Audit 370955

FY End
2025-05-31
Total Expended
$5.13M
Findings
0
Programs
2
Organization: New Pisgah Haven Homes INC (IL)
Year: 2025 Accepted: 2025-10-17
Auditor: Wipfli LLP

Organization Exclusion Status:

Checking exclusion status...

Findings

No findings recorded

Programs

ALN Program Spent Major Findings
14.157 Supportive Housing for the Elderly $4.17M Yes 0
14.195 Section 8 Housing Assistance Payments Program $957,066 Yes 0

Contacts

Name Title Type
Q8LQM4LPTVJ3 Takisha Artis Auditee
7732248650 Alex Pekler Auditor
No contacts on file

Notes to SEFA

The Project does not have sub-recipients of federal awards.
The Project did not receive any non-cash assistance.
New Pisgah Haven Homes HUD Project No. 071-EE056 did not receive any insurance assistance.
New Pisgah Haven Homes HUD Project No. 071-EE056 did not receive any additional loans or loan guarantees during the year ended May 31, 2025. Capital advance at the end of 2025 were $4,171,500.
Expenditures reported on the Schedule are reported on the accrual basis of accounting. Such expenditures are recognized following the cost principles contained in the Uniform Guidance, wherein certain types of expenditures are not allowable or are limited as to reimbursement. Pass through entity identifying numbers are presented where available. The Project has not elected to use the 10 percent de minimis indirect cost rate allowed under the Uniform Guidance.