Section 200.311 states that real property acquired with federal funds belongs to the recipient or subrecipient and must be used for its intended purpose as long as needed. When the property is no longer needed, the recipient must follow federal instructions for its disposition, which may include compensating the federal agency if they retain ownership.
View full section details →
FY End: 2024-09-30
American Soybean Association
Compliance Requirement: F
Criteria and Condition: Title to real property acquired or improved by non-federal entities under grants and cooperative agreements vests in the non-federal entity subject to the obligations and conditions specified in 2 CFR section 200.311 (2 CFR section 200.311(a)). Real property will be used for the originally authorized purpose as long as needed for that purpose, during which time the non-federal entity must not dispose of or encumber title to or other interests in the real property (2 CFR s...

Criteria and Condition: Title to real property acquired or improved by non-federal entities under grants and cooperative agreements vests in the non-federal entity subject to the obligations and conditions specified in 2 CFR section 200.311 (2 CFR section 200.311(a)). Real property will be used for the originally authorized purpose as long as needed for that purpose, during which time the non-federal entity must not dispose of or encumber title to or other interests in the real property (2 CFR section 200.311(b)). When real property is no longer needed for the originally authorized purpose, the non-federal entity must obtain disposition instructions from the federal awarding agency or the pass-through entity, as applicable. When real property is sold, sales procedures must be followed that provide for competition to the extent practicable and result in the highest possible return. If sold, non- federal entities must compensate the federal awarding agency for the portion of the net sales proceeds that represents the federal agency’s interest in the real property, which is the amount calculated by multiplying the current market value or sale proceeds by the federal agency’s participation in total project costs. If the property is retained, the non-federal entity must compensate the federal awarding agency for the federal portion of the current fair market value of the property. Disposition instructions may also provide for transfer of title to the federal awarding agency or a designated third party, in which case the non-federal entity is entitled to the non-federal interest in the property, which is calculated by multiplying the current market value or sale proceeds by the non-federal entity’s share in total project costs (2 CFR section 200.311(c)(3)). Context: A foreign office indicated that assets purchased with federal funds were disposed of, but were still included on the inventory listing. Cause: The federal awarding agency was not notified of the disposal of assets purchased with federal funds. Questioned Cost: No questioned costs. Effect: Assets no longer in service are included on the federal fixed asset listing. Recommendation: Fixed assets purchased with federal funds should be subject to regular inventory, with dispositions communicated to the federal agency. Classification: Compliance finding and control deficiency in internal controls.

FY End: 2024-09-30
American Soybean Association
Compliance Requirement: F
Criteria and Condition: Title to real property acquired or improved by non-federal entities under grants and cooperative agreements vests in the non-federal entity subject to the obligations and conditions specified in 2 CFR section 200.311 (2 CFR section 200.311(a)). Real property will be used for the originally authorized purpose as long as needed for that purpose, during which time the non-federal entity must not dispose of or encumber title to or other interests in the real property (2 CFR s...

Criteria and Condition: Title to real property acquired or improved by non-federal entities under grants and cooperative agreements vests in the non-federal entity subject to the obligations and conditions specified in 2 CFR section 200.311 (2 CFR section 200.311(a)). Real property will be used for the originally authorized purpose as long as needed for that purpose, during which time the non-federal entity must not dispose of or encumber title to or other interests in the real property (2 CFR section 200.311(b)). When real property is no longer needed for the originally authorized purpose, the non-federal entity must obtain disposition instructions from the federal awarding agency or the pass-through entity, as applicable. When real property is sold, sales procedures must be followed that provide for competition to the extent practicable and result in the highest possible return. If sold, non- federal entities must compensate the federal awarding agency for the portion of the net sales proceeds that represents the federal agency’s interest in the real property, which is the amount calculated by multiplying the current market value or sale proceeds by the federal agency’s participation in total project costs. If the property is retained, the non-federal entity must compensate the federal awarding agency for the federal portion of the current fair market value of the property. Disposition instructions may also provide for transfer of title to the federal awarding agency or a designated third party, in which case the non-federal entity is entitled to the non-federal interest in the property, which is calculated by multiplying the current market value or sale proceeds by the non-federal entity’s share in total project costs (2 CFR section 200.311(c)(3)). Context: A foreign office indicated that assets purchased with federal funds were disposed of, but were still included on the inventory listing. Cause: The federal awarding agency was not notified of the disposal of assets purchased with federal funds. Questioned Cost: No questioned costs. Effect: Assets no longer in service are included on the federal fixed asset listing. Recommendation: Fixed assets purchased with federal funds should be subject to regular inventory, with dispositions communicated to the federal agency. Classification: Compliance finding and control deficiency in internal controls.

