Section 200.311 states that real property acquired with federal funds belongs to the recipient or subrecipient and must be used for its intended purpose as long as needed. When the property is no longer needed, the recipient must follow federal instructions for its disposition, which may include compensating the federal agency if they retain ownership.
View full section details →
FY End: 2025-09-30
Okaloosa County, Florida
Compliance Requirement: F
Criteria Section 200.313(d) of the Cost Principles of the Title 2 U.S. Code of Federal Regulations Part 200—Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance) and the Florida Single Audit Act, Section 215.97, Florida Statutes, requires an entity to maintain identifying records for property acquired with federal and state awards. Additional equipment and real property requirements are contained in 2 CFR 200.311 and 48 CFR 52.245-1. T...

Criteria Section 200.313(d) of the Cost Principles of the Title 2 U.S. Code of Federal Regulations Part 200—Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance) and the Florida Single Audit Act, Section 215.97, Florida Statutes, requires an entity to maintain identifying records for property acquired with federal and state awards. Additional equipment and real property requirements are contained in 2 CFR 200.311 and 48 CFR 52.245-1. These requirements state property records must include a description of the property, a serial number or another identification number, the funding source (including the federal or state award identification number), the title holder, the acquisition date, the cost of the property, the percentage of the federal or state agency contribution towards the original purchase, the location, use and condition of the property, and any disposition data including the date of disposal and sale price of the property. Condition The fixed asset listing maintained by the County for assets acquired with federal and state awards did not contain all required elements. Cause The County has an established policy that meets the requirements of the criteria noted above. The policy was not consistently implemented during the period under audit. Effect Equipment, infrastructure, buildings and real property acquired with federal and state awards is not consistently tracked to ensure compliance with federal and state regulations. Questioned Costs None noted Repeat Finding No Context The County tracks property acquisitions using internal property records spreadsheets, which has the capability to retain grant specific identifying information for assets acquired with federal or state awards. However, this information is not entered into the records on a consistent basis. Infrastructure and building additions acquired with federal and state awards are tracked and identified while the project in progress; however, once projects are completed and placed into service, grant specific identifying information is not maintained. As a result, infrastructure and building records do not independently indicate whether an asset was federally or state funded or reference key grant details, such as the funding source or award identification number. Audit testing also identified grant funded equipment purchases that did not include required information within the fixed asset record. Recommendation The County should consistently follow their policy established for tracking and identifying fixed assets acquired with federal and state grant awards. Views of Responsible Officials Okaloosa County Management concurs with the finding and recommendation. While the County maintains a policy for tracking equipment and real property acquired with federal and state awards, we acknowledge that it was not consistently implemented during the audit period, resulting in missing grant-specific information (e.g., funding source, award ID, percentage of contribution) within our fixed asset records and on certain infrastructure/building records.

FY End: 2025-06-30
Belcourt Public School District #7
Compliance Requirement: F
Assistance Listing Number 84.425 Education Stabilization Fund Department of Education Passed Through North Dakota Department of Public Instruction Passed Through Turtle Mountain Band of Chippewa Indians Equipment/Real Property Management Criteria 2 CFR sections 200.313(c) and (e) includes a requirement for the non-federal entity to not encumber the equipment without prior approval of the federal awarding agency. 2 CFR section 200.311 includes a requirement for the non-federal entity, with prior ...

