Audit 364136

FY End
2022-06-30
Total Expended
$1.68M
Findings
18
Programs
6
Year: 2022 Accepted: 2025-08-12
Auditor: Landmark Plc

Organization Exclusion Status:

Checking exclusion status...

Findings

ID Ref Severity Repeat Requirement
573369 2022-001 - Yes L
573370 2022-001 - Yes L
573371 2022-001 - Yes L
573372 2022-001 - Yes L
573373 2022-001 - Yes L
573374 2022-001 - Yes L
573375 2022-001 - Yes L
573376 2022-001 - Yes L
573377 2022-001 - Yes L
1149811 2022-001 - Yes L
1149812 2022-001 - Yes L
1149813 2022-001 - Yes L
1149814 2022-001 - Yes L
1149815 2022-001 - Yes L
1149816 2022-001 - Yes L
1149817 2022-001 - Yes L
1149818 2022-001 - Yes L
1149819 2022-001 - Yes L

Programs

Contacts

Name Title Type
GCJ9Q9DEJVK6 Renee Dycus Auditee
8702357517 Robin Scott Auditor
No contacts on file

Notes to SEFA

Title: Note 1: Basis of Presentation Accounting Policies: The accompanying schedule of expenditures of federal awards (the Schedule) includes the federal award activity of Southwest Arkansas Planning and Development District, Inc. under programs of the federal government for the year ended June 30, 2022. The information in this Schedule is presented in accordance with the requirements of Title 2 U.S. Code of Federal Regulations, Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance). Because the Schedule presents only a portion of the operations of Southwest Arkansas Planning and Development District, Inc., it is not intended to and does not present the financial position, changes in net assets or cash flows of Southwest Arkansas Planning and Development District. Inc. De Minimis Rate Used: N Rate Explanation: Southwest Arkansas Planning and Development District, Inc. allocates indirect costs using a direct cost base type of direct charged salaries. The indirect cost allocation was acknowledged by the Economic Development Administration (EDA) as being received for the year. See table on page 17.
Title: Note 2: Summary of Significant Accounting Policies Accounting Policies: The accompanying schedule of expenditures of federal awards (the Schedule) includes the federal award activity of Southwest Arkansas Planning and Development District, Inc. under programs of the federal government for the year ended June 30, 2022. The information in this Schedule is presented in accordance with the requirements of Title 2 U.S. Code of Federal Regulations, Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance). Because the Schedule presents only a portion of the operations of Southwest Arkansas Planning and Development District, Inc., it is not intended to and does not present the financial position, changes in net assets or cash flows of Southwest Arkansas Planning and Development District. Inc. De Minimis Rate Used: N Rate Explanation: Southwest Arkansas Planning and Development District, Inc. allocates indirect costs using a direct cost base type of direct charged salaries. The indirect cost allocation was acknowledged by the Economic Development Administration (EDA) as being received for the year. See table on page 17.
Title: Note 3: Indirect Cost Allocation Accounting Policies: The accompanying schedule of expenditures of federal awards (the Schedule) includes the federal award activity of Southwest Arkansas Planning and Development District, Inc. under programs of the federal government for the year ended June 30, 2022. The information in this Schedule is presented in accordance with the requirements of Title 2 U.S. Code of Federal Regulations, Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance). Because the Schedule presents only a portion of the operations of Southwest Arkansas Planning and Development District, Inc., it is not intended to and does not present the financial position, changes in net assets or cash flows of Southwest Arkansas Planning and Development District. Inc. De Minimis Rate Used: N Rate Explanation: Southwest Arkansas Planning and Development District, Inc. allocates indirect costs using a direct cost base type of direct charged salaries. The indirect cost allocation was acknowledged by the Economic Development Administration (EDA) as being received for the year. See table on page 17.

