Audit 361128

FY End
2024-09-30
Total Expended
$3.55M
Findings
18
Programs
4
Year: 2024 Accepted: 2025-06-30

Organization Exclusion Status:

Checking exclusion status...

Findings

ID Ref Severity Repeat Requirement
569861 2024-001 - Yes P
569862 2024-001 - Yes P
569863 2024-001 - Yes P
569864 2024-001 - Yes P
569865 2024-001 - Yes P
569866 2024-001 - Yes P
569867 2024-001 - Yes P
569868 2024-001 - Yes P
569869 2024-001 - Yes P
1146303 2024-001 - Yes P
1146304 2024-001 - Yes P
1146305 2024-001 - Yes P
1146306 2024-001 - Yes P
1146307 2024-001 - Yes P
1146308 2024-001 - Yes P
1146309 2024-001 - Yes P
1146310 2024-001 - Yes P
1146311 2024-001 - Yes P

Programs

ALN Program Spent Major Findings
93.273 Alcohol Research Programs $257,162 Yes 1
93.361 Nursing Research $256,051 Yes 1
93.242 Mental Health Research Grants $102,488 Yes 1
93.865 Child Health and Human Development Extramural Research $93,241 Yes 1

Contacts

Name Title Type
HB8HEMLHJUJ4 Michele Ybarra Auditee
8773026858 Jeanne Mann Auditor
No contacts on file

Notes to SEFA

Title: BASIS OF PRESENTATION Accounting Policies: The accompanying schedule of expenditures of federal awards (the Schedule) includes Federal grant activity of CiPHR and is presented on the modified accrual basis of accounting. The information in this schedule is presented in accordance with the requirements of Title 2 U.S. Code of Federal Regulations Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance). Therefore, some amounts presented in this schedule may differ from amounts presented in, or used in the preparation of, the financial statements. De Minimis Rate Used: N Rate Explanation: The organization is using their approved indirect cost rate The accompanying schedule of expenditures of federal awards (the Schedule) includes Federal grant activity of CiPHR and is presented on the modified accrual basis of accounting. The information in this schedule is presented in accordance with the requirements of Title 2 U.S. Code of Federal Regulations Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance). Therefore, some amounts presented in this schedule may differ from amounts presented in, or used in the preparation of, the financial statements.
Title: INDIRECT COST RATE Accounting Policies: The accompanying schedule of expenditures of federal awards (the Schedule) includes Federal grant activity of CiPHR and is presented on the modified accrual basis of accounting. The information in this schedule is presented in accordance with the requirements of Title 2 U.S. Code of Federal Regulations Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance). Therefore, some amounts presented in this schedule may differ from amounts presented in, or used in the preparation of, the financial statements. De Minimis Rate Used: N Rate Explanation: The organization is using their approved indirect cost rate CiPHR has not elected to use the 10% de minimus costs rate.

