Corrective Action Plans

Browse how organizations respond to audit findings

Total CAPs
59,925
In database
Filtered Results
9,404
Matching current filters
Showing Page
97 of 377
25 per page

Filters

Clear
Active filters: § 200.303
2024-004: Material Weakness and Noncompliance – Written Policies Required by the Uniform Guidance Statement of Condition/Criteria: The County does not have written policies and procedures to implement the requirements of 2 CFR section 200 for the administration of federal awards. 2 CFR 200.303(a) e...
2024-004: Material Weakness and Noncompliance – Written Policies Required by the Uniform Guidance Statement of Condition/Criteria: The County does not have written policies and procedures to implement the requirements of 2 CFR section 200 for the administration of federal awards. 2 CFR 200.303(a) establishes that the auditee must establish and maintain effective internal controls over the federal awards that provide assurance that the entity is managing the federal awards in compliance with federal statutes, regulations, and the conditions of the federal award. Planned Corrective Action: County management will develop written policies and procedures for grants.
2024-003: Material Weakness and Noncompliance – Preparation of Schedule of Expenditures of Federal Awards (SEFA) Statement of Condition/Criteria: The Code of Federal Regulations requires a non-federal entity to prepare a schedule of expenditures of federal awards (SEFA) for the period covered by th...
2024-003: Material Weakness and Noncompliance – Preparation of Schedule of Expenditures of Federal Awards (SEFA) Statement of Condition/Criteria: The Code of Federal Regulations requires a non-federal entity to prepare a schedule of expenditures of federal awards (SEFA) for the period covered by the auditee’s financial statements which must include the total Federal awards expended as determined in accordance with CFR Section 200.502(a) and must reconcile amounts reported in the SEFA to the amounts reported in the auditee’s financial statements. Planned Corrective Action: County management will develop a closing process to ensure all federal expenditures are identified, recorded, and reconciled on the SEFA.
Federal Agency Name: Department of Agriculture Program Name: Communities Facilities Loans and Grants Federal Financial Assistance Listing Number: 10.766 Finding Summary: As a part of the audit process, a reclassification entry was made to move the funds from the cash sweep general fund to a separa...
Federal Agency Name: Department of Agriculture Program Name: Communities Facilities Loans and Grants Federal Financial Assistance Listing Number: 10.766 Finding Summary: As a part of the audit process, a reclassification entry was made to move the funds from the cash sweep general fund to a separate bookkeeping account. Management did not track the funds in a separate bank or bookkeeping account throughout the year. The Hospital had excess cash available to cover the required reserve amount for the fiscal year. Responsible Individuals: Renae Karst, Chief Financial Officer Corrective Action Plan: Management will establish a separate bookkeeping account in the general ledger to establish the correct reserve amount of cash held within its general operating bank account. The separate bookkeeping account will be utilized throughout the year to ensure the reserve requirement is met. The reserve account will be part of total cash in the bank to maximize interest earned on the reserve balance. Anticipated Completion Date: October 1, 2024.
Condition: The Board could not provide a copy, with supporting documentation, of the annual required information submission to the Alabama Department of Education for the federal program. Planned Corrective Action: The Board will keep a copy of all annual required federal programs submission and sup...
Condition: The Board could not provide a copy, with supporting documentation, of the annual required information submission to the Alabama Department of Education for the federal program. Planned Corrective Action: The Board will keep a copy of all annual required federal programs submission and supporting documentation to the Alabama State Department of Education. Anticipated Completion Date: Effective immediately Point of Contact: Gwendolyn Rogers
Finding 2024-004 Federal Grantor: United States Department of Health and Human Services Planned Corrective Actions: Management will improve internal controls to include the documentation and retention of approval on all supply expenditures and the annual fringe benefit analysis. Responsible Offici...