Assistance Listing Number 84.425 Education Stabilization Fund Department of Education Passed Through North Dakota Department of Public Instruction Passed Through Turtle Mountain Band of Chippewa Indians Equipment/Real Property Management Criteria 2 CFR sections 200.313(c) and (e) includes a requirement for the non-federal entity to not encumber the equipment without prior approval of the federal awarding agency. 2 CFR section 200.311 includes a requirement for the non-federal entity, with prior approval by the ED or passthrough entity, may also use ESF funds to purchase real property, perform construction or minor remodeling, and for improvements to land, buildings, or equipment. Condition The District did not obtain prior approval for equipment acquisition or construction projects. This condition was noted for the following expenditures: Check 241010 Dated 12/27/2024 for $104,931.00 Check 240640 Dated 11/14/2024 for $147,398.90 Check 239597 Dated 8/30/2024 for $121,240.00 Context Per discussion with the District staff and review of program expenditures, there were 22 capital asset acquisitions during the year, we tested three of them for prior state approval. All three of these purchases were made without prior state approval. Cause The District did not properly submit for prior approval for equipment acquisition or construction until after the expenditure had been incurred and in some instances there were no submissions for prior approval. Effect The District may have purchased capital items that were not allowed by the State. Questioned Costs Undeterminable. Repeat Finding See prior year finding 2024-004. Recommendation We recommend the District to review all compliance requirements of federal programs to ensure they have procedures to ensure compliance with those requirements and for the requests for acquisition to be made timely and for the appropriate expenditure amount. Management’s Response See corrective action plan.

FY End: 2025-06-30
State of Alaska
Compliance Requirement: F
Finding No. 2025-044 Prior Year Finding: 2024-044 Federal Awarding Agency: U.S. Department of the Interior Impact: Material Weakness AL Number and Title: 15.605, 15.611 Fish and Wildlife Cluster (FWC) Federal Award Number: Multiple Applicable Compliance Requirement: Equipment and Real Property Management Condition: Auditors could not obtain sufficient appropriate evidence to verify compliance with FWC’s equipment and real property management requirements. Context: DFG is responsible for ensuring...

Finding No. 2025-044 Prior Year Finding: 2024-044 Federal Awarding Agency: U.S. Department of the Interior Impact: Material Weakness AL Number and Title: 15.605, 15.611 Fish and Wildlife Cluster (FWC) Federal Award Number: Multiple Applicable Compliance Requirement: Equipment and Real Property Management Condition: Auditors could not obtain sufficient appropriate evidence to verify compliance with FWC’s equipment and real property management requirements. Context: DFG is responsible for ensuring equipment, real property, and capital improvements, acquired with FWC funds, are used for an authorized purpose, sufficiently tracked, and appropriately disposed of in accordance with federal regulations. DFG began efforts in FY 25 to address equipment and real property management weaknesses found in the prior year audit. However, at the end of FY 25, corrective action was incomplete. In FY 25, DFG did not maintain sufficient evidence to demonstrate compliance with equipment and real property management requirements. DFG equipment and real property records did not reliably catalog the universe of equipment, real property, and capital improvements funded with FWC grant monies. Equipment records were incomplete and not trackable by funding source in the accounting system. As a result, the audit was unable to determine the extent of equipment purchased with FWC funds. Real property records had not been reconciled since 2019 and could not be matched with DFG site visit logs. The audit could not identify the FWC assets to be monitored and the extent of site visits conducted during the audit period, and whether the site visits included monitoring for authorized uses. Cause: DFG management attributed the deficiencies to a lack of department-wide procedures, staff turnover, and insufficient training. Criteria: Title 2 CFR 200.303 requires the State to establish and maintain effective internal controls over the federal award that provides reasonable assurance that the State is managing the federal award in compliance with federal statutes, regulations, and terms and conditions of the federal award. Title 2 CFR 200.311 and Title 50 CFR 80.134 requires the State to use real property for the purpose authorized in the grant for as long as it is needed for that purpose. When real property is no longer needed for the originally authorized purpose, property must be disposed of in accordance with federal requirements. Title 2 CFR 200.313 requires the State to use, manage and dispose of equipment acquired under a federal award in accordance with State laws and procedures. Such equipment must be used for the project or program for which it was acquired and for as long as needed. The State agency must maintain equipment property records, perform physical inventory of equipment, develop a control system, and perform regular maintenance of equipment. Title 50 CFR 80.133 requires the State to maintain acquired or completed capital improvements under FWC grants to ensure that each capital improvement continues to serve its authorized purpose during its useful life. Effect: The lack of department-wide procedures increased the risk that FWC funded assets were not used for authorized purposes and properly disposed of when no longer needed. Inadequate equipment tracking increased the risk of loss or theft. Further, noncompliance with federal regulations may result in the federal awarding agency imposing additional conditions or taking corrective action, including additional reporting requirements or withholding/terminating funding. Questioned Costs: Indeterminate Recommendation: DFG’s commissioner should continue efforts to ensure procedures are developed and training is implemented so that FWC funded equipment, real property, and capital improvements are fully identified and are managed in compliance with federal requirements. Views of Responsible Officials: Management agrees with this finding.