FY End: 2024-09-30
City of Batesville, Mississippi
Compliance Requirement: F
Federal Program 23.002 - Appalachian Area Development 14.228 - Community Development Block Grants/State's Program Award Numbers ARC-20698 ARC-20699 CDBG Subgrant: 1137-21-111-PF-01 Federal Agency U.S. Department of Housing and Urban Development (HUD) Appalachian Regional Commission (ARC) Compliance Requirement Equipment and Real Property Management- 2 CFR §200.310-316 Type of Finding Internal Control over Compliance - Material Weakness Compliance - Noncompliance Questioned Costs None Criteria Pe...

Federal Program 23.002 - Appalachian Area Development 14.228 - Community Development Block Grants/State's Program Award Numbers ARC-20698 ARC-20699 CDBG Subgrant: 1137-21-111-PF-01 Federal Agency U.S. Department of Housing and Urban Development (HUD) Appalachian Regional Commission (ARC) Compliance Requirement Equipment and Real Property Management- 2 CFR §200.310-316 Type of Finding Internal Control over Compliance - Material Weakness Compliance - Noncompliance Questioned Costs None Criteria Per 2 CFR §200.310-316 and the 0MB Compliance Supplement, recipients of federal awards must: Maintain detailed property records including description, serial number, acquisition date, cost, location, and condition Conduct a physical inventory at least once every two years and reconcile results Safeguard assets from loss, damage, or theft File a Notice of Federal Interest for real property acquired with federal funds Follow disposition procedures outlined in 2 CFR §200.311-313 Condition The City of Batesville did not conduct a biennial physical inventory of federally funded equipment and real property as required by 2 CFR §200.313(d)(2). Inventory records were incomplete, decentralized, and lacked key data fields such as asset condition and federal funding source. Infrastructure assets funded by CDBG and ARC grants were not classified as real property, and no Notice of Federal Interest was filed. Additionally, the City could not demonstrate that federally funded assets were safeguarded or reconciled against disposals. Cause The City lacked centralized oversight and formal policies for property management. Staff were unaware of federal requirements related to infrastructure classification and inventory procedures. No training or monitoring mechanisms were in place to ensure compliance. Effect The City is at risk of noncompliance with federal property management standards, including failure to conduct biennial inventories and file Notices of Federal Interest for real property. Although the sewer infrastructure funded by CFDA 14.228 and 23.002 is not susceptible to theft or loss due to its fixed nature, the lack of documentation and oversight represents a material weakness in internal control. No questioned costs were identified, as all expenditures were supported and the assets remain in use. Although Assistance Listing 90.201 was not selected for audit, similar deficiencies in property management were observed during preliminary review, suggesting the issue may be systemic across federal programs. Recommendation Implement a centralized inventory system with required data fields Conduct and document biennial physical inventories File Notices of Federal Interest for applicable real property Provide staff training on federal property standards Deveiop written policies for asset classification, inventory, and disposition Establish internal monitoring procedures to ensure ongoing compliance Views of Responsible Officials Management concurs with the finding. The City will implement a centralized inventory system and conduct a physical inventory by March 31, 2026. Training will be provided to relevant staff, and a formal policy will be adopted to ensure compliance with 2 CFR §200.310-316. The City will consult with HUD and ARC regarding the filing of Notices of Federal Interest for infrastructure assets. Management also acknowledges that similar issues were observed in non-audited programs and will extend corrective actions City-wide.

FY End: 2024-06-30
Compton Unified School District
Compliance Requirement: AB
FINDING #2024-002: EDUCATION STABILIZATION FUNDS – EQUIPMENT AND OTHER CAPITAL EXPENDITURES (50000) Program Name: Elementary and Secondary School Emergency Relief II (ESSER II) Fund Assistance Listing Number: 84.425 Pass-Through Agency: California Department of Education (CDE) Federal Agency: U.S. Department of Education Criteria: Consistent with 2 CFR section 200.311 (real property), section 200.313 (equipment), and section 200.439 (equipment and other capital expenditures) ESF funds may be use...

