Audit 404271

FY End
2025-03-31
Total Expended
$1.30M
Findings
2
Programs
2
Year: 2025 Accepted: 2026-06-22
Auditor: JOHN FLUSCHE CPA

Organization Exclusion Status:

Checking exclusion status...

Findings

ID Ref Severity Repeat Requirement
1218089 2025-001 Material Weakness Yes P
1218090 2025-002 Material Weakness Yes P

Programs

ALN Program Spent Major Findings
14.181 SUPPORTIVE HOUSING FOR PERSONS WITH DISABILITIES $1.27M Yes 2
14.195 PROJECT-BASED RENTAL ASSISTANCE (PBRA) $27,665 Yes 0

Contacts

Name Title Type
HX5JMNKJN665 Westchester Realty & Management LLC Auditee
4052753855 John Flusche Auditor
No contacts on file

Finding Details

Title and CFDA Number of Federal Program: Section 202 Capital Advance CFDA # 14.181 Type of Finding: Federal Award Finding Finding Resolution Status: Unresolved Criteria: The Project is not permitted to withdraw funds from the Replacement Reserve Account without prior authorization from their HUD representative. Statement of Condition: The Project’s manager withdrew funds that were not approved by HUD using the HUD-9250 Funds Authorization from the Replacement Reserve worksheet. Cause: The Project’s management used funds to pay expenses for a different Property by mistake. Effect or Potential Effect: The Project’s Replacement Reserve Account is underfunded by $5,000 from 2025 unauthorized withdraws. Reporting Views of Responsible Officials: The Project’s management should redeposit the funds into the Replacement Reserve account as soon as possible, to bring the account to the correct balance. Recommendation: The Project’s management should redeposit the funds into the Replacement Reserve account as soon as possible, to bring the account to the correct balance. Auditor’s Summary of the Auditee’s Comments on the Finding Recommendations: The Project’s management withdrew funds without receiving authorization to withdraw funds from the Replacement Reserve account. Funds should only be withdrawn from the Replacement Reserve account after the HUD-9250 “Funds Authorization” form is signed by the HUD Representative. Response Indicator: Agree Completion Date: 06/26/2025 Response: The Project’s management will fully redeposit the funds into the Replacement Reserve account in 2025 and will not withdraw funds in the future without proper authorization.
Title and CFDA Number of Federal Program: Section 202 Capital Advance CFDA # 14.181 Type of Finding: Federal Award Finding Finding Resolution Status: Unresolved Criteria: The Project is required to maintain a Security Deposit bank account equal to or greater than the Security Deposits Liability. Statement of Condition: The Project’s security deposit bank account is underfunded $2,355. Cause: The Project’s management withdrew funds from the security deposit account to cover operations for a different Property. Effect or Potential Effect: The Project does not have the necessary funds to cover the security deposit liability. Reporting Views of Responsible Officials: The Project’s management should redeposit the funds into the security account as soon as possible, to bring the account to the correct balance. Recommendation: The Project’s management should redeposit the funds into the security account as soon as possible, to bring the account to the correct balance. Auditor’s Summary of the Auditee’s Comments on the Finding Recommendations: The Project’s management should not withdraw funds from the Security Deposit Bank account at any time for operations. Response Indicator: Agree Completion Date: 06/26/2025 Response: The Project’s management will redeposit the funds into the Security Deposit bank account as soon as possible and will not withdraw funds in the future without proper documentation.