SCHEDULE OF FEDERAL AWARD FINDINGS AND QUESTIONED COSTS City of Woodland January 1, 2023 through December 31, 2023 2023-003 The City did not have adequate internal controls and did not comply with federal suspension and debarment requirements. Assistance Listing Number and Title: 21.027 – COVID-19 – Coronavirus State and Local Fiscal Recovery Funds Federal Grantor Name: U.S. Department of the Treasury Federal Award/Contract Number: N/A Pass-through Entity Name: N/A Pass-through Award/Contract Number: N/A Known Questioned Cost Amount: $0 Prior Year Audit Finding: N/A Background The purpose of the Coronavirus State and Local Fiscal Recovery Funds is to respond to the COVID-19 pandemic’s negative effects on public health and the economy, provide government services to the extent COVID-19 caused a reduction in revenues collected, make necessary investments in water, sewer or broadband infrastructure, provide emergency relief from natural disasters or their negative economic impacts, fund projects eligible under certain programs administered by the U.S. Department of Transportation through three pathways and fund projects eligible under the programs established in Title I of the Housing and Community Development Act of 1974. In 2023, the City spent $1,275,948 in program funds for these activities. Federal regulations require recipients to establish, document and maintain effective internal controls that ensure compliance with program requirements. These controls include understanding program requirements and monitoring the effectiveness of established controls. Federal requirements prohibit recipients from contracting with or purchasing from parties suspended or debarred from doing business with the federal government. Whenever the City enters into contracts or purchases goods and services that it expects to equal or exceed $25,000, paid all or in part with federal funds, it must verify the contractors are not suspended, debarred or otherwise excluded from participating in federal programs. The City may verify this by obtaining a written certification from the contractor, adding a clause or condition into the contract that states the contractor is not suspended or debarred, or checking for exclusion records in the U.S. General Services Administration’s System for Award Management at SAM.gov. The City must verify this before entering into the contract and must maintain documentation demonstrating compliance with this federal requirement. Description of Condition Our audit found the City did not have internal controls to verify all contractors it paid more than $25,000 in federal funds were not suspended or debarred from participating in federal programs. We consider this deficiency in internal controls to be a material weakness that led to material noncompliance. Cause of Condition Staff were aware of the federal suspension and debarment verification requirements and normally verify this during the procurement process. However, staff were unaware that the requirement applies to purchases. Also, City staff did not realize verifying contractors using the state’s debarment list was not sufficient. Effect of Condition The City did not obtain a written certification from the contractors, insert a clause into the contracts, or check for exclusion records at SAM.gov to verify contractors it paid $680,353 using federal funds were not suspended or debarred before contracting. Without adequate internal controls, the City increases its risk of awarding federal funds to contractors that are excluded from participating in federal programs. Any payments the City made to an ineligible party would be unallowable, and the awarding agency could potentially recover them. We subsequently verified the contractors were not suspended or debarred. Therefore, we are not questioning costs. Recommendation We recommend the City strengthen its internal controls to verify all contractors it pays $25,000 or more, all or in part with federal funds, are not suspended or debarred from participating in federal programs and maintain documentation demonstrating compliance with this requirement. City’s Response The City has added a step in the checklist process to always check for suspension and debarment and then save a screenshot of the results in the project file. Auditor’s Remarks We thank the City for its cooperation and assistance during the audit and acknowledge its commitment to resolve this finding. We will review the corrective action taken during our next audit. Applicable Laws and Regulations Title 2 U.S. Code of Federal Regulations (CFR) Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance), section 516, Audit findings, establishes reporting requirements for audit findings. Title 2 CFR Part 200, Uniform Guidance, section 303, Internal controls, describes the requirements for auditees to maintain internal controls over federal programs and comply with federal program requirements. The American Institute of Certified Public Accountants defines significant deficiencies and material weaknesses in its Codification of Statements on Auditing Standards, section 935, Compliance Audits, paragraph 11. Title 2 CFR Part 180, OMB Guidelines to Agencies on Governmentwide Debarment and Suspension (Nonprocurement), establishes nonprocurement debarment and suspension regulations implementing Executive Orders 12549 and 12689.