FY End: 2025-04-30
I Care, INC
Compliance Requirement: F
Criteria - Federal regulations require that equipment and real property acquired under a federal award be properly documented in accordance with 2 CFR §§200.310–200.313 and applicable program requirements. "Equipment acquired under a federal award must be used for the authorized purposes of the project during the period of performance, or until the property is no longer needed for the project. A HSA may not dispose of, replace, or encumber title to equipment without prior ACF approval (45 CFR se...

Criteria - Federal regulations require that equipment and real property acquired under a federal award be properly documented in accordance with 2 CFR §§200.310–200.313 and applicable program requirements. "Equipment acquired under a federal award must be used for the authorized purposes of the project during the period of performance, or until the property is no longer needed for the project. A HSA may not dispose of, replace, or encumber title to equipment without prior ACF approval (45 CFR section 75.319; 45 CFR section 75.308(c)(1)(xi))." "Property records must be maintained for equipment acquired under a federal award that includes a description of the property, a serial number or another identification number, the source of funding for the property (including the FAIN), who holds the title, the acquisition date, and cost of the property, percentage of federal participation in the project costs for the federal award under which the property was acquired the location, use, and condition of the property, and any ultimate disposition data including the date of disposal and sale price of the property. A physical inventory of the property must be taken and the results reconciled with the property records at least once every two years." Condition and Context - The audit identified gaps in documentation and centralized tracking of equipment and real property acquired under federal awards. Certain historical additions and disposals were not fully documented in accordance with Uniform Guidance, and some current-year asset activity was not captured or reconciled in the property records. Questioned Costs - $14,410 relates to documentation and classification issues identified during the audit. Cause - Property management policies did not fully incorporate current Uniform Guidance requirements, and asset tracking relied on manual processes that were handled across multiple areas and would benefit from more consistent central oversight. Effect - Compliance risk: Noncompliance with property standards increases the risk of disallowed costs, clawbacks, or additional restrictions by the Federal agency. Reporting risk: The Schedule of Expenditures of Federal Awards (SEFA) and related disclosures may be incomplete or inaccurate if property‑related terms and conditions are not followed, affecting low‑risk auditee status evaluations under Subpart F. Recommendation - Update property management policies to mirror requirements in 2 CFR §200.313, §200.311, and §200.310, including explicit steps to (a) verify authorized use, (b) prohibit encumbrances without prior approval, (c) document and seek disposition instructions when no longer needed, and (d) maintain insurance equivalency. Provide targeted staff training and oversight. Views of responsible officials - Management concurs with the finding and views it as an opportunity to modernize property management practices. Corrective actions are underway to strengthen documentation, training, and oversight.

FY End: 2024-09-30
American Soybean Association
Compliance Requirement: F
Criteria and Condition: Title to real property acquired or improved by non-federal entities under grants and cooperative agreements vests in the non-federal entity subject to the obligations and conditions specified in 2 CFR section 200.311 (2 CFR section 200.311(a)). Real property will be used for the originally authorized purpose as long as needed for that purpose, during which time the non-federal entity must not dispose of or encumber title to or other interests in the real property (2 CFR s...