Finding Details

WIOA Cluster/Adult (17.258), Youth (17.259) and Dislocated Worker (17.278); Federal Agency: U.S. Department of Labor; Pass-through Agency: Arkansas Department of Workforce Services; Criteria: Per guidance provided in 2 CFR part 200.512, the audit must be completed, and the data collection form and reporting package must be submitted within the earlier of 30 calendar days after receipt of the auditor's report(s), or nine months after the end of the audit period. A six-month extension was provided for submission of the data collection form and reporting package for the reporting period.; Condition/Context: The financial statement audit was not completed within the allowed timeframe and the data collection form and reporting package for the audit period.; Effect: Southwest Arkansas Planning and Development District, Inc. filed a late submission of the data collection form for the audit period.; Questioned Costs: None.; Cause: Southwest Arkansas Planning and Development District, Inc. was impacted by the COVID-19 pandemic and was unable to meet the due date of the data collection form and reporting package.; Recommendation: We recommend Southwest Arkansas Planning and Development District, Inc. implement procedures and controls to ensure the reporting requirements are properly completed within the mandated timeframe.; View of Responsible Officials: See corrective action plan.
WIOA Cluster/Adult (17.258), Youth (17.259) and Dislocated Worker (17.278); Federal Agency: U.S. Department of Labor; Pass-through Agency: Arkansas Department of Workforce Services; Criteria: Per guidance provided in 2 CFR part 200.512, the audit must be completed, and the data collection form and reporting package must be submitted within the earlier of 30 calendar days after receipt of the auditor's report(s), or nine months after the end of the audit period. A six-month extension was provided for submission of the data collection form and reporting package for the reporting period.; Condition/Context: The financial statement audit was not completed within the allowed timeframe and the data collection form and reporting package for the audit period.; Effect: Southwest Arkansas Planning and Development District, Inc. filed a late submission of the data collection form for the audit period.; Questioned Costs: None.; Cause: Southwest Arkansas Planning and Development District, Inc. was impacted by the COVID-19 pandemic and was unable to meet the due date of the data collection form and reporting package.; Recommendation: We recommend Southwest Arkansas Planning and Development District, Inc. implement procedures and controls to ensure the reporting requirements are properly completed within the mandated timeframe.; View of Responsible Officials: See corrective action plan.
WIOA Cluster/Adult (17.258), Youth (17.259) and Dislocated Worker (17.278); Federal Agency: U.S. Department of Labor; Pass-through Agency: Arkansas Department of Workforce Services; Criteria: Per guidance provided in 2 CFR part 200.512, the audit must be completed, and the data collection form and reporting package must be submitted within the earlier of 30 calendar days after receipt of the auditor's report(s), or nine months after the end of the audit period. A six-month extension was provided for submission of the data collection form and reporting package for the reporting period.; Condition/Context: The financial statement audit was not completed within the allowed timeframe and the data collection form and reporting package for the audit period.; Effect: Southwest Arkansas Planning and Development District, Inc. filed a late submission of the data collection form for the audit period.; Questioned Costs: None.; Cause: Southwest Arkansas Planning and Development District, Inc. was impacted by the COVID-19 pandemic and was unable to meet the due date of the data collection form and reporting package.; Recommendation: We recommend Southwest Arkansas Planning and Development District, Inc. implement procedures and controls to ensure the reporting requirements are properly completed within the mandated timeframe.; View of Responsible Officials: See corrective action plan.
WIOA Cluster/Adult (17.258), Youth (17.259) and Dislocated Worker (17.278); Federal Agency: U.S. Department of Labor; Pass-through Agency: Arkansas Department of Workforce Services; Criteria: Per guidance provided in 2 CFR part 200.512, the audit must be completed, and the data collection form and reporting package must be submitted within the earlier of 30 calendar days after receipt of the auditor's report(s), or nine months after the end of the audit period. A six-month extension was provided for submission of the data collection form and reporting package for the reporting period.; Condition/Context: The financial statement audit was not completed within the allowed timeframe and the data collection form and reporting package for the audit period.; Effect: Southwest Arkansas Planning and Development District, Inc. filed a late submission of the data collection form for the audit period.; Questioned Costs: None.; Cause: Southwest Arkansas Planning and Development District, Inc. was impacted by the COVID-19 pandemic and was unable to meet the due date of the data collection form and reporting package.; Recommendation: We recommend Southwest Arkansas Planning and Development District, Inc. implement procedures and controls to ensure the reporting requirements are properly completed within the mandated timeframe.; View of Responsible Officials: See corrective action plan.