FINDING #2024-002: EDUCATION STABILIZATION FUNDS – EQUIPMENT AND OTHER CAPITAL EXPENDITURES (50000) Program Name: Elementary and Secondary School Emergency Relief II (ESSER II) Fund Assistance Listing Number: 84.425 Pass-Through Agency: California Department of Education (CDE) Federal Agency: U.S. Department of Education Criteria: Consistent with 2 CFR section 200.311 (real property), section 200.313 (equipment), and section 200.439 (equipment and other capital expenditures) ESF funds may be used to purchase equipment. Capital expenditures for general and special purpose equipment purchases are subject to prior approval by ED or the pass-through entity. Condition: Through testing of a representative sample of ESF expenditures, we noted that the equipment expenditures with Data Impressions in the amount totaling $617,023, did not appear to be pre-approved by the California Department of Education (CDE). Context: The condition was identified through the testing of ESF expenditures. Cause: District oversight. Effect: The funds spent on these purchases may be subject to review by or return to the awarding agency. Questioned Costs: $617,023. Repeat Finding: This is not a repeat finding. Recommendation: We recommend that the District obtain prior approval from CDE for all capital purchases from the Education Stabilization Fund in excess of $5,000. Views of Responsible Officials: See Corrective Action Plan on following page.

FY End: 2024-06-30
Compton Unified School District
Compliance Requirement: AB
FINDING #2024-002: EDUCATION STABILIZATION FUNDS – EQUIPMENT AND OTHER CAPITAL EXPENDITURES (50000) Program Name: Elementary and Secondary School Emergency Relief II (ESSER II) Fund Assistance Listing Number: 84.425 Pass-Through Agency: California Department of Education (CDE) Federal Agency: U.S. Department of Education Criteria: Consistent with 2 CFR section 200.311 (real property), section 200.313 (equipment), and section 200.439 (equipment and other capital expenditures) ESF funds may be use...

FINDING #2024-002: EDUCATION STABILIZATION FUNDS – EQUIPMENT AND OTHER CAPITAL EXPENDITURES (50000) Program Name: Elementary and Secondary School Emergency Relief II (ESSER II) Fund Assistance Listing Number: 84.425 Pass-Through Agency: California Department of Education (CDE) Federal Agency: U.S. Department of Education Criteria: Consistent with 2 CFR section 200.311 (real property), section 200.313 (equipment), and section 200.439 (equipment and other capital expenditures) ESF funds may be used to purchase equipment. Capital expenditures for general and special purpose equipment purchases are subject to prior approval by ED or the pass-through entity. Condition: Through testing of a representative sample of ESF expenditures, we noted that the equipment expenditures with Data Impressions in the amount totaling $617,023, did not appear to be pre-approved by the California Department of Education (CDE). Context: The condition was identified through the testing of ESF expenditures. Cause: District oversight. Effect: The funds spent on these purchases may be subject to review by or return to the awarding agency. Questioned Costs: $617,023. Repeat Finding: This is not a repeat finding. Recommendation: We recommend that the District obtain prior approval from CDE for all capital purchases from the Education Stabilization Fund in excess of $5,000. Views of Responsible Officials: See Corrective Action Plan on following page.

FY End: 2024-06-30
Compton Unified School District
Compliance Requirement: AB
FINDING #2024-002: EDUCATION STABILIZATION FUNDS – EQUIPMENT AND OTHER CAPITAL EXPENDITURES (50000) Program Name: Elementary and Secondary School Emergency Relief II (ESSER II) Fund Assistance Listing Number: 84.425 Pass-Through Agency: California Department of Education (CDE) Federal Agency: U.S. Department of Education Criteria: Consistent with 2 CFR section 200.311 (real property), section 200.313 (equipment), and section 200.439 (equipment and other capital expenditures) ESF funds may be use...