Criteria and Condition: Title to real property acquired or improved by non-federal entities under grants and cooperative agreements vests in the non-federal entity subject to the obligations and conditions specified in 2 CFR section 200.311 (2 CFR section 200.311(a)). Real property will be used for the originally authorized purpose as long as needed for that purpose, during which time the non-federal entity must not dispose of or encumber title to or other interests in the real property (2 CFR section 200.311(b)). When real property is no longer needed for the originally authorized purpose, the non-federal entity must obtain disposition instructions from the federal awarding agency or the pass-through entity, as applicable. When real property is sold, sales procedures must be followed that provide for competition to the extent practicable and result in the highest possible return. If sold, non- federal entities must compensate the federal awarding agency for the portion of the net sales proceeds that represents the federal agency’s interest in the real property, which is the amount calculated by multiplying the current market value or sale proceeds by the federal agency’s participation in total project costs. If the property is retained, the non-federal entity must compensate the federal awarding agency for the federal portion of the current fair market value of the property. Disposition instructions may also provide for transfer of title to the federal awarding agency or a designated third party, in which case the non-federal entity is entitled to the non-federal interest in the property, which is calculated by multiplying the current market value or sale proceeds by the non-federal entity’s share in total project costs (2 CFR section 200.311(c)(3)). Context: A foreign office indicated that assets purchased with federal funds were disposed of, but were still included on the inventory listing. Cause: The federal awarding agency was not notified of the disposal of assets purchased with federal funds. Questioned Cost: No questioned costs. Effect: Assets no longer in service are included on the federal fixed asset listing. Recommendation: Fixed assets purchased with federal funds should be subject to regular inventory, with dispositions communicated to the federal agency. Classification: Compliance finding and control deficiency in internal controls.

FY End: 2024-09-30
American Soybean Association
Compliance Requirement: F
Criteria and Condition: Title to real property acquired or improved by non-federal entities under grants and cooperative agreements vests in the non-federal entity subject to the obligations and conditions specified in 2 CFR section 200.311 (2 CFR section 200.311(a)). Real property will be used for the originally authorized purpose as long as needed for that purpose, during which time the non-federal entity must not dispose of or encumber title to or other interests in the real property (2 CFR s...

Criteria and Condition: Title to real property acquired or improved by non-federal entities under grants and cooperative agreements vests in the non-federal entity subject to the obligations and conditions specified in 2 CFR section 200.311 (2 CFR section 200.311(a)). Real property will be used for the originally authorized purpose as long as needed for that purpose, during which time the non-federal entity must not dispose of or encumber title to or other interests in the real property (2 CFR section 200.311(b)). When real property is no longer needed for the originally authorized purpose, the non-federal entity must obtain disposition instructions from the federal awarding agency or the pass-through entity, as applicable. When real property is sold, sales procedures must be followed that provide for competition to the extent practicable and result in the highest possible return. If sold, non- federal entities must compensate the federal awarding agency for the portion of the net sales proceeds that represents the federal agency’s interest in the real property, which is the amount calculated by multiplying the current market value or sale proceeds by the federal agency’s participation in total project costs. If the property is retained, the non-federal entity must compensate the federal awarding agency for the federal portion of the current fair market value of the property. Disposition instructions may also provide for transfer of title to the federal awarding agency or a designated third party, in which case the non-federal entity is entitled to the non-federal interest in the property, which is calculated by multiplying the current market value or sale proceeds by the non-federal entity’s share in total project costs (2 CFR section 200.311(c)(3)). Context: A foreign office indicated that assets purchased with federal funds were disposed of, but were still included on the inventory listing. Cause: The federal awarding agency was not notified of the disposal of assets purchased with federal funds. Questioned Cost: No questioned costs. Effect: Assets no longer in service are included on the federal fixed asset listing. Recommendation: Fixed assets purchased with federal funds should be subject to regular inventory, with dispositions communicated to the federal agency. Classification: Compliance finding and control deficiency in internal controls.

FY End: 2024-09-30
City of Batesville, Mississippi
Compliance Requirement: F
Federal Program 23.002 - Appalachian Area Development 14.228 - Community Development Block Grants/State's Program Award Numbers ARC-20698 ARC-20699 CDBG Subgrant: 1137-21-111-PF-01 Federal Agency U.S. Department of Housing and Urban Development (HUD) Appalachian Regional Commission (ARC) Compliance Requirement Equipment and Real Property Management- 2 CFR §200.310-316 Type of Finding Internal Control over Compliance - Material Weakness Compliance - Noncompliance Questioned Costs None Criteria Pe...