WIOA Cluster/Adult (17.258), Youth (17.259) and Dislocated Worker (17.278); Federal Agency: U.S. Department of Labor; Pass-through Agency: Arkansas Department of Workforce Services; Criteria: Per guidance provided in 2 CFR part 200.512, the audit must be completed, and the data collection form and reporting package must be submitted within the earlier of 30 calendar days after receipt of the auditor's report(s), or nine months after the end of the audit period. A six-month extension was provided for submission of the data collection form and reporting package for the reporting period.; Condition/Context: The financial statement audit was not completed within the allowed timeframe and the data collection form and reporting package for the audit period.; Effect: Southwest Arkansas Planning and Development District, Inc. filed a late submission of the data collection form for the audit period.; Questioned Costs: None.; Cause: Southwest Arkansas Planning and Development District, Inc. was impacted by the COVID-19 pandemic and was unable to meet the due date of the data collection form and reporting package.; Recommendation: We recommend Southwest Arkansas Planning and Development District, Inc. implement procedures and controls to ensure the reporting requirements are properly completed within the mandated timeframe.; View of Responsible Officials: See corrective action plan.
WIOA Cluster/Adult (17.258), Youth (17.259) and Dislocated Worker (17.278); Federal Agency: U.S. Department of Labor; Pass-through Agency: Arkansas Department of Workforce Services; Criteria: Per guidance provided in 2 CFR part 200.512, the audit must be completed, and the data collection form and reporting package must be submitted within the earlier of 30 calendar days after receipt of the auditor's report(s), or nine months after the end of the audit period. A six-month extension was provided for submission of the data collection form and reporting package for the reporting period.; Condition/Context: The financial statement audit was not completed within the allowed timeframe and the data collection form and reporting package for the audit period.; Effect: Southwest Arkansas Planning and Development District, Inc. filed a late submission of the data collection form for the audit period.; Questioned Costs: None.; Cause: Southwest Arkansas Planning and Development District, Inc. was impacted by the COVID-19 pandemic and was unable to meet the due date of the data collection form and reporting package.; Recommendation: We recommend Southwest Arkansas Planning and Development District, Inc. implement procedures and controls to ensure the reporting requirements are properly completed within the mandated timeframe.; View of Responsible Officials: See corrective action plan.
WIOA Cluster/Adult (17.258), Youth (17.259) and Dislocated Worker (17.278); Federal Agency: U.S. Department of Labor; Pass-through Agency: Arkansas Department of Workforce Services; Criteria: Per guidance provided in 2 CFR part 200.512, the audit must be completed, and the data collection form and reporting package must be submitted within the earlier of 30 calendar days after receipt of the auditor's report(s), or nine months after the end of the audit period. A six-month extension was provided for submission of the data collection form and reporting package for the reporting period.; Condition/Context: The financial statement audit was not completed within the allowed timeframe and the data collection form and reporting package for the audit period.; Effect: Southwest Arkansas Planning and Development District, Inc. filed a late submission of the data collection form for the audit period.; Questioned Costs: None.; Cause: Southwest Arkansas Planning and Development District, Inc. was impacted by the COVID-19 pandemic and was unable to meet the due date of the data collection form and reporting package.; Recommendation: We recommend Southwest Arkansas Planning and Development District, Inc. implement procedures and controls to ensure the reporting requirements are properly completed within the mandated timeframe.; View of Responsible Officials: See corrective action plan.