Finding 2024-004 Federal Grantor: United States Department of Health and Human Services Planned Corrective Actions: Management will improve internal controls to include the documentation and retention of approval on all supply expenditures and the annual fringe benefit analysis. Responsible Official – Dawn Ksepka, VP of Finance and System Controller Anticipated completion date –August 2025 Management agrees with the finding. Remediation: The accounting manager reviewed and approved the updated 2025 fringe benefit analysis with 2024 actuals on February 28, 2025. Upon finalization of the 2025 budget, the analysis will be revised and reviewed again. Accounting will collect evidence of review and approval of supply expenditure throughout the year to ensure proper retention of the documentation.
Finding 2024-003 Federal Grantor: United States Department of Health and Human Services Planned Corrective Actions: Monthly Suspension and Debarment files will be reviewed, and documented approval will be retained within the monthly files. Responsible Official – Dawn Ksepka, VP of Finance and Syst...
Finding 2024-003 Federal Grantor: United States Department of Health and Human Services Planned Corrective Actions: Monthly Suspension and Debarment files will be reviewed, and documented approval will be retained within the monthly files. Responsible Official – Dawn Ksepka, VP of Finance and System Controller Anticipated completion date –June 30, 2025 Management agrees with the finding. Remediation: Starting June 2025, the monthly suspension and debarment file will be reviewed. A signed statement confirming its accuracy will be included post-review. The accounts payable standard work document will be updated accordingly.
Finding 2024-002 Federal Grantor: United States Department of Health and Human Services Planned Corrective Actions: Responsible Official – Dawn Ksepka, VP of Finance and System Controller Anticipated completion date – July 31, 2025 Management agrees with the finding. Remediation: Fairview update...
Finding 2024-002 Federal Grantor: United States Department of Health and Human Services Planned Corrective Actions: Responsible Official – Dawn Ksepka, VP of Finance and System Controller Anticipated completion date – July 31, 2025 Management agrees with the finding. Remediation: Fairview updated its internal control processes to better retain and document sole source procurement justification before entering vendor agreements. A standard form for sole source justification will be implemented to enhance documentation.
Finding 2024-001 Federal Grantor: United States Department of Health and Human Services Planned Corrective Actions: Responsible Official – Dawn Ksepka, VP of Finance and System Controller Anticipated completion date – April 15, 2025 Management agrees with the finding. Remediation: The FFATA repo...
Finding 2024-001 Federal Grantor: United States Department of Health and Human Services Planned Corrective Actions: Responsible Official – Dawn Ksepka, VP of Finance and System Controller Anticipated completion date – April 15, 2025 Management agrees with the finding. Remediation: The FFATA report was filed on April 15, 2025. Fairview has established an internal control to ensure timely filing of FFATA reports in the future.
The METRO Vanpool Department, in collaboration with the Grant Programs Administration Division, has initiated actions to strengthen internal controls and improve compliance with federal cost principles. These actions include: • Updating existing policies and procedures related to grant-funded expens...
The METRO Vanpool Department, in collaboration with the Grant Programs Administration Division, has initiated actions to strengthen internal controls and improve compliance with federal cost principles. These actions include: • Updating existing policies and procedures related to grant-funded expense transactions; • Developing guidance to ensure transactions are appropriately reviewed for allowability, allocability, and reasonableness; • Enhancing training for relevant personnel to reinforce understanding and application of award-specific terms and conditions; • Ensuring compliance with 2 CFR § 200.403 and § 200.303. These process improvements and control enhancements will be finalized and implemented no later than December 31, 2025, under the direction of the Director, Commuter Services. METRO believes these steps will ensure compliance and mitigate recurrence of similar findings in future audit periods.
View Audit 360643 Questioned Costs: $1
Finding 568859 (2024-002)
Significant Deficiency 2024
Town will no longer be holding invoices until ARPA funding is received but will follow the reimbursement guidelines per the grant agreement. April 30th 2025 anticipated completion date. James A. Sullivan Mayor
Town will no longer be holding invoices until ARPA funding is received but will follow the reimbursement guidelines per the grant agreement. April 30th 2025 anticipated completion date. James A. Sullivan Mayor
MANAGEMENT’S CORRECTIVE ACTION PLAN Finding Number: 2024-001 Planned Corrective Action: We concur with the finding. We will continue with retaining documentation of sliding scale determination electronically. The CFO will continue to monitor whether the record retention policy is being followed. Ant...