Federal Program 23.002 - Appalachian Area Development 14.228 - Community Development Block Grants/State's Program Award Numbers ARC-20698 ARC-20699 CDBG Subgrant: 1137-21-111-PF-01 Federal Agency U.S. Department of Housing and Urban Development (HUD) Appalachian Regional Commission (ARC) Compliance Requirement Equipment and Real Property Management- 2 CFR §200.310-316 Type of Finding Internal Control over Compliance - Material Weakness Compliance - Noncompliance Questioned Costs None Criteria Per 2 CFR §200.310-316 and the 0MB Compliance Supplement, recipients of federal awards must: Maintain detailed property records including description, serial number, acquisition date, cost, location, and condition Conduct a physical inventory at least once every two years and reconcile results Safeguard assets from loss, damage, or theft File a Notice of Federal Interest for real property acquired with federal funds Follow disposition procedures outlined in 2 CFR §200.311-313 Condition The City of Batesville did not conduct a biennial physical inventory of federally funded equipment and real property as required by 2 CFR §200.313(d)(2). Inventory records were incomplete, decentralized, and lacked key data fields such as asset condition and federal funding source. Infrastructure assets funded by CDBG and ARC grants were not classified as real property, and no Notice of Federal Interest was filed. Additionally, the City could not demonstrate that federally funded assets were safeguarded or reconciled against disposals. Cause The City lacked centralized oversight and formal policies for property management. Staff were unaware of federal requirements related to infrastructure classification and inventory procedures. No training or monitoring mechanisms were in place to ensure compliance. Effect The City is at risk of noncompliance with federal property management standards, including failure to conduct biennial inventories and file Notices of Federal Interest for real property. Although the sewer infrastructure funded by CFDA 14.228 and 23.002 is not susceptible to theft or loss due to its fixed nature, the lack of documentation and oversight represents a material weakness in internal control. No questioned costs were identified, as all expenditures were supported and the assets remain in use. Although Assistance Listing 90.201 was not selected for audit, similar deficiencies in property management were observed during preliminary review, suggesting the issue may be systemic across federal programs. Recommendation Implement a centralized inventory system with required data fields Conduct and document biennial physical inventories File Notices of Federal Interest for applicable real property Provide staff training on federal property standards Deveiop written policies for asset classification, inventory, and disposition Establish internal monitoring procedures to ensure ongoing compliance Views of Responsible Officials Management concurs with the finding. The City will implement a centralized inventory system and conduct a physical inventory by March 31, 2026. Training will be provided to relevant staff, and a formal policy will be adopted to ensure compliance with 2 CFR §200.310-316. The City will consult with HUD and ARC regarding the filing of Notices of Federal Interest for infrastructure assets. Management also acknowledges that similar issues were observed in non-audited programs and will extend corrective actions City-wide.

FY End: 2024-06-30
Compton Unified School District
Compliance Requirement: AB
FINDING #2024-002: EDUCATION STABILIZATION FUNDS – EQUIPMENT AND OTHER CAPITAL EXPENDITURES (50000) Program Name: Elementary and Secondary School Emergency Relief II (ESSER II) Fund Assistance Listing Number: 84.425 Pass-Through Agency: California Department of Education (CDE) Federal Agency: U.S. Department of Education Criteria: Consistent with 2 CFR section 200.311 (real property), section 200.313 (equipment), and section 200.439 (equipment and other capital expenditures) ESF funds may be use...

