Audit 413179

FY End
2023-12-31
Total Expended
$5.04M
Findings
1
Programs
5
Organization: City of Blaine, Mn (MN)
Year: 2023 Accepted: 2026-09-29

Organization Exclusion Status:

Checking exclusion status...

Findings

ID Ref Severity Repeat Requirement
1238302 2023-002 Material Weakness Yes P

Programs

Contacts

Name Title Type
LAKYD6YNJHJ9 Jason Zimmerman Auditee
7637172677 Andy Hering Auditor
No contacts on file

Notes to SEFA

The accompanying schedule of expenditures of federal awards (the Schedule) includes the federal award activity of City of Blaine, Minnesota for the year ended December 31, 2023. The information in this Schedule is presented in accordance with the requirements of Title 2 U.S. Code of Federal Regulations Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance). Therefore, some amounts presented in this schedule may differ from amounts presented in, or used in the presentation of, the financial statements.
The City of Blaine, Minnesota did not pass any federal funds to subrecipients during 2023.
Subsequent to the issuance of our report dated September 12, 2024, the City of Blaine, Minnesota discovered that it had mistakenly excluded federal funding received and expended from the State of Minnesota under the Highway Planning and Construction (Federal-Aid Highway Program) in the amount of $935,584. The City of Blaine, Minnesota revised the Schedule of Expenditures of Federal Awards previously reported to reflect correction of this error. Our audit opinion is not modified as a result of this change.

Finding Details

Criteria: The Schedule of Expenditures of Federal Awards reported for the year under audit must reflect actual federal expenditures. Per 2 CFR 200.510(b) Schedule of expenditures of Federal awards, “the auditee must also prepare a schedule of expenditures of Federal awards for the period covered by the auditee's financial statements which must include the total Federal awards expended as determined in accordance with 2 CFR 200.502, Basis for determining Federal awards expended. 2 CFR 200.502(a) Determining Federal awards expended, states that “the determination of when a Federal award is expended must be based on when the activity related to the Federal award occurs.” Condition: Federal expenditures were not correctly reported on the City of Blaine, Minnesota’s 2023 SEFA included in the original audit report dated September 12, 2024. Subsequent to the original audit report issuance dated September 12, 2024, it was determined that $935,584 of expenditures relating to a subrecipient grant from the State of Minnesota under the Highway Planning and Construction (Federal-Aid Highway Program) were not included on the SEFA. Cause: Sufficient internal controls were not in place to ensure proper recognition of contractor versus subrecipient relationships for federal funds received through pass-through entities. Questioned Costs: None. Effect: By not having proper controls over SEFA preparation, there is a risk that the SEFA will not reflect all the federal awards subject to the Uniform Guidance. The total change in federal expenditures reported on the SEFA was $935,584. Context: The City considered itself to have a contractor relationship with the State of Minnesota under Federal Project # HSIP 0223 (118), DCP Agreement #1050395, instead of a subrecipient relationship; therefore, these funds were excluded from the SEFA. However, per subsequent review of grant documentation and communications with the State, it was determined the City was a subrecipient of federal funds under this project. Recommendation: We recommend that the City of Blaine, Minnesota review procedures to ensure timely identification of federal funds, including the clear distinction between subrecipient and contractor relationships for all contract and grant agreements involving federal funds, and verify any changes are properly communicated. In situations where the relationship is unclear, we recommend City staff contact the pass-through entity for clarification. Views of Responsible Officials and Planned Corrective Actions: Management agrees with this finding and has developed internal controls to ensure timely identification of federal funds including identifying whether the City is a subrecipient and contractor when receiving funds. Additional details can be found in the City of Blaine, Minnesota’s Corrective Action Plan.