WIOA Cluster/Adult (17.258), Youth (17.259) and Dislocated Worker (17.278); Federal Agency: U.S. Department of Labor; Pass-through Agency: Arkansas Department of Workforce Services; Criteria: Per guidance provided in 2 CFR part 200.512, the audit must be completed, and the data collection form and reporting package must be submitted within the earlier of 30 calendar days after receipt of the auditor's report(s), or nine months after the end of the audit period. A six-month extension was provided for submission of the data collection form and reporting package for the reporting period.; Condition/Context: The financial statement audit was not completed within the allowed timeframe and the data collection form and reporting package for the audit period.; Effect: Southwest Arkansas Planning and Development District, Inc. filed a late submission of the data collection form for the audit period.; Questioned Costs: None.; Cause: Southwest Arkansas Planning and Development District, Inc. was impacted by the COVID-19 pandemic and was unable to meet the due date of the data collection form and reporting package.; Recommendation: We recommend Southwest Arkansas Planning and Development District, Inc. implement procedures and controls to ensure the reporting requirements are properly completed within the mandated timeframe.; View of Responsible Officials: See corrective action plan.
WIOA Cluster/Adult (17.258), Youth (17.259) and Dislocated Worker (17.278); Federal Agency: U.S. Department of Labor; Pass-through Agency: Arkansas Department of Workforce Services; Criteria: Per guidance provided in 2 CFR part 200.512, the audit must be completed, and the data collection form and reporting package must be submitted within the earlier of 30 calendar days after receipt of the auditor's report(s), or nine months after the end of the audit period. A six-month extension was provided for submission of the data collection form and reporting package for the reporting period.; Condition/Context: The financial statement audit was not completed within the allowed timeframe and the data collection form and reporting package for the audit period.; Effect: Southwest Arkansas Planning and Development District, Inc. filed a late submission of the data collection form for the audit period.; Questioned Costs: None.; Cause: Southwest Arkansas Planning and Development District, Inc. was impacted by the COVID-19 pandemic and was unable to meet the due date of the data collection form and reporting package.; Recommendation: We recommend Southwest Arkansas Planning and Development District, Inc. implement procedures and controls to ensure the reporting requirements are properly completed within the mandated timeframe.; View of Responsible Officials: See corrective action plan.
WIOA Cluster/Adult (17.258), Youth (17.259) and Dislocated Worker (17.278); Federal Agency: U.S. Department of Labor; Pass-through Agency: Arkansas Department of Workforce Services; Criteria: Per guidance provided in 2 CFR part 200.512, the audit must be completed, and the data collection form and reporting package must be submitted within the earlier of 30 calendar days after receipt of the auditor's report(s), or nine months after the end of the audit period. A six-month extension was provided for submission of the data collection form and reporting package for the reporting period.; Condition/Context: The financial statement audit was not completed within the allowed timeframe and the data collection form and reporting package for the audit period.; Effect: Southwest Arkansas Planning and Development District, Inc. filed a late submission of the data collection form for the audit period.; Questioned Costs: None.; Cause: Southwest Arkansas Planning and Development District, Inc. was impacted by the COVID-19 pandemic and was unable to meet the due date of the data collection form and reporting package.; Recommendation: We recommend Southwest Arkansas Planning and Development District, Inc. implement procedures and controls to ensure the reporting requirements are properly completed within the mandated timeframe.; View of Responsible Officials: See corrective action plan.
WIOA Cluster/Adult (17.258), Youth (17.259) and Dislocated Worker (17.278); Federal Agency: U.S. Department of Labor; Pass-through Agency: Arkansas Department of Workforce Services; Criteria: Per guidance provided in 2 CFR part 200.512, the audit must be completed, and the data collection form and reporting package must be submitted within the earlier of 30 calendar days after receipt of the auditor's report(s), or nine months after the end of the audit period. A six-month extension was provided for submission of the data collection form and reporting package for the reporting period.; Condition/Context: The financial statement audit was not completed within the allowed timeframe and the data collection form and reporting package for the audit period.; Effect: Southwest Arkansas Planning and Development District, Inc. filed a late submission of the data collection form for the audit period.; Questioned Costs: None.; Cause: Southwest Arkansas Planning and Development District, Inc. was impacted by the COVID-19 pandemic and was unable to meet the due date of the data collection form and reporting package.; Recommendation: We recommend Southwest Arkansas Planning and Development District, Inc. implement procedures and controls to ensure the reporting requirements are properly completed within the mandated timeframe.; View of Responsible Officials: See corrective action plan.