FINDING #2024-002: EDUCATION STABILIZATION FUNDS – EQUIPMENT AND OTHER CAPITAL EXPENDITURES (50000) Program Name: Elementary and Secondary School Emergency Relief II (ESSER II) Fund Assistance Listing Number: 84.425 Pass-Through Agency: California Department of Education (CDE) Federal Agency: U.S. Department of Education Criteria: Consistent with 2 CFR section 200.311 (real property), section 200.313 (equipment), and section 200.439 (equipment and other capital expenditures) ESF funds may be used to purchase equipment. Capital expenditures for general and special purpose equipment purchases are subject to prior approval by ED or the pass-through entity. Condition: Through testing of a representative sample of ESF expenditures, we noted that the equipment expenditures with Data Impressions in the amount totaling $617,023, did not appear to be pre-approved by the California Department of Education (CDE). Context: The condition was identified through the testing of ESF expenditures. Cause: District oversight. Effect: The funds spent on these purchases may be subject to review by or return to the awarding agency. Questioned Costs: $617,023. Repeat Finding: This is not a repeat finding. Recommendation: We recommend that the District obtain prior approval from CDE for all capital purchases from the Education Stabilization Fund in excess of $5,000. Views of Responsible Officials: See Corrective Action Plan on following page.

FY End: 2024-06-30
Compton Unified School District
Compliance Requirement: AB
FINDING #2024-002: EDUCATION STABILIZATION FUNDS – EQUIPMENT AND OTHER CAPITAL EXPENDITURES (50000) Program Name: Elementary and Secondary School Emergency Relief II (ESSER II) Fund Assistance Listing Number: 84.425 Pass-Through Agency: California Department of Education (CDE) Federal Agency: U.S. Department of Education Criteria: Consistent with 2 CFR section 200.311 (real property), section 200.313 (equipment), and section 200.439 (equipment and other capital expenditures) ESF funds may be use...

FINDING #2024-002: EDUCATION STABILIZATION FUNDS – EQUIPMENT AND OTHER CAPITAL EXPENDITURES (50000) Program Name: Elementary and Secondary School Emergency Relief II (ESSER II) Fund Assistance Listing Number: 84.425 Pass-Through Agency: California Department of Education (CDE) Federal Agency: U.S. Department of Education Criteria: Consistent with 2 CFR section 200.311 (real property), section 200.313 (equipment), and section 200.439 (equipment and other capital expenditures) ESF funds may be used to purchase equipment. Capital expenditures for general and special purpose equipment purchases are subject to prior approval by ED or the pass-through entity. Condition: Through testing of a representative sample of ESF expenditures, we noted that the equipment expenditures with Data Impressions in the amount totaling $617,023, did not appear to be pre-approved by the California Department of Education (CDE). Context: The condition was identified through the testing of ESF expenditures. Cause: District oversight. Effect: The funds spent on these purchases may be subject to review by or return to the awarding agency. Questioned Costs: $617,023. Repeat Finding: This is not a repeat finding. Recommendation: We recommend that the District obtain prior approval from CDE for all capital purchases from the Education Stabilization Fund in excess of $5,000. Views of Responsible Officials: See Corrective Action Plan on following page.

FY End: 2024-06-30
Compton Unified School District
Compliance Requirement: AB
FINDING #2024-002: EDUCATION STABILIZATION FUNDS – EQUIPMENT AND OTHER CAPITAL EXPENDITURES (50000) Program Name: Elementary and Secondary School Emergency Relief II (ESSER II) Fund Assistance Listing Number: 84.425 Pass-Through Agency: California Department of Education (CDE) Federal Agency: U.S. Department of Education Criteria: Consistent with 2 CFR section 200.311 (real property), section 200.313 (equipment), and section 200.439 (equipment and other capital expenditures) ESF funds may be use...

FINDING #2024-002: EDUCATION STABILIZATION FUNDS – EQUIPMENT AND OTHER CAPITAL EXPENDITURES (50000) Program Name: Elementary and Secondary School Emergency Relief II (ESSER II) Fund Assistance Listing Number: 84.425 Pass-Through Agency: California Department of Education (CDE) Federal Agency: U.S. Department of Education Criteria: Consistent with 2 CFR section 200.311 (real property), section 200.313 (equipment), and section 200.439 (equipment and other capital expenditures) ESF funds may be used to purchase equipment. Capital expenditures for general and special purpose equipment purchases are subject to prior approval by ED or the pass-through entity. Condition: Through testing of a representative sample of ESF expenditures, we noted that the equipment expenditures with Data Impressions in the amount totaling $617,023, did not appear to be pre-approved by the California Department of Education (CDE). Context: The condition was identified through the testing of ESF expenditures. Cause: District oversight. Effect: The funds spent on these purchases may be subject to review by or return to the awarding agency. Questioned Costs: $617,023. Repeat Finding: This is not a repeat finding. Recommendation: We recommend that the District obtain prior approval from CDE for all capital purchases from the Education Stabilization Fund in excess of $5,000. Views of Responsible Officials: See Corrective Action Plan on following page.

