Audit 396360

FY End
2023-06-30
Total Expended
$1.90M
Findings
10
Programs
7
Year: 2023 Accepted: 2026-03-30
Auditor: WIPFLI LLP

Organization Exclusion Status:

Checking exclusion status...

Findings

ID Ref Severity Repeat Requirement
1203133 2023-001 Material Weakness Yes P
1203134 2023-001 Material Weakness Yes P
1203135 2023-001 Material Weakness Yes P
1203136 2023-001 Material Weakness Yes P
1203137 2023-001 Material Weakness Yes P
1203138 2023-001 Material Weakness Yes P
1203139 2023-001 Material Weakness Yes P
1203140 2023-001 Material Weakness Yes P
1203141 2023-001 Material Weakness Yes P
1203142 2023-001 Material Weakness Yes P

Programs

ALN Program Spent Major Findings
84.425 EDUCATION STABILIZATION FUND $573,186 Yes 1
84.010 TITLE I GRANTS TO LOCAL EDUCATIONAL AGENCIES $462,529 Yes 1
84.027 SPECIAL EDUCATION_GRANTS TO STATES $186,387 Yes 1
10.553 SCHOOL BREAKFAST PROGRAM $108,004 Yes 1
84.365 ENGLISH LANGUAGE ACQUISITION STATE GRANTS $94,298 Yes 1
21.027 CORONAVIRUS STATE AND LOCAL FISCAL RECOVERY FUNDS $76,000 Yes 1
10.555 NATIONAL SCHOOL LUNCH PROGRAM $19,587 Yes 1

Contacts

Name Title Type
C3QCTDMC49Q9 Robert Procaccini Auditee
6513092233 Rob Ganschow Auditor
No contacts on file

Notes to SEFA

Metro Schools College Prep does not have any sub-recipients of federal funding.

Finding Details

Criteria or Specific Requirement: 2 CFR Section 200.512(a) requires the reporting package and data collection form to be submitted to the Federal Audit Clearinghouse the earlier of 30 calender days after the reports are received from the auditors or nine months after the end of the audit period. Condition: The fiscal year audit package for the year ended June 30, 2023 is being submitted after the required due date. Context: We have completed the financial statement audit and the reporting package has been submitted more than nine months after the end of the school's fiscal year ended June 30, 2023. Questioned Costs:None. Effect: There is a potential for suspension or cessation of federal and/or state funding. Cause: The school's previous independent auditor did not complete the audit for the year ended June 30, 2022 until March 7, 2024. Therefore, the new independent auditor wasn't able to start and complete the audit for the school's fiscal year ended June 30, 2023 within nine months of the year end. Repeat: No Auditor's Recommendation: The school should take steps to ensure that its financial records are maintained on a current basis, reconciled timely, and audited within nine months after year end. View of Responsible Officials: We agree with the finding as presented.