WIOA Cluster/Adult (17.258), Youth (17.259) and Dislocated Worker (17.278); Federal Agency: U.S. Department of Labor; Pass-through Agency: Arkansas Department of Workforce Services; Criteria: Per guidance provided in 2 CFR part 200.512, the audit must be completed, and the data collection form and reporting package must be submitted within the earlier of 30 calendar days after receipt of the auditor's report(s), or nine months after the end of the audit period. A six-month extension was provided for submission of the data collection form and reporting package for the reporting period.; Condition/Context: The financial statement audit was not completed within the allowed timeframe and the data collection form and reporting package for the audit period.; Effect: Southwest Arkansas Planning and Development District, Inc. filed a late submission of the data collection form for the audit period.; Questioned Costs: None.; Cause: Southwest Arkansas Planning and Development District, Inc. was impacted by the COVID-19 pandemic and was unable to meet the due date of the data collection form and reporting package.; Recommendation: We recommend Southwest Arkansas Planning and Development District, Inc. implement procedures and controls to ensure the reporting requirements are properly completed within the mandated timeframe.; View of Responsible Officials: See corrective action plan.
WIOA Cluster/Adult (17.258), Youth (17.259) and Dislocated Worker (17.278); Federal Agency: U.S. Department of Labor; Pass-through Agency: Arkansas Department of Workforce Services; Criteria: Per guidance provided in 2 CFR part 200.512, the audit must be completed, and the data collection form and reporting package must be submitted within the earlier of 30 calendar days after receipt of the auditor's report(s), or nine months after the end of the audit period. A six-month extension was provided for submission of the data collection form and reporting package for the reporting period.; Condition/Context: The financial statement audit was not completed within the allowed timeframe and the data collection form and reporting package for the audit period.; Effect: Southwest Arkansas Planning and Development District, Inc. filed a late submission of the data collection form for the audit period.; Questioned Costs: None.; Cause: Southwest Arkansas Planning and Development District, Inc. was impacted by the COVID-19 pandemic and was unable to meet the due date of the data collection form and reporting package.; Recommendation: We recommend Southwest Arkansas Planning and Development District, Inc. implement procedures and controls to ensure the reporting requirements are properly completed within the mandated timeframe.; View of Responsible Officials: See corrective action plan.
WIOA Cluster/Adult (17.258), Youth (17.259) and Dislocated Worker (17.278); Federal Agency: U.S. Department of Labor; Pass-through Agency: Arkansas Department of Workforce Services; Criteria: Per guidance provided in 2 CFR part 200.512, the audit must be completed, and the data collection form and reporting package must be submitted within the earlier of 30 calendar days after receipt of the auditor's report(s), or nine months after the end of the audit period. A six-month extension was provided for submission of the data collection form and reporting package for the reporting period.; Condition/Context: The financial statement audit was not completed within the allowed timeframe and the data collection form and reporting package for the audit period.; Effect: Southwest Arkansas Planning and Development District, Inc. filed a late submission of the data collection form for the audit period.; Questioned Costs: None.; Cause: Southwest Arkansas Planning and Development District, Inc. was impacted by the COVID-19 pandemic and was unable to meet the due date of the data collection form and reporting package.; Recommendation: We recommend Southwest Arkansas Planning and Development District, Inc. implement procedures and controls to ensure the reporting requirements are properly completed within the mandated timeframe.; View of Responsible Officials: See corrective action plan.