FY End: 2024-06-30
Compton Unified School District
Compliance Requirement: AB
FINDING #2024-002: EDUCATION STABILIZATION FUNDS – EQUIPMENT AND OTHER CAPITAL EXPENDITURES (50000) Program Name: Elementary and Secondary School Emergency Relief II (ESSER II) Fund Assistance Listing Number: 84.425 Pass-Through Agency: California Department of Education (CDE) Federal Agency: U.S. Department of Education Criteria: Consistent with 2 CFR section 200.311 (real property), section 200.313 (equipment), and section 200.439 (equipment and other capital expenditures) ESF funds may be use...

FINDING #2024-002: EDUCATION STABILIZATION FUNDS – EQUIPMENT AND OTHER CAPITAL EXPENDITURES (50000) Program Name: Elementary and Secondary School Emergency Relief II (ESSER II) Fund Assistance Listing Number: 84.425 Pass-Through Agency: California Department of Education (CDE) Federal Agency: U.S. Department of Education Criteria: Consistent with 2 CFR section 200.311 (real property), section 200.313 (equipment), and section 200.439 (equipment and other capital expenditures) ESF funds may be used to purchase equipment. Capital expenditures for general and special purpose equipment purchases are subject to prior approval by ED or the pass-through entity. Condition: Through testing of a representative sample of ESF expenditures, we noted that the equipment expenditures with Data Impressions in the amount totaling $617,023, did not appear to be pre-approved by the California Department of Education (CDE). Context: The condition was identified through the testing of ESF expenditures. Cause: District oversight. Effect: The funds spent on these purchases may be subject to review by or return to the awarding agency. Questioned Costs: $617,023. Repeat Finding: This is not a repeat finding. Recommendation: We recommend that the District obtain prior approval from CDE for all capital purchases from the Education Stabilization Fund in excess of $5,000. Views of Responsible Officials: See Corrective Action Plan on following page.

FY End: 2024-06-30
Compton Unified School District
Compliance Requirement: AB
FINDING #2024-002: EDUCATION STABILIZATION FUNDS – EQUIPMENT AND OTHER CAPITAL EXPENDITURES (50000) Program Name: Elementary and Secondary School Emergency Relief II (ESSER II) Fund Assistance Listing Number: 84.425 Pass-Through Agency: California Department of Education (CDE) Federal Agency: U.S. Department of Education Criteria: Consistent with 2 CFR section 200.311 (real property), section 200.313 (equipment), and section 200.439 (equipment and other capital expenditures) ESF funds may be use...

FINDING #2024-002: EDUCATION STABILIZATION FUNDS – EQUIPMENT AND OTHER CAPITAL EXPENDITURES (50000) Program Name: Elementary and Secondary School Emergency Relief II (ESSER II) Fund Assistance Listing Number: 84.425 Pass-Through Agency: California Department of Education (CDE) Federal Agency: U.S. Department of Education Criteria: Consistent with 2 CFR section 200.311 (real property), section 200.313 (equipment), and section 200.439 (equipment and other capital expenditures) ESF funds may be used to purchase equipment. Capital expenditures for general and special purpose equipment purchases are subject to prior approval by ED or the pass-through entity. Condition: Through testing of a representative sample of ESF expenditures, we noted that the equipment expenditures with Data Impressions in the amount totaling $617,023, did not appear to be pre-approved by the California Department of Education (CDE). Context: The condition was identified through the testing of ESF expenditures. Cause: District oversight. Effect: The funds spent on these purchases may be subject to review by or return to the awarding agency. Questioned Costs: $617,023. Repeat Finding: This is not a repeat finding. Recommendation: We recommend that the District obtain prior approval from CDE for all capital purchases from the Education Stabilization Fund in excess of $5,000. Views of Responsible Officials: See Corrective Action Plan on following page.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
State of North Dakota
Compliance Requirement: M
CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as require...

