Audit 6715

FY End
2023-06-30
Total Expended
$6.13M
Findings
0
Programs
1
Year: 2023 Accepted: 2023-12-14
Auditor: Redw LLC

Organization Exclusion Status:

Checking exclusion status...

Findings

No findings recorded

Programs

ALN Program Spent Major Findings
16.610 Regional Information Sharing Systems $6.13M Yes 0

Contacts

Name Title Type
KCRSYXVDFHN5 Sheri Ferguson Auditee
6232513303 Curtis Balls Auditor
No contacts on file

Notes to SEFA

Title: Basis of Presentation Accounting Policies: The accompanying schedule of expenditures of federal awards (the “Schedule”) includes the federal grant activity of Rocky Mountain Information Network and is presented on the accrual basis of accounting. The information in this schedule is presented in accordance with the requirements of Title 2 U.S. Code of Federal Regulations Part 200, Uniform Administrative Requirements, Cost Principles and Audit Requirements for Federal Awards (Uniform Guidance). De Minimis Rate Used: N Rate Explanation: The organization has one award, therefore there are no indirect costs The accompanying schedule of expenditures of federal awards includes the federal grant activity of Rocky Mountain Information Network, Inc. and is presented on the accrual basis of accounting. The information in this schedule is presented in accordance with the requirements of Title 2 U.S. Code of Federal Regulations (CFR) Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance). Therefore, some amounts presented in this schedule may differ from amounts presented in, or used in the preparation of, the financial statements.
Title: Federal Award Identification Number Accounting Policies: The accompanying schedule of expenditures of federal awards (the “Schedule”) includes the federal grant activity of Rocky Mountain Information Network and is presented on the accrual basis of accounting. The information in this schedule is presented in accordance with the requirements of Title 2 U.S. Code of Federal Regulations Part 200, Uniform Administrative Requirements, Cost Principles and Audit Requirements for Federal Awards (Uniform Guidance). De Minimis Rate Used: N Rate Explanation: The organization has one award, therefore there are no indirect costs The federal granting agency is responsible for providing RMIN with the Assistance Listing Number and program title for the grant or contract.
Title: Indirect Cost Rate Accounting Policies: The accompanying schedule of expenditures of federal awards (the “Schedule”) includes the federal grant activity of Rocky Mountain Information Network and is presented on the accrual basis of accounting. The information in this schedule is presented in accordance with the requirements of Title 2 U.S. Code of Federal Regulations Part 200, Uniform Administrative Requirements, Cost Principles and Audit Requirements for Federal Awards (Uniform Guidance). De Minimis Rate Used: N Rate Explanation: The organization has one award, therefore there are no indirect costs RMIN did not apply for or use an indirect cost rate. Therefore, the de minims rate of 10% was not used.
Title: Subrecipients Accounting Policies: The accompanying schedule of expenditures of federal awards (the “Schedule”) includes the federal grant activity of Rocky Mountain Information Network and is presented on the accrual basis of accounting. The information in this schedule is presented in accordance with the requirements of Title 2 U.S. Code of Federal Regulations Part 200, Uniform Administrative Requirements, Cost Principles and Audit Requirements for Federal Awards (Uniform Guidance). De Minimis Rate Used: N Rate Explanation: The organization has one award, therefore there are no indirect costs RMIN did not provide federal awards to subrecipients during the year ended June 30, 2023.