FY End
2022-12-31
Total Expended
$768,440
Findings
4
Programs
10
Year: 2022 Accepted: 2023-09-28

Organization Exclusion Status:

Checking exclusion status...

Contacts

Name Title Type
KCANXNR2P4M3 Dennis Skrajewski Auditee
4143086839 Erica Blumberg Auditor
No contacts on file

Notes to SEFA

Accounting Policies: Expenditures reported on the Schedule are reported on the accrual basis of accounting. Such expenditures are recognized following the cost principles contained in the Uniform Guidance, wherein certain types of expenditures are limited to reimbursement or grant stipulations. De Minimis Rate Used: N Rate Explanation: WAFCC has indirect rates that are directly negotiated with each funding source. Accordingly,WAFCC did not elect to use the 10% de minimis indirect cost rate.

Finding Details

2022-003 Significant Deficiency in Internal Control over Compliance Expense Approvals Federal Program Title: 93.268 ? Immunization Cooperative Agreements State Program Title: 435100-G24-113561-290 ? Immunization Program 435100-G22-VACCINECO-86 ? Vaccination Community Outreach 2.0 Criteria: In order to ensure compliance with Federal and State allowable costs/cost principles compliance requirements, WAFCC's internal control structure requires that all disbursements to subrecipients be approved by the Business Manager and Executive Director. Condition: As a result of our testing, we identified six subrecipient disbursements for which the required approvals were not documented. Effect: The disbursements made without documented approvals did appear to comply with applicable compliance requirements. However, disbursements could be made that are not in compliance with requirements if they are not properly approved in accordance with WAFCC's policies. Questioned Costs: None Recommendation: We recommend WAFCC document the approval process for each subrecipient disbursement to ensure compliance with applicable requirements. Repeat Finding: No Views of Responsible Officials: Subsequent to year end, the expense approval process has been updated. WAFCC now uses a shared drive to document and timestamp the approval process before expenses are disbursed.
2022-003 Significant Deficiency in Internal Control over Compliance Expense Approvals Federal Program Title: 93.268 ? Immunization Cooperative Agreements State Program Title: 435100-G24-113561-290 ? Immunization Program 435100-G22-VACCINECO-86 ? Vaccination Community Outreach 2.0 Criteria: In order to ensure compliance with Federal and State allowable costs/cost principles compliance requirements, WAFCC's internal control structure requires that all disbursements to subrecipients be approved by the Business Manager and Executive Director. Condition: As a result of our testing, we identified six subrecipient disbursements for which the required approvals were not documented. Effect: The disbursements made without documented approvals did appear to comply with applicable compliance requirements. However, disbursements could be made that are not in compliance with requirements if they are not properly approved in accordance with WAFCC's policies. Questioned Costs: None Recommendation: We recommend WAFCC document the approval process for each subrecipient disbursement to ensure compliance with applicable requirements. Repeat Finding: No Views of Responsible Officials: Subsequent to year end, the expense approval process has been updated. WAFCC now uses a shared drive to document and timestamp the approval process before expenses are disbursed.
2022-003 Significant Deficiency in Internal Control over Compliance Expense Approvals Federal Program Title: 93.268 ? Immunization Cooperative Agreements State Program Title: 435100-G24-113561-290 ? Immunization Program 435100-G22-VACCINECO-86 ? Vaccination Community Outreach 2.0 Criteria: In order to ensure compliance with Federal and State allowable costs/cost principles compliance requirements, WAFCC's internal control structure requires that all disbursements to subrecipients be approved by the Business Manager and Executive Director. Condition: As a result of our testing, we identified six subrecipient disbursements for which the required approvals were not documented. Effect: The disbursements made without documented approvals did appear to comply with applicable compliance requirements. However, disbursements could be made that are not in compliance with requirements if they are not properly approved in accordance with WAFCC's policies. Questioned Costs: None Recommendation: We recommend WAFCC document the approval process for each subrecipient disbursement to ensure compliance with applicable requirements. Repeat Finding: No Views of Responsible Officials: Subsequent to year end, the expense approval process has been updated. WAFCC now uses a shared drive to document and timestamp the approval process before expenses are disbursed.
2022-003 Significant Deficiency in Internal Control over Compliance Expense Approvals Federal Program Title: 93.268 ? Immunization Cooperative Agreements State Program Title: 435100-G24-113561-290 ? Immunization Program 435100-G22-VACCINECO-86 ? Vaccination Community Outreach 2.0 Criteria: In order to ensure compliance with Federal and State allowable costs/cost principles compliance requirements, WAFCC's internal control structure requires that all disbursements to subrecipients be approved by the Business Manager and Executive Director. Condition: As a result of our testing, we identified six subrecipient disbursements for which the required approvals were not documented. Effect: The disbursements made without documented approvals did appear to comply with applicable compliance requirements. However, disbursements could be made that are not in compliance with requirements if they are not properly approved in accordance with WAFCC's policies. Questioned Costs: None Recommendation: We recommend WAFCC document the approval process for each subrecipient disbursement to ensure compliance with applicable requirements. Repeat Finding: No Views of Responsible Officials: Subsequent to year end, the expense approval process has been updated. WAFCC now uses a shared drive to document and timestamp the approval process before expenses are disbursed.