Finding Details

Criteria: As a condition of receiving federal awards, the awardee organization must comply with filing the required reports timely, specifically, submission of an audit report within nine months after the end of the audit period. Condition: The entity submitted their audit report eleven months after the end of their audit period September 30, 2023. Cause: The entity has not been able to close their books in a timely manner due to the late submission of vendor invoices. At times their closing has conflicted with the auditor’s availability and therefore, the audit was unable to be completed within the nine month period. Effect: The entity was not in compliance with the deadline for the audit report under 2 CFR 200.516 (a). Questioned costs: None Reported Context/Sampling: None Reported Repeat Finding from Prior Year: Yes 2023-001 Recommendation: We recommend that management communicate with their vendors to assure that timely invoices are submitted and that a strict timeline for completion of the audit is adhered to. Views of Responsible Officials: The entity has implemented wording in their vendor contracts that they will not honor invoices that are more than 90 days out.
Criteria: As a condition of receiving federal awards, the awardee organization must comply with filing the required reports timely, specifically, submission of an audit report within nine months after the end of the audit period. Condition: The entity submitted their audit report eleven months after the end of their audit period September 30, 2023. Cause: The entity has not been able to close their books in a timely manner due to the late submission of vendor invoices. At times their closing has conflicted with the auditor’s availability and therefore, the audit was unable to be completed within the nine month period. Effect: The entity was not in compliance with the deadline for the audit report under 2 CFR 200.516 (a). Questioned costs: None Reported Context/Sampling: None Reported Repeat Finding from Prior Year: Yes 2023-001 Recommendation: We recommend that management communicate with their vendors to assure that timely invoices are submitted and that a strict timeline for completion of the audit is adhered to. Views of Responsible Officials: The entity has implemented wording in their vendor contracts that they will not honor invoices that are more than 90 days out.
Criteria: As a condition of receiving federal awards, the awardee organization must comply with filing the required reports timely, specifically, submission of an audit report within nine months after the end of the audit period. Condition: The entity submitted their audit report eleven months after the end of their audit period September 30, 2023. Cause: The entity has not been able to close their books in a timely manner due to the late submission of vendor invoices. At times their closing has conflicted with the auditor’s availability and therefore, the audit was unable to be completed within the nine month period. Effect: The entity was not in compliance with the deadline for the audit report under 2 CFR 200.516 (a). Questioned costs: None Reported Context/Sampling: None Reported Repeat Finding from Prior Year: Yes 2023-001 Recommendation: We recommend that management communicate with their vendors to assure that timely invoices are submitted and that a strict timeline for completion of the audit is adhered to. Views of Responsible Officials: The entity has implemented wording in their vendor contracts that they will not honor invoices that are more than 90 days out.
Criteria: As a condition of receiving federal awards, the awardee organization must comply with filing the required reports timely, specifically, submission of an audit report within nine months after the end of the audit period. Condition: The entity submitted their audit report eleven months after the end of their audit period September 30, 2023. Cause: The entity has not been able to close their books in a timely manner due to the late submission of vendor invoices. At times their closing has conflicted with the auditor’s availability and therefore, the audit was unable to be completed within the nine month period. Effect: The entity was not in compliance with the deadline for the audit report under 2 CFR 200.516 (a). Questioned costs: None Reported Context/Sampling: None Reported Repeat Finding from Prior Year: Yes 2023-001 Recommendation: We recommend that management communicate with their vendors to assure that timely invoices are submitted and that a strict timeline for completion of the audit is adhered to. Views of Responsible Officials: The entity has implemented wording in their vendor contracts that they will not honor invoices that are more than 90 days out.
Criteria: As a condition of receiving federal awards, the awardee organization must comply with filing the required reports timely, specifically, submission of an audit report within nine months after the end of the audit period. Condition: The entity submitted their audit report eleven months after the end of their audit period September 30, 2023. Cause: The entity has not been able to close their books in a timely manner due to the late submission of vendor invoices. At times their closing has conflicted with the auditor’s availability and therefore, the audit was unable to be completed within the nine month period. Effect: The entity was not in compliance with the deadline for the audit report under 2 CFR 200.516 (a). Questioned costs: None Reported Context/Sampling: None Reported Repeat Finding from Prior Year: Yes 2023-001 Recommendation: We recommend that management communicate with their vendors to assure that timely invoices are submitted and that a strict timeline for completion of the audit is adhered to. Views of Responsible Officials: The entity has implemented wording in their vendor contracts that they will not honor invoices that are more than 90 days out.
Criteria: As a condition of receiving federal awards, the awardee organization must comply with filing the required reports timely, specifically, submission of an audit report within nine months after the end of the audit period. Condition: The entity submitted their audit report eleven months after the end of their audit period September 30, 2023. Cause: The entity has not been able to close their books in a timely manner due to the late submission of vendor invoices. At times their closing has conflicted with the auditor’s availability and therefore, the audit was unable to be completed within the nine month period. Effect: The entity was not in compliance with the deadline for the audit report under 2 CFR 200.516 (a). Questioned costs: None Reported Context/Sampling: None Reported Repeat Finding from Prior Year: Yes 2023-001 Recommendation: We recommend that management communicate with their vendors to assure that timely invoices are submitted and that a strict timeline for completion of the audit is adhered to. Views of Responsible Officials: The entity has implemented wording in their vendor contracts that they will not honor invoices that are more than 90 days out.