MANAGEMENT’S CORRECTIVE ACTION PLAN Finding Number: 2024-001 Planned Corrective Action: We concur with the finding. We will continue with retaining documentation of sliding scale determination electronically. The CFO will continue to monitor whether the record retention policy is being followed. Anticipated Completion Date: On-going Responsible Contact Person: Cynthia Diaz, Chief Financial Officer
Department of Health and Human Services Federal Financial Assistance Listing #93.498 COVID-19 Provider Relief Fund and American Rescue Plan (ARP) Rural Distribution (PRF) Applicable Federal Award Number and Year - Period 6 TIN #205330283 Activities Allowed or Unallowed and Allowable Costs/Cost Pri...
Department of Health and Human Services Federal Financial Assistance Listing #93.498 COVID-19 Provider Relief Fund and American Rescue Plan (ARP) Rural Distribution (PRF) Applicable Federal Award Number and Year - Period 6 TIN #205330283 Activities Allowed or Unallowed and Allowable Costs/Cost Principles Material Weakness in Internal Control Over Compliance Finding Summary: There was no formal review or approval of the expenditure spreadsheet used to calculate the expenditures claimed for the federal program outside of the preparer. In addition, we noted the individual transactions were also not reviewed or approved by someone outside of the business office manager. Responsible Individuals: Kathy Morrow, Business Office Manager, Kelly VandeVorste, Interim Administrator Corrective Action Plan: Management will ensure that the information contained in supporting spreadsheets and individual transactions for federal programs is reviewed and approved by someone other than the preparer or the person initiating the transactions. Anticipated Completion Date: December 31, 2025
Department of Health and Human Services Federal Financial Assistance Listing #93.498 COVID-19 Provider Relief Fund and American Rescue Plan (ARP) Rural Distribution (PRF) Applicable Federal Award Number and Year - Period 6 TIN #205330283 Reporting Material Weakness in Internal Control Over Complia...
Department of Health and Human Services Federal Financial Assistance Listing #93.498 COVID-19 Provider Relief Fund and American Rescue Plan (ARP) Rural Distribution (PRF) Applicable Federal Award Number and Year - Period 6 TIN #205330283 Reporting Material Weakness in Internal Control Over Compliance and Material Noncompliance Finding Summary: Rolette Community Care Center does not have an internal control system to ensure the amounts reported in the HHS Period 6 Special Report agreed to supporting documentation for each of the quarters included. In addition, there was no evidence of review of either the supporting documentation or the HHS Period 6 Special Report by someone other than the preparer. Responsible Individuals: Kathy Morrow, Business Office Manager Corrective Action Plan: Management will ensure that the information contained in the reports agrees to the supporting documentation and both documentation and the reports submitted are reviewed by someone other than the preparer. Anticipated Completion Date: December 31, 2025
Audit Report Reference: 2024-003 Program name: Research and Development Completion Date: September 30, 2025 Finding 2024-003 is a repeat finding (2023-001) from fiscal year end September 30, 2023. The Health System implemented change controls and audit of employee permissions per the corrective act...