WIOA Cluster/Adult (17.258), Youth (17.259) and Dislocated Worker (17.278); Federal Agency: U.S. Department of Labor; Pass-through Agency: Arkansas Department of Workforce Services; Criteria: Per guidance provided in 2 CFR part 200.512, the audit must be completed, and the data collection form and reporting package must be submitted within the earlier of 30 calendar days after receipt of the auditor's report(s), or nine months after the end of the audit period. A six-month extension was provided for submission of the data collection form and reporting package for the reporting period.; Condition/Context: The financial statement audit was not completed within the allowed timeframe and the data collection form and reporting package for the audit period.; Effect: Southwest Arkansas Planning and Development District, Inc. filed a late submission of the data collection form for the audit period.; Questioned Costs: None.; Cause: Southwest Arkansas Planning and Development District, Inc. was impacted by the COVID-19 pandemic and was unable to meet the due date of the data collection form and reporting package.; Recommendation: We recommend Southwest Arkansas Planning and Development District, Inc. implement procedures and controls to ensure the reporting requirements are properly completed within the mandated timeframe.; View of Responsible Officials: See corrective action plan.
WIOA Cluster/Adult (17.258), Youth (17.259) and Dislocated Worker (17.278); Federal Agency: U.S. Department of Labor; Pass-through Agency: Arkansas Department of Workforce Services; Criteria: Per guidance provided in 2 CFR part 200.512, the audit must be completed, and the data collection form and reporting package must be submitted within the earlier of 30 calendar days after receipt of the auditor's report(s), or nine months after the end of the audit period. A six-month extension was provided for submission of the data collection form and reporting package for the reporting period.; Condition/Context: The financial statement audit was not completed within the allowed timeframe and the data collection form and reporting package for the audit period.; Effect: Southwest Arkansas Planning and Development District, Inc. filed a late submission of the data collection form for the audit period.; Questioned Costs: None.; Cause: Southwest Arkansas Planning and Development District, Inc. was impacted by the COVID-19 pandemic and was unable to meet the due date of the data collection form and reporting package.; Recommendation: We recommend Southwest Arkansas Planning and Development District, Inc. implement procedures and controls to ensure the reporting requirements are properly completed within the mandated timeframe.; View of Responsible Officials: See corrective action plan.
WIOA Cluster/Adult (17.258), Youth (17.259) and Dislocated Worker (17.278); Federal Agency: U.S. Department of Labor; Pass-through Agency: Arkansas Department of Workforce Services; Criteria: Per guidance provided in 2 CFR part 200.512, the audit must be completed, and the data collection form and reporting package must be submitted within the earlier of 30 calendar days after receipt of the auditor's report(s), or nine months after the end of the audit period. A six-month extension was provided for submission of the data collection form and reporting package for the reporting period.; Condition/Context: The financial statement audit was not completed within the allowed timeframe and the data collection form and reporting package for the audit period.; Effect: Southwest Arkansas Planning and Development District, Inc. filed a late submission of the data collection form for the audit period.; Questioned Costs: None.; Cause: Southwest Arkansas Planning and Development District, Inc. was impacted by the COVID-19 pandemic and was unable to meet the due date of the data collection form and reporting package.; Recommendation: We recommend Southwest Arkansas Planning and Development District, Inc. implement procedures and controls to ensure the reporting requirements are properly completed within the mandated timeframe.; View of Responsible Officials: See corrective action plan.
WIOA Cluster/Adult (17.258), Youth (17.259) and Dislocated Worker (17.278); Federal Agency: U.S. Department of Labor; Pass-through Agency: Arkansas Department of Workforce Services; Criteria: Per guidance provided in 2 CFR part 200.512, the audit must be completed, and the data collection form and reporting package must be submitted within the earlier of 30 calendar days after receipt of the auditor's report(s), or nine months after the end of the audit period. A six-month extension was provided for submission of the data collection form and reporting package for the reporting period.; Condition/Context: The financial statement audit was not completed within the allowed timeframe and the data collection form and reporting package for the audit period.; Effect: Southwest Arkansas Planning and Development District, Inc. filed a late submission of the data collection form for the audit period.; Questioned Costs: None.; Cause: Southwest Arkansas Planning and Development District, Inc. was impacted by the COVID-19 pandemic and was unable to meet the due date of the data collection form and reporting package.; Recommendation: We recommend Southwest Arkansas Planning and Development District, Inc. implement procedures and controls to ensure the reporting requirements are properly completed within the mandated timeframe.; View of Responsible Officials: See corrective action plan.