Criteria: As a condition of receiving federal awards, the awardee organization must comply with filing the required reports timely, specifically, submission of an audit report within nine months after the end of the audit period. Condition: The entity submitted their audit report eleven months after the end of their audit period September 30, 2023. Cause: The entity has not been able to close their books in a timely manner due to the late submission of vendor invoices. At times their closing has conflicted with the auditor’s availability and therefore, the audit was unable to be completed within the nine month period. Effect: The entity was not in compliance with the deadline for the audit report under 2 CFR 200.516 (a). Questioned costs: None Reported Context/Sampling: None Reported Repeat Finding from Prior Year: Yes 2023-001 Recommendation: We recommend that management communicate with their vendors to assure that timely invoices are submitted and that a strict timeline for completion of the audit is adhered to. Views of Responsible Officials: The entity has implemented wording in their vendor contracts that they will not honor invoices that are more than 90 days out.
Criteria: As a condition of receiving federal awards, the awardee organization must comply with filing the required reports timely, specifically, submission of an audit report within nine months after the end of the audit period. Condition: The entity submitted their audit report eleven months after the end of their audit period September 30, 2023. Cause: The entity has not been able to close their books in a timely manner due to the late submission of vendor invoices. At times their closing has conflicted with the auditor’s availability and therefore, the audit was unable to be completed within the nine month period. Effect: The entity was not in compliance with the deadline for the audit report under 2 CFR 200.516 (a). Questioned costs: None Reported Context/Sampling: None Reported Repeat Finding from Prior Year: Yes 2023-001 Recommendation: We recommend that management communicate with their vendors to assure that timely invoices are submitted and that a strict timeline for completion of the audit is adhered to. Views of Responsible Officials: The entity has implemented wording in their vendor contracts that they will not honor invoices that are more than 90 days out.
Criteria: As a condition of receiving federal awards, the awardee organization must comply with filing the required reports timely, specifically, submission of an audit report within nine months after the end of the audit period. Condition: The entity submitted their audit report eleven months after the end of their audit period September 30, 2023. Cause: The entity has not been able to close their books in a timely manner due to the late submission of vendor invoices. At times their closing has conflicted with the auditor’s availability and therefore, the audit was unable to be completed within the nine month period. Effect: The entity was not in compliance with the deadline for the audit report under 2 CFR 200.516 (a). Questioned costs: None Reported Context/Sampling: None Reported Repeat Finding from Prior Year: Yes 2023-001 Recommendation: We recommend that management communicate with their vendors to assure that timely invoices are submitted and that a strict timeline for completion of the audit is adhered to. Views of Responsible Officials: The entity has implemented wording in their vendor contracts that they will not honor invoices that are more than 90 days out.
Criteria: As a condition of receiving federal awards, the awardee organization must comply with filing the required reports timely, specifically, submission of an audit report within nine months after the end of the audit period. Condition: The entity submitted their audit report eleven months after the end of their audit period September 30, 2023. Cause: The entity has not been able to close their books in a timely manner due to the late submission of vendor invoices. At times their closing has conflicted with the auditor’s availability and therefore, the audit was unable to be completed within the nine month period. Effect: The entity was not in compliance with the deadline for the audit report under 2 CFR 200.516 (a). Questioned costs: None Reported Context/Sampling: None Reported Repeat Finding from Prior Year: Yes 2023-001 Recommendation: We recommend that management communicate with their vendors to assure that timely invoices are submitted and that a strict timeline for completion of the audit is adhered to. Views of Responsible Officials: The entity has implemented wording in their vendor contracts that they will not honor invoices that are more than 90 days out.
Criteria: As a condition of receiving federal awards, the awardee organization must comply with filing the required reports timely, specifically, submission of an audit report within nine months after the end of the audit period. Condition: The entity submitted their audit report eleven months after the end of their audit period September 30, 2023. Cause: The entity has not been able to close their books in a timely manner due to the late submission of vendor invoices. At times their closing has conflicted with the auditor’s availability and therefore, the audit was unable to be completed within the nine month period. Effect: The entity was not in compliance with the deadline for the audit report under 2 CFR 200.516 (a). Questioned costs: None Reported Context/Sampling: None Reported Repeat Finding from Prior Year: Yes 2023-001 Recommendation: We recommend that management communicate with their vendors to assure that timely invoices are submitted and that a strict timeline for completion of the audit is adhered to. Views of Responsible Officials: The entity has implemented wording in their vendor contracts that they will not honor invoices that are more than 90 days out.
Criteria: As a condition of receiving federal awards, the awardee organization must comply with filing the required reports timely, specifically, submission of an audit report within nine months after the end of the audit period. Condition: The entity submitted their audit report eleven months after the end of their audit period September 30, 2023. Cause: The entity has not been able to close their books in a timely manner due to the late submission of vendor invoices. At times their closing has conflicted with the auditor’s availability and therefore, the audit was unable to be completed within the nine month period. Effect: The entity was not in compliance with the deadline for the audit report under 2 CFR 200.516 (a). Questioned costs: None Reported Context/Sampling: None Reported Repeat Finding from Prior Year: Yes 2023-001 Recommendation: We recommend that management communicate with their vendors to assure that timely invoices are submitted and that a strict timeline for completion of the audit is adhered to. Views of Responsible Officials: The entity has implemented wording in their vendor contracts that they will not honor invoices that are more than 90 days out.
