the property must be taken and the results reconciled with the property records at least once every two years. (3) A control system must be developed to ensure adequate safeguards to prevent loss, damage, or theft of the property. Any loss, damage, or theft must be investigated. (4) Adequate maintenance procedures must be developed to keep the property in good condition. (5) If the non-Federal entity is authorized or required to sell the property, proper sales procedures must be established to ensure the highest possible return. Condition The Health System did not perform a physical inventory of federally purchased fixed assets at least once during the last two years. Additionally, the federal asset listing did not specify all of the details required by 2 CFR section 200.313 (d) (1) such as asset locations, tag numbers, use and condition. The full population of equipment funded with federal research and development dollars, as provided by the Health System, consisted of 9 items with a total historical cost of $105k. Cause The Health System lacks a process to ensure that policies and procedures related to identifying and managing its federally purchased fixed assets in accordance with 2 CFR section 200.313 are followed, including updating property records to include all required data elements and the performance of a physical inventory at least once every two years. Effect The Health System's accounting records for its federally purchased fixed assets could be inaccurate as the Health System has not formally verified the existence, current utilization and continued need for the equipment through this physical inventory process. Additionally, without maintaining tag numbers and records of asset locations, safeguarding of assets could be impacted. Questioned Costs None noted. Recommendation We recommend that the Health System implement a process to ensure its policies and procedures over equipment management are followed, including the performance of a physical inventory of federally purchased fixed assets at least once every two years in accordance with 2 CFR section 200.313(d)(2), and updating its property records to include all details required by 2 CFR section 200.313(d)(1). Management?s Views and Corrective Action Plan Management?s Views and Corrective Action Plan is included at the end of this report after the summary schedule of prior audit findings and status.

FY End: 2022-06-30
Dartmouth-Hitchcock Health and Subsidiaries
Compliance Requirement: F
Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records...

Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records must be maintained that include a description of the property, a serial number or other identification number, the source of funding for the property (including the FAIN), who holds title, the acquisition date, and cost of the property, percentage of Federal participation in the project costs for the Federal award under which the property was acquired, the location, use and condition of the property, and any ultimate disposition data including the date of disposal and sale price of the property. (2) A physical inventory of the property must be taken and the results reconciled with the property records at least once every two years. (3) A control system must be developed to ensure adequate safeguards to prevent loss, damage, or theft of the property. Any loss, damage, or theft must be investigated. (4) Adequate maintenance procedures must be developed to keep the property in good condition. (5) If the non-Federal entity is authorized or required to sell the property, proper sales procedures must be established to ensure the highest possible return. Condition The Health System did not perform a physical inventory of federally purchased fixed assets at least once during the last two years. Additionally, the federal asset listing did not specify all of the details required by 2 CFR section 200.313 (d) (1) such as asset locations, tag numbers, use and condition. The full population of equipment funded with federal research and development dollars, as provided by the Health System, consisted of 9 items with a total historical cost of $105k. Cause The Health System lacks a process to ensure that policies and procedures related to identifying and managing its federally purchased fixed assets in accordance with 2 CFR section 200.313 are followed, including updating property records to include all required data elements and the performance of a physical inventory at least once every two years. Effect The Health System's accounting records for its federally purchased fixed assets could be inaccurate as the Health System has not formally verified the existence, current utilization and continued need for the equipment through this physical inventory process. Additionally, without maintaining tag numbers and records of asset locations, safeguarding of assets could be impacted. Questioned Costs None noted. Recommendation We recommend that the Health System implement a process to ensure its policies and procedures over equipment management are followed, including the performance of a physical inventory of federally purchased fixed assets at least once every two years in accordance with 2 CFR section 200.313(d)(2), and updating its property records to include all details required by 2 CFR section 200.313(d)(1). Management?s Views and Corrective Action Plan Management?s Views and Corrective Action Plan is included at the end of this report after the summary schedule of prior audit findings and status.

FY End: 2022-06-30
Dartmouth-Hitchcock Health and Subsidiaries
Compliance Requirement: F
Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records...

Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records must be maintained that include a description of the property, a serial number or other identification number, the source of funding for the property (including the FAIN), who holds title, the acquisition date, and cost of the property, percentage of Federal participation in the project costs for the Federal award under which the property was acquired, the location, use and condition of the property, and any ultimate disposition data including the date of disposal and sale price of the property. (2) A physical inventory of the property must be taken and the results reconciled with the property records at least once every two years. (3) A control system must be developed to ensure adequate safeguards to prevent loss, damage, or theft of the property. Any loss, damage, or theft must be investigated. (4) Adequate maintenance procedures must be developed to keep the property in good condition. (5) If the non-Federal entity is authorized or required to sell the property, proper sales procedures must be established to ensure the highest possible return. Condition The Health System did not perform a physical inventory of federally purchased fixed assets at least once during the last two years. Additionally, the federal asset listing did not specify all of the details required by 2 CFR section 200.313 (d) (1) such as asset locations, tag numbers, use and condition. The full population of equipment funded with federal research and development dollars, as provided by the Health System, consisted of 9 items with a total historical cost of $105k. Cause The Health System lacks a process to ensure that policies and procedures related to identifying and managing its federally purchased fixed assets in accordance with 2 CFR section 200.313 are followed, including updating property records to include all required data elements and the performance of a physical inventory at least once every two years. Effect The Health System's accounting records for its federally purchased fixed assets could be inaccurate as the Health System has not formally verified the existence, current utilization and continued need for the equipment through this physical inventory process. Additionally, without maintaining tag numbers and records of asset locations, safeguarding of assets could be impacted. Questioned Costs None noted. Recommendation We recommend that the Health System implement a process to ensure its policies and procedures over equipment management are followed, including the performance of a physical inventory of federally purchased fixed assets at least once every two years in accordance with 2 CFR section 200.313(d)(2), and updating its property records to include all details required by 2 CFR section 200.313(d)(1). Management?s Views and Corrective Action Plan Management?s Views and Corrective Action Plan is included at the end of this report after the summary schedule of prior audit findings and status.

FY End: 2022-06-30
Dartmouth-Hitchcock Health and Subsidiaries
Compliance Requirement: F
Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records...

Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records must be maintained that include a description of the property, a serial number or other identification number, the source of funding for the property (including the FAIN), who holds title, the acquisition date, and cost of the property, percentage of Federal participation in the project costs for the Federal award under which the property was acquired, the location, use and condition of the property, and any ultimate disposition data including the date of disposal and sale price of the property. (2) A physical inventory of the property must be taken and the results reconciled with the property records at least once every two years. (3) A control system must be developed to ensure adequate safeguards to prevent loss, damage, or theft of the property. Any loss, damage, or theft must be investigated. (4) Adequate maintenance procedures must be developed to keep the property in good condition. (5) If the non-Federal entity is authorized or required to sell the property, proper sales procedures must be established to ensure the highest possible return. Condition The Health System did not perform a physical inventory of federally purchased fixed assets at least once during the last two years. Additionally, the federal asset listing did not specify all of the details required by 2 CFR section 200.313 (d) (1) such as asset locations, tag numbers, use and condition. The full population of equipment funded with federal research and development dollars, as provided by the Health System, consisted of 9 items with a total historical cost of $105k. Cause The Health System lacks a process to ensure that policies and procedures related to identifying and managing its federally purchased fixed assets in accordance with 2 CFR section 200.313 are followed, including updating property records to include all required data elements and the performance of a physical inventory at least once every two years. Effect The Health System's accounting records for its federally purchased fixed assets could be inaccurate as the Health System has not formally verified the existence, current utilization and continued need for the equipment through this physical inventory process. Additionally, without maintaining tag numbers and records of asset locations, safeguarding of assets could be impacted. Questioned Costs None noted. Recommendation We recommend that the Health System implement a process to ensure its policies and procedures over equipment management are followed, including the performance of a physical inventory of federally purchased fixed assets at least once every two years in accordance with 2 CFR section 200.313(d)(2), and updating its property records to include all details required by 2 CFR section 200.313(d)(1). Management?s Views and Corrective Action Plan Management?s Views and Corrective Action Plan is included at the end of this report after the summary schedule of prior audit findings and status.

