Audit 388591

FY End
2024-12-31
Total Expended
$1.16M
Findings
1
Programs
3
Year: 2024 Accepted: 2026-02-23
Auditor: C J RUNYON PC

Organization Exclusion Status:

Checking exclusion status...

Findings

ID Ref Severity Repeat Requirement
1174966 2024-001 Material Weakness Yes B

Programs

Contacts

Name Title Type
DNWQY77L7BN5 Daniel Hardt Auditee
4052322437 C. J. Runyon Auditor
No contacts on file

Notes to SEFA

Ryan White Programs - Projects 1,2 and 3 - Federal Assistance Listing Number 93.917 Condition: Claims to the Oklahoma Department of Health for reimbursement of administrative costs for Projects 1, 2 and 3 excceded the statutory requirements that limits costs to a strict 10% cap per project. Effect: Ryan White Projects 1, 2 and 3 were collectively over billed $7,452. Cause: Executive Director understanding of the administrative costs cap of 10% was that the 10% related to total grant and if a project in that grant disallowed the 10% then that amount could be allocated to other projects within the grant. Criteria: Consult federal guidelines for assistance regarding 10% administrative costs cap for projects. Recommendation: Follow administrative costs cap guidelines for projects. Response: Allowable project administrative costs cap of 10% will be followed. The general ledger has been corrected and reviewed by management prior to issuance of audit.

Finding Details

Ryan White Programs - Projects 1, 2 and 3 - Federal Assistance Listing Number 93.917 Condition: Claims to the Oklahoma Department of Health for reimbursement of administrative costs for Projects 1, 2 and 3 exceeded the statutory requirements that limits costs to a strict 10% cap per project. Effect: Ryan White Projects 1, 2 and 3 were collectively over billed $7,452. Cause: Executive Director understanding of the administrative costs cap of 10% was that the 10% related to total grant and if a project in that grant disallowed the 10% then that amount could be allocated to other projects within that grant. Criteria: Consult federal guidelines for assistance regarding 10% administrative costs cap for projects. Recommendation: Follow administrative costs cap guidelines for projects. Response: Allowable project administrative costs cap of 10% will be followed. The general ledger has been corrected and reviewed by management prior to issuance of audit.