CONDITION The Department of Public Instruction did not ensure all subrecipients submitted a Single Audit Report or a form identifying a Single Audit is not required. In addition, The Department of Public Instruction did not issue management decisions on audit findings within 6 months or ensure that timely and appropriate corrective action was taken in all applicable instances. CRITERIA 2 CFR 200.331(f) states that a pass-through entity must verify that every subrecipient is audited as required by 2 CFS 200 Subpart F. 2 CFR 200.311(d)(2) states that a pass-through entity must ensure subrecipients take timely and appropriate action on all deficiencies pertaining to the Federal award provided to the subrecipient from the pass-through entity through audits, on-site reviews, and other means. 2 CFR 200.521(d) states that a pass-through entity must issue a management decision within six months of acceptance of the audit report by the Federal Audit Clearinghouse (FAC). 2 CFR 200.303(a) states that non-federal entities must establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with statutes, regulations, and the terms and condition of the federal award. CAUSE The Department of Public Instruction maintains a spreadsheet to track all subrecipient audit report monitoring, however, they did not ensure that everyone on the spreadsheet provided a Single Audit report, or review the filed report within 6 months, or provided a certification of total federal expenditures. EFFECT Subrecipients spending more than $750,000 from all federal sources may not be obtaining audits as required or may not be implementing a corrective action plan in a timely manner if findings are noted in audits that were completed. The Department of Public instruction is not meeting the requirements of 2 CFR 200 Subpart F. CONTEXT The total number of subrecipients was 536 and the total amount received from the Department of Public Instruction was $667,731,290. Where sampling was performed, the audit used a non-statistical sampling method. Of all the subrecipients that had errors, the total amount they received from the Department of Public Instruction was $53,403,270. Sixty subrecipients that received funds from the Department of Public Instruction were included in our sampling. One subrecipient was not included on the Departments tracking spreadsheet, two subrecipients did not received the required audit as required by 2 CFR Subpart F. 10 Subrecipients had reports filed, but the Department did not review the report within the required 6 month window. IDENTIFICATION AS A REPEAT FINDING Finding 2022-033 was reported in the immediate prior year. Findings 2020-021 and 2018-041 were reported in previous years. The prior audit finding was reported as implemented on the summary schedule of prior audit findings. This materially misrepresents the status of the finding. RECOMMENDATION We recommend the Department of Public Instruction: • Ensure all subrecipients obtain audits in accordance with 2 CFR 200 Subpart F if they meet the requirements; • Issue management decisions within a timely manner; • Ensure subrecipients took timely corrective action on deficiencies identified in the audits. DEPARTMENT OF PUBLIC INSTRUCTION RESPONSE The Department of Public Instruction agrees with the finding. See “Management’s Response and Corrective Action” section of this report.

FY End: 2024-06-30
Belcourt Public School District #7
Compliance Requirement: F
Assistance Listing Number 84.425 Education Stabilization Fund Department of Education Passed Through North Dakota Department of Public Instruction Passed Through Turtle Mountain Band of Chippewa Indians Equipment/Real Property Management Criteria 2 CFR sections 200.313(c) and (e) includes a requirement for the non-federal entity to not encumber the equipment without prior approval of the federal awarding agency. 2 CFR section 200.311 includes a requirement for the non-federal entity, with prior ...

Assistance Listing Number 84.425 Education Stabilization Fund Department of Education Passed Through North Dakota Department of Public Instruction Passed Through Turtle Mountain Band of Chippewa Indians Equipment/Real Property Management Criteria 2 CFR sections 200.313(c) and (e) includes a requirement for the non-federal entity to not encumber the equipment without prior approval of the federal awarding agency. 2 CFR section 200.311 includes a requirement for the non-federal entity, with prior approval by the ED or passthrough entity, may also use ESF funds to purchase real property, perform construction or minor remodeling, and for improvements to land, buildings, or equipment. Condition The District did not obtain prior approval for equipment acquisition or construction projects. Context Per discussion with the District staff and review of program expenditures, there were 19 capital asset acquisitions during the year, we tested all of them for prior state approval. One purchase was approved by the state after the purchase was made. Seven purchases were made without prior state approval. Cause The District did not properly submit for prior approval for equipment acquisition or construction until after the expenditure had been incurred and in some instances there were no submissions for prior approval. Effect The District may have purchased capital items that were not allowed by the State. Questioned Costs Undeterminable. Repeat Finding See prior year finding 2023-004. Recommendation We recommend the District to review all compliance requirements of federal programs to ensure they have procedures to ensure compliance with those requirements and for the requests for acquisition to be made timely and for the appropriate expenditure amount. Management’s Response See corrective action plan.