FY End: 2022-06-30
Dartmouth-Hitchcock Health and Subsidiaries
Compliance Requirement: F
Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records...

Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records must be maintained that include a description of the property, a serial number or other identification number, the source of funding for the property (including the FAIN), who holds title, the acquisition date, and cost of the property, percentage of Federal participation in the project costs for the Federal award under which the property was acquired, the location, use and condition of the property, and any ultimate disposition data including the date of disposal and sale price of the property. (2) A physical inventory of the property must be taken and the results reconciled with the property records at least once every two years. (3) A control system must be developed to ensure adequate safeguards to prevent loss, damage, or theft of the property. Any loss, damage, or theft must be investigated. (4) Adequate maintenance procedures must be developed to keep the property in good condition. (5) If the non-Federal entity is authorized or required to sell the property, proper sales procedures must be established to ensure the highest possible return. Condition The Health System did not perform a physical inventory of federally purchased fixed assets at least once during the last two years. Additionally, the federal asset listing did not specify all of the details required by 2 CFR section 200.313 (d) (1) such as asset locations, tag numbers, use and condition. The full population of equipment funded with federal research and development dollars, as provided by the Health System, consisted of 9 items with a total historical cost of $105k. Cause The Health System lacks a process to ensure that policies and procedures related to identifying and managing its federally purchased fixed assets in accordance with 2 CFR section 200.313 are followed, including updating property records to include all required data elements and the performance of a physical inventory at least once every two years. Effect The Health System's accounting records for its federally purchased fixed assets could be inaccurate as the Health System has not formally verified the existence, current utilization and continued need for the equipment through this physical inventory process. Additionally, without maintaining tag numbers and records of asset locations, safeguarding of assets could be impacted. Questioned Costs None noted. Recommendation We recommend that the Health System implement a process to ensure its policies and procedures over equipment management are followed, including the performance of a physical inventory of federally purchased fixed assets at least once every two years in accordance with 2 CFR section 200.313(d)(2), and updating its property records to include all details required by 2 CFR section 200.313(d)(1). Management?s Views and Corrective Action Plan Management?s Views and Corrective Action Plan is included at the end of this report after the summary schedule of prior audit findings and status.

FY End: 2022-06-30
Dartmouth-Hitchcock Health and Subsidiaries
Compliance Requirement: F
Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records...

Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records must be maintained that include a description of the property, a serial number or other identification number, the source of funding for the property (including the FAIN), who holds title, the acquisition date, and cost of the property, percentage of Federal participation in the project costs for the Federal award under which the property was acquired, the location, use and condition of the property, and any ultimate disposition data including the date of disposal and sale price of the property. (2) A physical inventory of the property must be taken and the results reconciled with the property records at least once every two years. (3) A control system must be developed to ensure adequate safeguards to prevent loss, damage, or theft of the property. Any loss, damage, or theft must be investigated. (4) Adequate maintenance procedures must be developed to keep the property in good condition. (5) If the non-Federal entity is authorized or required to sell the property, proper sales procedures must be established to ensure the highest possible return. Condition The Health System did not perform a physical inventory of federally purchased fixed assets at least once during the last two years. Additionally, the federal asset listing did not specify all of the details required by 2 CFR section 200.313 (d) (1) such as asset locations, tag numbers, use and condition. The full population of equipment funded with federal research and development dollars, as provided by the Health System, consisted of 9 items with a total historical cost of $105k. Cause The Health System lacks a process to ensure that policies and procedures related to identifying and managing its federally purchased fixed assets in accordance with 2 CFR section 200.313 are followed, including updating property records to include all required data elements and the performance of a physical inventory at least once every two years. Effect The Health System's accounting records for its federally purchased fixed assets could be inaccurate as the Health System has not formally verified the existence, current utilization and continued need for the equipment through this physical inventory process. Additionally, without maintaining tag numbers and records of asset locations, safeguarding of assets could be impacted. Questioned Costs None noted. Recommendation We recommend that the Health System implement a process to ensure its policies and procedures over equipment management are followed, including the performance of a physical inventory of federally purchased fixed assets at least once every two years in accordance with 2 CFR section 200.313(d)(2), and updating its property records to include all details required by 2 CFR section 200.313(d)(1). Management?s Views and Corrective Action Plan Management?s Views and Corrective Action Plan is included at the end of this report after the summary schedule of prior audit findings and status.