FINDING #2024-002: EDUCATION STABILIZATION FUNDS – EQUIPMENT AND OTHER CAPITAL EXPENDITURES (50000) Program Name: Elementary and Secondary School Emergency Relief II (ESSER II) Fund Assistance Listing Number: 84.425 Pass-Through Agency: California Department of Education (CDE) Federal Agency: U.S. Department of Education Criteria: Consistent with 2 CFR section 200.311 (real property), section 200.313 (equipment), and section 200.439 (equipment and other capital expenditures) ESF funds may be used to purchase equipment. Capital expenditures for general and special purpose equipment purchases are subject to prior approval by ED or the pass-through entity. Condition: Through testing of a representative sample of ESF expenditures, we noted that the equipment expenditures with Data Impressions in the amount totaling $617,023, did not appear to be pre-approved by the California Department of Education (CDE). Context: The condition was identified through the testing of ESF expenditures. Cause: District oversight. Effect: The funds spent on these purchases may be subject to review by or return to the awarding agency. Questioned Costs: $617,023. Repeat Finding: This is not a repeat finding. Recommendation: We recommend that the District obtain prior approval from CDE for all capital purchases from the Education Stabilization Fund in excess of $5,000. Views of Responsible Officials: See Corrective Action Plan on following page.

FY End: 2024-06-30
Compton Unified School District
Compliance Requirement: AB
FINDING #2024-002: EDUCATION STABILIZATION FUNDS – EQUIPMENT AND OTHER CAPITAL EXPENDITURES (50000) Program Name: Elementary and Secondary School Emergency Relief II (ESSER II) Fund Assistance Listing Number: 84.425 Pass-Through Agency: California Department of Education (CDE) Federal Agency: U.S. Department of Education Criteria: Consistent with 2 CFR section 200.311 (real property), section 200.313 (equipment), and section 200.439 (equipment and other capital expenditures) ESF funds may be use...

FINDING #2024-002: EDUCATION STABILIZATION FUNDS – EQUIPMENT AND OTHER CAPITAL EXPENDITURES (50000) Program Name: Elementary and Secondary School Emergency Relief II (ESSER II) Fund Assistance Listing Number: 84.425 Pass-Through Agency: California Department of Education (CDE) Federal Agency: U.S. Department of Education Criteria: Consistent with 2 CFR section 200.311 (real property), section 200.313 (equipment), and section 200.439 (equipment and other capital expenditures) ESF funds may be used to purchase equipment. Capital expenditures for general and special purpose equipment purchases are subject to prior approval by ED or the pass-through entity. Condition: Through testing of a representative sample of ESF expenditures, we noted that the equipment expenditures with Data Impressions in the amount totaling $617,023, did not appear to be pre-approved by the California Department of Education (CDE). Context: The condition was identified through the testing of ESF expenditures. Cause: District oversight. Effect: The funds spent on these purchases may be subject to review by or return to the awarding agency. Questioned Costs: $617,023. Repeat Finding: This is not a repeat finding. Recommendation: We recommend that the District obtain prior approval from CDE for all capital purchases from the Education Stabilization Fund in excess of $5,000. Views of Responsible Officials: See Corrective Action Plan on following page.

FY End: 2024-06-30
Compton Unified School District
Compliance Requirement: AB
FINDING #2024-002: EDUCATION STABILIZATION FUNDS – EQUIPMENT AND OTHER CAPITAL EXPENDITURES (50000) Program Name: Elementary and Secondary School Emergency Relief II (ESSER II) Fund Assistance Listing Number: 84.425 Pass-Through Agency: California Department of Education (CDE) Federal Agency: U.S. Department of Education Criteria: Consistent with 2 CFR section 200.311 (real property), section 200.313 (equipment), and section 200.439 (equipment and other capital expenditures) ESF funds may be use...

FINDING #2024-002: EDUCATION STABILIZATION FUNDS – EQUIPMENT AND OTHER CAPITAL EXPENDITURES (50000) Program Name: Elementary and Secondary School Emergency Relief II (ESSER II) Fund Assistance Listing Number: 84.425 Pass-Through Agency: California Department of Education (CDE) Federal Agency: U.S. Department of Education Criteria: Consistent with 2 CFR section 200.311 (real property), section 200.313 (equipment), and section 200.439 (equipment and other capital expenditures) ESF funds may be used to purchase equipment. Capital expenditures for general and special purpose equipment purchases are subject to prior approval by ED or the pass-through entity. Condition: Through testing of a representative sample of ESF expenditures, we noted that the equipment expenditures with Data Impressions in the amount totaling $617,023, did not appear to be pre-approved by the California Department of Education (CDE). Context: The condition was identified through the testing of ESF expenditures. Cause: District oversight. Effect: The funds spent on these purchases may be subject to review by or return to the awarding agency. Questioned Costs: $617,023. Repeat Finding: This is not a repeat finding. Recommendation: We recommend that the District obtain prior approval from CDE for all capital purchases from the Education Stabilization Fund in excess of $5,000. Views of Responsible Officials: See Corrective Action Plan on following page.