Audit Report Reference: 2024-003 Program name: Research and Development Completion Date: September 30, 2025 Finding 2024-003 is a repeat finding (2023-001) from fiscal year end September 30, 2023. The Health System implemented change controls and audit of employee permissions per the corrective action plan for 2023-001.The corrective actions for repeat finding 2024-003 addresses documentation of performed controls and training for employees involved in the control activities. Workday Change Review: The HRIS team will continue with a change review audit as they have done in the previous year with a few enhancements to increase auditability. The Sr. HRIS Manager will send official communication to the HRIS team to initiate the end-of-year change review. This email will provide a clear timeline for the audit period with a hard deadline. Once complete, the HR Compliance Manager and/or the Sr. HRIS Manager will issue a written communication to document the completion of the review summary of findings (if any), and corrective actions taken (if applicable). This will remedy the issue of missing approval documentation. The team will also be reeducated around the need to document written approval and testing for changes throughout the year. Workday Security Review: The HRIS team will continue to conduct an audit of security roles and users within Workday to ensure that permissions are updated appropriately. The HRIS Analyst will generate reports for the Sr. HRIS Manager's review, identifying any required changes. The analyst will then make these updates in Workday, followed by a new report for verification. Upon successful verification, the Sr. HRIS Manager will send a formal written communication of the approved changes. Workday Terminations: To address the access provisioning deficiency as it relates to terminating employees, the management team will be re-trained in the importance of adhering to timely terminations of employees in Workday. Person Responsible: Ashley Cesarano - HR Compliance and Workplace Accommodations Manager; Karen Alvarado – Senior Manager HRIS E-mail address: Ashley.Cesarano@bmc.org; Karen.Alvarado@bmc.org
Person(s) responsible for corrective action: Todd Bolster, Director of Administration and Dietrich Schmitt, Grants Program Manager. Management’s Response/Corrective Action Plan: For this tribal pass-through program, narrative, non-financial progress reports are collected from tribes, reviewed and...
Person(s) responsible for corrective action: Todd Bolster, Director of Administration and Dietrich Schmitt, Grants Program Manager. Management’s Response/Corrective Action Plan: For this tribal pass-through program, narrative, non-financial progress reports are collected from tribes, reviewed and approved by the NWIFC Grants Program Manager and submitted to PSFMC. Effective immediately, the NWIFC grants program manager will increase internal controls by including documentation of internal review and approval prior to progress reports being submitted to PSMFC. Anticipated completion date: July 2025.
Person(s) responsible for corrective action: Lucy Yanez, Contract Specialist, Tracy Johnson, Accounts Payable, Tina Hurtado Controller, NWIFC staff and supervisors engaged in procurement and contracting. Management’s Response/Corrective Action Plan: The NWIFC implemented corrective measures relat...
Person(s) responsible for corrective action: Lucy Yanez, Contract Specialist, Tracy Johnson, Accounts Payable, Tina Hurtado Controller, NWIFC staff and supervisors engaged in procurement and contracting. Management’s Response/Corrective Action Plan: The NWIFC implemented corrective measures related to procurement in March of 2024. See FY23 Corrective Action Plan. However, the one procurement sample that was cited as not including “documentation of bidding, alternative price quotes or sole source documentation” contained a sole source justification that was developed before implementation of the FY23 Corrective Action Plan. The sole source justification was based on the specialized knowledge and specific expertise. Procurement samples for purchases or contracts after the implementation of the FY23 Corrective Action Plan, show compliance of adequate bidding, price quotes or sole source documentation consistent with 2 CFR 200. The NWIFC will continue to implement the FY23 Corrective Action Plan, by requiring NWIFC managers and their staff to be responsible for soliciting bids or developing sole source justifications for procurements and contracts consistent with 2 CFR 200. The Contract Specialist will ensure that bid solicitations and sole source justifications are properly documented and filed with each contract. Similarly, the audit noted that certain suspension and debarment samples selected, before the FY23 Corrective Action Plan was implemented in March 2024, lacked documentation of a suspension and debarment review prior to doing business with vendors. In response, the FY23 Corrective Action Plan, put into effect in March 2024, included measures to ensure that both new vendor and annual reviews are documented. The Accounts Payable department will continue to conduct suspension and debarment reviews for all new vendors before conducting business and perform annual reviews of all vendors, in line with the FY23 Corrective Action Plan. Anticipated completion date: Completed March 2024.