FY End: 2022-06-30
Dartmouth-Hitchcock Health and Subsidiaries
Compliance Requirement: F
Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records...

Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records must be maintained that include a description of the property, a serial number or other identification number, the source of funding for the property (including the FAIN), who holds title, the acquisition date, and cost of the property, percentage of Federal participation in the project costs for the Federal award under which the property was acquired, the location, use and condition of the property, and any ultimate disposition data including the date of disposal and sale price of the property. (2) A physical inventory of the property must be taken and the results reconciled with the property records at least once every two years. (3) A control system must be developed to ensure adequate safeguards to prevent loss, damage, or theft of the property. Any loss, damage, or theft must be investigated. (4) Adequate maintenance procedures must be developed to keep the property in good condition. (5) If the non-Federal entity is authorized or required to sell the property, proper sales procedures must be established to ensure the highest possible return. Condition The Health System did not perform a physical inventory of federally purchased fixed assets at least once during the last two years. Additionally, the federal asset listing did not specify all of the details required by 2 CFR section 200.313 (d) (1) such as asset locations, tag numbers, use and condition. The full population of equipment funded with federal research and development dollars, as provided by the Health System, consisted of 9 items with a total historical cost of $105k. Cause The Health System lacks a process to ensure that policies and procedures related to identifying and managing its federally purchased fixed assets in accordance with 2 CFR section 200.313 are followed, including updating property records to include all required data elements and the performance of a physical inventory at least once every two years. Effect The Health System's accounting records for its federally purchased fixed assets could be inaccurate as the Health System has not formally verified the existence, current utilization and continued need for the equipment through this physical inventory process. Additionally, without maintaining tag numbers and records of asset locations, safeguarding of assets could be impacted. Questioned Costs None noted. Recommendation We recommend that the Health System implement a process to ensure its policies and procedures over equipment management are followed, including the performance of a physical inventory of federally purchased fixed assets at least once every two years in accordance with 2 CFR section 200.313(d)(2), and updating its property records to include all details required by 2 CFR section 200.313(d)(1). Management?s Views and Corrective Action Plan Management?s Views and Corrective Action Plan is included at the end of this report after the summary schedule of prior audit findings and status.

FY End: 2022-06-30
Dartmouth-Hitchcock Health and Subsidiaries
Compliance Requirement: F
Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records...

Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records must be maintained that include a description of the property, a serial number or other identification number, the source of funding for the property (including the FAIN), who holds title, the acquisition date, and cost of the property, percentage of Federal participation in the project costs for the Federal award under which the property was acquired, the location, use and condition of the property, and any ultimate disposition data including the date of disposal and sale price of the property. (2) A physical inventory of the property must be taken and the results reconciled with the property records at least once every two years. (3) A control system must be developed to ensure adequate safeguards to prevent loss, damage, or theft of the property. Any loss, damage, or theft must be investigated. (4) Adequate maintenance procedures must be developed to keep the property in good condition. (5) If the non-Federal entity is authorized or required to sell the property, proper sales procedures must be established to ensure the highest possible return. Condition The Health System did not perform a physical inventory of federally purchased fixed assets at least once during the last two years. Additionally, the federal asset listing did not specify all of the details required by 2 CFR section 200.313 (d) (1) such as asset locations, tag numbers, use and condition. The full population of equipment funded with federal research and development dollars, as provided by the Health System, consisted of 9 items with a total historical cost of $105k. Cause The Health System lacks a process to ensure that policies and procedures related to identifying and managing its federally purchased fixed assets in accordance with 2 CFR section 200.313 are followed, including updating property records to include all required data elements and the performance of a physical inventory at least once every two years. Effect The Health System's accounting records for its federally purchased fixed assets could be inaccurate as the Health System has not formally verified the existence, current utilization and continued need for the equipment through this physical inventory process. Additionally, without maintaining tag numbers and records of asset locations, safeguarding of assets could be impacted. Questioned Costs None noted. Recommendation We recommend that the Health System implement a process to ensure its policies and procedures over equipment management are followed, including the performance of a physical inventory of federally purchased fixed assets at least once every two years in accordance with 2 CFR section 200.313(d)(2), and updating its property records to include all details required by 2 CFR section 200.313(d)(1). Management?s Views and Corrective Action Plan Management?s Views and Corrective Action Plan is included at the end of this report after the summary schedule of prior audit findings and status.