FY End: 2024-06-30
Compton Unified School District
Compliance Requirement: AB
FINDING #2024-002: EDUCATION STABILIZATION FUNDS – EQUIPMENT AND OTHER CAPITAL EXPENDITURES (50000) Program Name: Elementary and Secondary School Emergency Relief II (ESSER II) Fund Assistance Listing Number: 84.425 Pass-Through Agency: California Department of Education (CDE) Federal Agency: U.S. Department of Education Criteria: Consistent with 2 CFR section 200.311 (real property), section 200.313 (equipment), and section 200.439 (equipment and other capital expenditures) ESF funds may be use...

FINDING #2024-002: EDUCATION STABILIZATION FUNDS – EQUIPMENT AND OTHER CAPITAL EXPENDITURES (50000) Program Name: Elementary and Secondary School Emergency Relief II (ESSER II) Fund Assistance Listing Number: 84.425 Pass-Through Agency: California Department of Education (CDE) Federal Agency: U.S. Department of Education Criteria: Consistent with 2 CFR section 200.311 (real property), section 200.313 (equipment), and section 200.439 (equipment and other capital expenditures) ESF funds may be used to purchase equipment. Capital expenditures for general and special purpose equipment purchases are subject to prior approval by ED or the pass-through entity. Condition: Through testing of a representative sample of ESF expenditures, we noted that the equipment expenditures with Data Impressions in the amount totaling $617,023, did not appear to be pre-approved by the California Department of Education (CDE). Context: The condition was identified through the testing of ESF expenditures. Cause: District oversight. Effect: The funds spent on these purchases may be subject to review by or return to the awarding agency. Questioned Costs: $617,023. Repeat Finding: This is not a repeat finding. Recommendation: We recommend that the District obtain prior approval from CDE for all capital purchases from the Education Stabilization Fund in excess of $5,000. Views of Responsible Officials: See Corrective Action Plan on following page.

FY End: 2024-06-30
Compton Unified School District
Compliance Requirement: AB
FINDING #2024-002: EDUCATION STABILIZATION FUNDS – EQUIPMENT AND OTHER CAPITAL EXPENDITURES (50000) Program Name: Elementary and Secondary School Emergency Relief II (ESSER II) Fund Assistance Listing Number: 84.425 Pass-Through Agency: California Department of Education (CDE) Federal Agency: U.S. Department of Education Criteria: Consistent with 2 CFR section 200.311 (real property), section 200.313 (equipment), and section 200.439 (equipment and other capital expenditures) ESF funds may be use...

FINDING #2024-002: EDUCATION STABILIZATION FUNDS – EQUIPMENT AND OTHER CAPITAL EXPENDITURES (50000) Program Name: Elementary and Secondary School Emergency Relief II (ESSER II) Fund Assistance Listing Number: 84.425 Pass-Through Agency: California Department of Education (CDE) Federal Agency: U.S. Department of Education Criteria: Consistent with 2 CFR section 200.311 (real property), section 200.313 (equipment), and section 200.439 (equipment and other capital expenditures) ESF funds may be used to purchase equipment. Capital expenditures for general and special purpose equipment purchases are subject to prior approval by ED or the pass-through entity. Condition: Through testing of a representative sample of ESF expenditures, we noted that the equipment expenditures with Data Impressions in the amount totaling $617,023, did not appear to be pre-approved by the California Department of Education (CDE). Context: The condition was identified through the testing of ESF expenditures. Cause: District oversight. Effect: The funds spent on these purchases may be subject to review by or return to the awarding agency. Questioned Costs: $617,023. Repeat Finding: This is not a repeat finding. Recommendation: We recommend that the District obtain prior approval from CDE for all capital purchases from the Education Stabilization Fund in excess of $5,000. Views of Responsible Officials: See Corrective Action Plan on following page.

