Audit 363868

FY End
2024-12-31
Total Expended
$9.60M
Findings
0
Programs
1
Organization: East Central Energy (MN)
Year: 2024 Accepted: 2025-08-07

Organization Exclusion Status:

Checking exclusion status...

Findings

No findings recorded

Programs

ALN Program Spent Major Findings
21.029 Coronavirus Capital Projects Fund $40,881 Yes 0

Contacts

Name Title Type
HBXWH1P95E33 Lisa Prachar Auditee
7636898014 Brian Opsahl Auditor
No contacts on file

Notes to SEFA

Title: BASIS OF PRESENTATION Accounting Policies: Expenditures reported in the accompanying schedule of expenditures of federal awards (the Schedule) are reported on the accrual basis of accounting. Such expenditures are recognized following the cost principles contained in Title 2 U.S. Code of Federal Regulations Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards, wherein certain types of expenditures are not allowable or are limited as to reimbursement. De Minimis Rate Used: N Rate Explanation: East Central Energy and Subsidiaries has not elected to use the 10-percent de minimis indirect cost rate as allowed under the Uniform Guidance. The accompanying schedule of expenditures of federal awards (the “Schedule”) includes the federal award activity of East Central Energy and Subsidiaries under programs of the federal government for the year ended December 31, 2024. The information in this schedule is presented in accordance with the requirements of Title 2 U.S. Code of Federal Regulations Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance). Because the Schedule presents only a selected portion of operations of East Central Energy and Subsidiaries it is not intended to and does not present the financial position, change in net position, or cash flows of the East Central Energy and Subsidiaries.
Title: PASS-THROUGH ENTITIES Accounting Policies: Expenditures reported in the accompanying schedule of expenditures of federal awards (the Schedule) are reported on the accrual basis of accounting. Such expenditures are recognized following the cost principles contained in Title 2 U.S. Code of Federal Regulations Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards, wherein certain types of expenditures are not allowable or are limited as to reimbursement. De Minimis Rate Used: N Rate Explanation: East Central Energy and Subsidiaries has not elected to use the 10-percent de minimis indirect cost rate as allowed under the Uniform Guidance. Pass-through entity identifying numbers are presented where available.