Criteria: As a condition of receiving federal awards, the awardee organization must comply with filing the required reports timely, specifically, submission of an audit report within nine months after the end of the audit period. Condition: The entity submitted their audit report eleven months after the end of their audit period September 30, 2023. Cause: The entity has not been able to close their books in a timely manner due to the late submission of vendor invoices. At times their closing has conflicted with the auditor’s availability and therefore, the audit was unable to be completed within the nine month period. Effect: The entity was not in compliance with the deadline for the audit report under 2 CFR 200.516 (a). Questioned costs: None Reported Context/Sampling: None Reported Repeat Finding from Prior Year: Yes 2023-001 Recommendation: We recommend that management communicate with their vendors to assure that timely invoices are submitted and that a strict timeline for completion of the audit is adhered to. Views of Responsible Officials: The entity has implemented wording in their vendor contracts that they will not honor invoices that are more than 90 days out.
Criteria: As a condition of receiving federal awards, the awardee organization must comply with filing the required reports timely, specifically, submission of an audit report within nine months after the end of the audit period. Condition: The entity submitted their audit report eleven months after the end of their audit period September 30, 2023. Cause: The entity has not been able to close their books in a timely manner due to the late submission of vendor invoices. At times their closing has conflicted with the auditor’s availability and therefore, the audit was unable to be completed within the nine month period. Effect: The entity was not in compliance with the deadline for the audit report under 2 CFR 200.516 (a). Questioned costs: None Reported Context/Sampling: None Reported Repeat Finding from Prior Year: Yes 2023-001 Recommendation: We recommend that management communicate with their vendors to assure that timely invoices are submitted and that a strict timeline for completion of the audit is adhered to. Views of Responsible Officials: The entity has implemented wording in their vendor contracts that they will not honor invoices that are more than 90 days out.
Criteria: As a condition of receiving federal awards, the awardee organization must comply with filing the required reports timely, specifically, submission of an audit report within nine months after the end of the audit period. Condition: The entity submitted their audit report eleven months after the end of their audit period September 30, 2023. Cause: The entity has not been able to close their books in a timely manner due to the late submission of vendor invoices. At times their closing has conflicted with the auditor’s availability and therefore, the audit was unable to be completed within the nine month period. Effect: The entity was not in compliance with the deadline for the audit report under 2 CFR 200.516 (a). Questioned costs: None Reported Context/Sampling: None Reported Repeat Finding from Prior Year: Yes 2023-001 Recommendation: We recommend that management communicate with their vendors to assure that timely invoices are submitted and that a strict timeline for completion of the audit is adhered to. Views of Responsible Officials: The entity has implemented wording in their vendor contracts that they will not honor invoices that are more than 90 days out.
Criteria: As a condition of receiving federal awards, the awardee organization must comply with filing the required reports timely, specifically, submission of an audit report within nine months after the end of the audit period. Condition: The entity submitted their audit report eleven months after the end of their audit period September 30, 2023. Cause: The entity has not been able to close their books in a timely manner due to the late submission of vendor invoices. At times their closing has conflicted with the auditor’s availability and therefore, the audit was unable to be completed within the nine month period. Effect: The entity was not in compliance with the deadline for the audit report under 2 CFR 200.516 (a). Questioned costs: None Reported Context/Sampling: None Reported Repeat Finding from Prior Year: Yes 2023-001 Recommendation: We recommend that management communicate with their vendors to assure that timely invoices are submitted and that a strict timeline for completion of the audit is adhered to. Views of Responsible Officials: The entity has implemented wording in their vendor contracts that they will not honor invoices that are more than 90 days out.
Criteria: As a condition of receiving federal awards, the awardee organization must comply with filing the required reports timely, specifically, submission of an audit report within nine months after the end of the audit period. Condition: The entity submitted their audit report eleven months after the end of their audit period September 30, 2023. Cause: The entity has not been able to close their books in a timely manner due to the late submission of vendor invoices. At times their closing has conflicted with the auditor’s availability and therefore, the audit was unable to be completed within the nine month period. Effect: The entity was not in compliance with the deadline for the audit report under 2 CFR 200.516 (a). Questioned costs: None Reported Context/Sampling: None Reported Repeat Finding from Prior Year: Yes 2023-001 Recommendation: We recommend that management communicate with their vendors to assure that timely invoices are submitted and that a strict timeline for completion of the audit is adhered to. Views of Responsible Officials: The entity has implemented wording in their vendor contracts that they will not honor invoices that are more than 90 days out.
Criteria: As a condition of receiving federal awards, the awardee organization must comply with filing the required reports timely, specifically, submission of an audit report within nine months after the end of the audit period. Condition: The entity submitted their audit report eleven months after the end of their audit period September 30, 2023. Cause: The entity has not been able to close their books in a timely manner due to the late submission of vendor invoices. At times their closing has conflicted with the auditor’s availability and therefore, the audit was unable to be completed within the nine month period. Effect: The entity was not in compliance with the deadline for the audit report under 2 CFR 200.516 (a). Questioned costs: None Reported Context/Sampling: None Reported Repeat Finding from Prior Year: Yes 2023-001 Recommendation: We recommend that management communicate with their vendors to assure that timely invoices are submitted and that a strict timeline for completion of the audit is adhered to. Views of Responsible Officials: The entity has implemented wording in their vendor contracts that they will not honor invoices that are more than 90 days out.