FY End: 2024-06-30
Compton Unified School District
Compliance Requirement: AB
FINDING #2024-002: EDUCATION STABILIZATION FUNDS – EQUIPMENT AND OTHER CAPITAL EXPENDITURES (50000) Program Name: Elementary and Secondary School Emergency Relief II (ESSER II) Fund Assistance Listing Number: 84.425 Pass-Through Agency: California Department of Education (CDE) Federal Agency: U.S. Department of Education Criteria: Consistent with 2 CFR section 200.311 (real property), section 200.313 (equipment), and section 200.439 (equipment and other capital expenditures) ESF funds may be use...

FINDING #2024-002: EDUCATION STABILIZATION FUNDS – EQUIPMENT AND OTHER CAPITAL EXPENDITURES (50000) Program Name: Elementary and Secondary School Emergency Relief II (ESSER II) Fund Assistance Listing Number: 84.425 Pass-Through Agency: California Department of Education (CDE) Federal Agency: U.S. Department of Education Criteria: Consistent with 2 CFR section 200.311 (real property), section 200.313 (equipment), and section 200.439 (equipment and other capital expenditures) ESF funds may be used to purchase equipment. Capital expenditures for general and special purpose equipment purchases are subject to prior approval by ED or the pass-through entity. Condition: Through testing of a representative sample of ESF expenditures, we noted that the equipment expenditures with Data Impressions in the amount totaling $617,023, did not appear to be pre-approved by the California Department of Education (CDE). Context: The condition was identified through the testing of ESF expenditures. Cause: District oversight. Effect: The funds spent on these purchases may be subject to review by or return to the awarding agency. Questioned Costs: $617,023. Repeat Finding: This is not a repeat finding. Recommendation: We recommend that the District obtain prior approval from CDE for all capital purchases from the Education Stabilization Fund in excess of $5,000. Views of Responsible Officials: See Corrective Action Plan on following page.

FY End: 2024-06-30
Compton Unified School District
Compliance Requirement: AB
FINDING #2024-002: EDUCATION STABILIZATION FUNDS – EQUIPMENT AND OTHER CAPITAL EXPENDITURES (50000) Program Name: Elementary and Secondary School Emergency Relief II (ESSER II) Fund Assistance Listing Number: 84.425 Pass-Through Agency: California Department of Education (CDE) Federal Agency: U.S. Department of Education Criteria: Consistent with 2 CFR section 200.311 (real property), section 200.313 (equipment), and section 200.439 (equipment and other capital expenditures) ESF funds may be use...

FINDING #2024-002: EDUCATION STABILIZATION FUNDS – EQUIPMENT AND OTHER CAPITAL EXPENDITURES (50000) Program Name: Elementary and Secondary School Emergency Relief II (ESSER II) Fund Assistance Listing Number: 84.425 Pass-Through Agency: California Department of Education (CDE) Federal Agency: U.S. Department of Education Criteria: Consistent with 2 CFR section 200.311 (real property), section 200.313 (equipment), and section 200.439 (equipment and other capital expenditures) ESF funds may be used to purchase equipment. Capital expenditures for general and special purpose equipment purchases are subject to prior approval by ED or the pass-through entity. Condition: Through testing of a representative sample of ESF expenditures, we noted that the equipment expenditures with Data Impressions in the amount totaling $617,023, did not appear to be pre-approved by the California Department of Education (CDE). Context: The condition was identified through the testing of ESF expenditures. Cause: District oversight. Effect: The funds spent on these purchases may be subject to review by or return to the awarding agency. Questioned Costs: $617,023. Repeat Finding: This is not a repeat finding. Recommendation: We recommend that the District obtain prior approval from CDE for all capital purchases from the Education Stabilization Fund in excess of $5,000. Views of Responsible Officials: See Corrective Action Plan on following page.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.