View Audit 360492 Questioned Costs: $1
Finding 2024-002 Condition: During the auditors’ walkthroughs of the cash draw process, the Organization indicated that there is a lack of evidence supporting preparation and review of federal drawdowns. Corrective action plan: Management agrees with the recommendation and will establish a written ...
Finding 2024-002 Condition: During the auditors’ walkthroughs of the cash draw process, the Organization indicated that there is a lack of evidence supporting preparation and review of federal drawdowns. Corrective action plan: Management agrees with the recommendation and will establish a written policy and implement a documented process for the preparation and review of federal drawdowns, including clear evidence of review such as signoffs or electronic approvals. Responsible Individual: Andres Chavarro, Finance Manager Planned Completion date: 07/01/2025
1) Effective 3/7/25, reports and requests for reimbursements are being reviewed, signed and dated by the Executive Director prior to submission to ensure the reports and requests for reimbursements are not incomplete or inaccurate; and 2) Financial Policy addressing the Deficiency in Internal Contro...
1) Effective 3/7/25, reports and requests for reimbursements are being reviewed, signed and dated by the Executive Director prior to submission to ensure the reports and requests for reimbursements are not incomplete or inaccurate; and 2) Financial Policy addressing the Deficiency in Internal Controls over Compliance were already in place during the audit period. These policies were reviewed by the Board of Directors on 6/11/25 and found to align with the best practices and compliance requirements. Following the audit, we have also taken steps to reinforce the adherence and ensure consistent implementation across all relevant areas. Responsible Parties: Brandi Senters, Finance Director, will be responsible for implementation, with oversight from Interim Executive Director, Bernie Jackson.
Management acknowledges the importance of maintaining accessible and complete documentation to support all transactions charged to federal grants. The inability to provide the requested approvals for certain transactions was due to the challenging security conditions in some country offices during t...
Management acknowledges the importance of maintaining accessible and complete documentation to support all transactions charged to federal grants. The inability to provide the requested approvals for certain transactions was due to the challenging security conditions in some country offices during the audit period. To strengthen documentation access and retention, the Organization has transitioned to NetSuite, where backup documentation for transactions is now stored centrally on the cloud and can be easily accessed by headquarters staff. This change enhances our ability to ensure timely review, approval, and audit readiness, regardless of field conditions. We remain committed to continuous improvement of our internal controls and documentation practices. Responsible Person: Country Finance Directors
Corrective Actions Taken or Planned: Create procedures by the type of required reporting by grantor, as necessary. The procedure will include what and how the required report will be completed, who will and/or should review the required report, including signature for proof, and when the required re...
Corrective Actions Taken or Planned: Create procedures by the type of required reporting by grantor, as necessary. The procedure will include what and how the required report will be completed, who will and/or should review the required report, including signature for proof, and when the required report should be completed. Procedures will be added to the accounting department procedures and shared with staff as necessary. This is a work in progress and will continue to be adjusted as necessary. Contact person(s) responsible for corrective action: Gina Brown, CFO Anticipated Completion Date: September 2025
Finding Number: 2024-001 Condition: The City lacked adequate controls to verify that expenditures charged to the grant were incurred within the proper period of performance. Transactions were processed without sufficient review or procedures around the period of performance, resulting in expenditur...
Finding Number: 2024-001 Condition: The City lacked adequate controls to verify that expenditures charged to the grant were incurred within the proper period of performance. Transactions were processed without sufficient review or procedures around the period of performance, resulting in expenditures being charged from outside the allowable timeframe. Planned Corrective Action: The City has worked with the State to identify expenses outside the period of performance. The City has sent the money back to the State that was before the performance start date. All balances are properly stated as of November 30. 2024. Contact person responsible for corrective action: Connie Kumpula Anticipated Completion Date: 5/23/2025
Finding 567881 (2024-056)
Significant Deficiency 2024
Finding 2024-056 Disaster Grants - Public Assistance (Presidentially Declared Disasters), ALN 97.036 - EM Grants Manager Security Management and Access Controls Management Views MSP agrees with the finding. MSP implemented the EM Grants Manager system in November 2023 and did not fully establish pr...