FY End: 2022-06-30
Dartmouth-Hitchcock Health and Subsidiaries
Compliance Requirement: F
Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records...

Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records must be maintained that include a description of the property, a serial number or other identification number, the source of funding for the property (including the FAIN), who holds title, the acquisition date, and cost of the property, percentage of Federal participation in the project costs for the Federal award under which the property was acquired, the location, use and condition of the property, and any ultimate disposition data including the date of disposal and sale price of the property. (2) A physical inventory of the property must be taken and the results reconciled with the property records at least once every two years. (3) A control system must be developed to ensure adequate safeguards to prevent loss, damage, or theft of the property. Any loss, damage, or theft must be investigated. (4) Adequate maintenance procedures must be developed to keep the property in good condition. (5) If the non-Federal entity is authorized or required to sell the property, proper sales procedures must be established to ensure the highest possible return. Condition The Health System did not perform a physical inventory of federally purchased fixed assets at least once during the last two years. Additionally, the federal asset listing did not specify all of the details required by 2 CFR section 200.313 (d) (1) such as asset locations, tag numbers, use and condition. The full population of equipment funded with federal research and development dollars, as provided by the Health System, consisted of 9 items with a total historical cost of $105k. Cause The Health System lacks a process to ensure that policies and procedures related to identifying and managing its federally purchased fixed assets in accordance with 2 CFR section 200.313 are followed, including updating property records to include all required data elements and the performance of a physical inventory at least once every two years. Effect The Health System's accounting records for its federally purchased fixed assets could be inaccurate as the Health System has not formally verified the existence, current utilization and continued need for the equipment through this physical inventory process. Additionally, without maintaining tag numbers and records of asset locations, safeguarding of assets could be impacted. Questioned Costs None noted. Recommendation We recommend that the Health System implement a process to ensure its policies and procedures over equipment management are followed, including the performance of a physical inventory of federally purchased fixed assets at least once every two years in accordance with 2 CFR section 200.313(d)(2), and updating its property records to include all details required by 2 CFR section 200.313(d)(1). Management?s Views and Corrective Action Plan Management?s Views and Corrective Action Plan is included at the end of this report after the summary schedule of prior audit findings and status.

FY End: 2022-06-30
Dartmouth-Hitchcock Health and Subsidiaries
Compliance Requirement: F
Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records...

Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records must be maintained that include a description of the property, a serial number or other identification number, the source of funding for the property (including the FAIN), who holds title, the acquisition date, and cost of the property, percentage of Federal participation in the project costs for the Federal award under which the property was acquired, the location, use and condition of the property, and any ultimate disposition data including the date of disposal and sale price of the property. (2) A physical inventory of the property must be taken and the results reconciled with the property records at least once every two years. (3) A control system must be developed to ensure adequate safeguards to prevent loss, damage, or theft of the property. Any loss, damage, or theft must be investigated. (4) Adequate maintenance procedures must be developed to keep the property in good condition. (5) If the non-Federal entity is authorized or required to sell the property, proper sales procedures must be established to ensure the highest possible return. Condition The Health System did not perform a physical inventory of federally purchased fixed assets at least once during the last two years. Additionally, the federal asset listing did not specify all of the details required by 2 CFR section 200.313 (d) (1) such as asset locations, tag numbers, use and condition. The full population of equipment funded with federal research and development dollars, as provided by the Health System, consisted of 9 items with a total historical cost of $105k. Cause The Health System lacks a process to ensure that policies and procedures related to identifying and managing its federally purchased fixed assets in accordance with 2 CFR section 200.313 are followed, including updating property records to include all required data elements and the performance of a physical inventory at least once every two years. Effect The Health System's accounting records for its federally purchased fixed assets could be inaccurate as the Health System has not formally verified the existence, current utilization and continued need for the equipment through this physical inventory process. Additionally, without maintaining tag numbers and records of asset locations, safeguarding of assets could be impacted. Questioned Costs None noted. Recommendation We recommend that the Health System implement a process to ensure its policies and procedures over equipment management are followed, including the performance of a physical inventory of federally purchased fixed assets at least once every two years in accordance with 2 CFR section 200.313(d)(2), and updating its property records to include all details required by 2 CFR section 200.313(d)(1). Management?s Views and Corrective Action Plan Management?s Views and Corrective Action Plan is included at the end of this report after the summary schedule of prior audit findings and status.

FY End: 2022-06-30
Dartmouth-Hitchcock Health and Subsidiaries
Compliance Requirement: F
Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records...

Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records must be maintained that include a description of the property, a serial number or other identification number, the source of funding for the property (including the FAIN), who holds title, the acquisition date, and cost of the property, percentage of Federal participation in the project costs for the Federal award under which the property was acquired, the location, use and condition of the property, and any ultimate disposition data including the date of disposal and sale price of the property. (2) A physical inventory of the property must be taken and the results reconciled with the property records at least once every two years. (3) A control system must be developed to ensure adequate safeguards to prevent loss, damage, or theft of the property. Any loss, damage, or theft must be investigated. (4) Adequate maintenance procedures must be developed to keep the property in good condition. (5) If the non-Federal entity is authorized or required to sell the property, proper sales procedures must be established to ensure the highest possible return. Condition The Health System did not perform a physical inventory of federally purchased fixed assets at least once during the last two years. Additionally, the federal asset listing did not specify all of the details required by 2 CFR section 200.313 (d) (1) such as asset locations, tag numbers, use and condition. The full population of equipment funded with federal research and development dollars, as provided by the Health System, consisted of 9 items with a total historical cost of $105k. Cause The Health System lacks a process to ensure that policies and procedures related to identifying and managing its federally purchased fixed assets in accordance with 2 CFR section 200.313 are followed, including updating property records to include all required data elements and the performance of a physical inventory at least once every two years. Effect The Health System's accounting records for its federally purchased fixed assets could be inaccurate as the Health System has not formally verified the existence, current utilization and continued need for the equipment through this physical inventory process. Additionally, without maintaining tag numbers and records of asset locations, safeguarding of assets could be impacted. Questioned Costs None noted. Recommendation We recommend that the Health System implement a process to ensure its policies and procedures over equipment management are followed, including the performance of a physical inventory of federally purchased fixed assets at least once every two years in accordance with 2 CFR section 200.313(d)(2), and updating its property records to include all details required by 2 CFR section 200.313(d)(1). Management?s Views and Corrective Action Plan Management?s Views and Corrective Action Plan is included at the end of this report after the summary schedule of prior audit findings and status.

FY End: 2022-06-30
Dartmouth-Hitchcock Health and Subsidiaries
Compliance Requirement: F
Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records...

Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records must be maintained that include a description of the property, a serial number or other identification number, the source of funding for the property (including the FAIN), who holds title, the acquisition date, and cost of the property, percentage of Federal participation in the project costs for the Federal award under which the property was acquired, the location, use and condition of the property, and any ultimate disposition data including the date of disposal and sale price of the property. (2) A physical inventory of the property must be taken and the results reconciled with the property records at least once every two years. (3) A control system must be developed to ensure adequate safeguards to prevent loss, damage, or theft of the property. Any loss, damage, or theft must be investigated. (4) Adequate maintenance procedures must be developed to keep the property in good condition. (5) If the non-Federal entity is authorized or required to sell the property, proper sales procedures must be established to ensure the highest possible return. Condition The Health System did not perform a physical inventory of federally purchased fixed assets at least once during the last two years. Additionally, the federal asset listing did not specify all of the details required by 2 CFR section 200.313 (d) (1) such as asset locations, tag numbers, use and condition. The full population of equipment funded with federal research and development dollars, as provided by the Health System, consisted of 9 items with a total historical cost of $105k. Cause The Health System lacks a process to ensure that policies and procedures related to identifying and managing its federally purchased fixed assets in accordance with 2 CFR section 200.313 are followed, including updating property records to include all required data elements and the performance of a physical inventory at least once every two years. Effect The Health System's accounting records for its federally purchased fixed assets could be inaccurate as the Health System has not formally verified the existence, current utilization and continued need for the equipment through this physical inventory process. Additionally, without maintaining tag numbers and records of asset locations, safeguarding of assets could be impacted. Questioned Costs None noted. Recommendation We recommend that the Health System implement a process to ensure its policies and procedures over equipment management are followed, including the performance of a physical inventory of federally purchased fixed assets at least once every two years in accordance with 2 CFR section 200.313(d)(2), and updating its property records to include all details required by 2 CFR section 200.313(d)(1). Management?s Views and Corrective Action Plan Management?s Views and Corrective Action Plan is included at the end of this report after the summary schedule of prior audit findings and status.

FY End: 2022-06-30
Dartmouth-Hitchcock Health and Subsidiaries
Compliance Requirement: F
Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records...

Cluster: Research and Development Federal Agency: Various Award Names: Various Award Numbers: Various Assistance Listing Title: Various Assistance Listing Number: Various Award Year: 2021- 2022 Pass-through entity: Various Criteria According to 2 CFR section 200.313, procedures for managing equipment (including replacement equipment), whether acquired in whole or in part under a Federal award, until disposition takes place will, at a minimum, meet the following requirements: (1) Property records must be maintained that include a description of the property, a serial number or other identification number, the source of funding for the property (including the FAIN), who holds title, the acquisition date, and cost of the property, percentage of Federal participation in the project costs for the Federal award under which the property was acquired, the location, use and condition of the property, and any ultimate disposition data including the date of disposal and sale price of the property. (2) A physical inventory of the property must be taken and the results reconciled with the property records at least once every two years. (3) A control system must be developed to ensure adequate safeguards to prevent loss, damage, or theft of the property. Any loss, damage, or theft must be investigated. (4) Adequate maintenance procedures must be developed to keep the property in good condition. (5) If the non-Federal entity is authorized or required to sell the property, proper sales procedures must be established to ensure the highest possible return. Condition The Health System did not perform a physical inventory of federally purchased fixed assets at least once during the last two years. Additionally, the federal asset listing did not specify all of the details required by 2 CFR section 200.313 (d) (1) such as asset locations, tag numbers, use and condition. The full population of equipment funded with federal research and development dollars, as provided by the Health System, consisted of 9 items with a total historical cost of $105k. Cause The Health System lacks a process to ensure that policies and procedures related to identifying and managing its federally purchased fixed assets in accordance with 2 CFR section 200.313 are followed, including updating property records to include all required data elements and the performance of a physical inventory at least once every two years. Effect The Health System's accounting records for its federally purchased fixed assets could be inaccurate as the Health System has not formally verified the existence, current utilization and continued need for the equipment through this physical inventory process. Additionally, without maintaining tag numbers and records of asset locations, safeguarding of assets could be impacted. Questioned Costs None noted. Recommendation We recommend that the Health System implement a process to ensure its policies and procedures over equipment management are followed, including the performance of a physical inventory of federally purchased fixed assets at least once every two years in accordance with 2 CFR section 200.313(d)(2), and updating its property records to include all details required by 2 CFR section 200.313(d)(1). Management?s Views and Corrective Action Plan Management?s Views and Corrective Action Plan is included at the end of this report after the summary schedule of prior audit findings and status.

« 1 671 672 674 675 814 »