Finding 2024-056 Disaster Grants - Public Assistance (Presidentially Declared Disasters), ALN 97.036 - EM Grants Manager Security Management and Access Controls Management Views MSP agrees with the finding. MSP implemented the EM Grants Manager system in November 2023 and did not fully establish procedures for maintaining documentation of user access forms, reviewing privileged access, and disabling inactive users due to the number of current disasters and limited staff. Planned Corrective Action For part a., MSP implemented an access approval process in November 2023 to maintain documentation of access request forms within the EM Grants Manager system. For parts b. and c., MSP will create procedures to help ensure the timely completion of privileged user reviews and inactive user deactivation. MSP will perform the required user reviews and deactivate applicable accounts by September 30, 2025. Anticipated Completion Date September 30, 2025 Responsible Individual(s) Penny Burger, MSP
Finding 567697 (2024-026)
Significant Deficiency 2024
Finding 2024-026 Coronavirus State and Local Fiscal Recovery Funds, ALN 21.027 - Workfront Security Management and Access Controls Management Views DTMB agrees with the finding. Planned Corrective Action DTMB implemented process improvements in May 2024 related to the tracking and documentation of...
Finding 2024-026 Coronavirus State and Local Fiscal Recovery Funds, ALN 21.027 - Workfront Security Management and Access Controls Management Views DTMB agrees with the finding. Planned Corrective Action DTMB implemented process improvements in May 2024 related to the tracking and documentation of user access requests to support approval of user access and system roles. The exceptions cited are related to users whose access was granted prior to the improved documentation being implemented. Anticipated Completion Date Completed Responsible Individual(s) Jennifer Edmonds, DTMB
Finding 567696 (2024-025)
Significant Deficiency 2024
Finding 2024-025 Coronavirus State and Local Fiscal Recovery Funds, ALN 21.027 - Insufficient Respite Payment Controls Management Views MDHHS agrees with the finding. Planned Corrective Action During fiscal year 2024, MDHHS improved the payment review process prior to manual input into the Medic...
Finding 2024-025 Coronavirus State and Local Fiscal Recovery Funds, ALN 21.027 - Insufficient Respite Payment Controls Management Views MDHHS agrees with the finding. Planned Corrective Action During fiscal year 2024, MDHHS improved the payment review process prior to manual input into the Medical Services Administration Manual Payment System (MSAPay) to help ensure there are no improper payments, as demonstrated by no improper payments identified for fiscal year 2024. MDHHS will develop and implement a post payment review process for the final respite payments that were entered into MSAPay during December 2024 and anticipates completion by September 30, 2025. Anticipated Completion Date September 30, 2025 Responsible Individual(s) Crystal Kline, MDHHS Jessica Bowen, MDHHS Elaina Brown, MDHHS
Finding 567695 (2024-024)
Significant Deficiency 2024
Finding 2024-024 Coronavirus State and Local Fiscal Recovery Funds, ALN 21.027 - Grant Reimbursement Approval Procedures Management Views EGLE agrees with the finding. Planned Corrective Action The EGLE Water Resources Division’s (WRD) administration staff adjusted their review process in April 20...
Finding 2024-024 Coronavirus State and Local Fiscal Recovery Funds, ALN 21.027 - Grant Reimbursement Approval Procedures Management Views EGLE agrees with the finding. Planned Corrective Action The EGLE Water Resources Division’s (WRD) administration staff adjusted their review process in April 2024 to comply with overall EGLE guidance that all reimbursement requests should be reviewed by a program representative and financial representative to ensure payments are made for activities authorized by the grant agreement. However, WRD had not fully completed the retroactive review of payments for fiscal year 2024. This has since been corrected and all retroactive reviews to ensure compliance with program technical specifications were completed as of May 1, 2025. Anticipated Completion Date Completed Responsible Individual(s) Phil Argiroff, EGLE Amy Hicks, EGLE