Notes to SEFA
Title: NOTE 1 - BASIS OF PRESENTATION
Accounting Policies: The accompanying schedule of expenditures of federal awards is presented on the accrual basis of accounting. The information in this schedule is presented in accordance with the requirements of Title 2 U.S. Code of Federal Regulations Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance). Therefore, some amounts presented in this schedule may differ from amounts presented in, or used in the preparation of, the basic financial statements.
De Minimis Rate Used: N
Rate Explanation: The Coalition has elected to not use the 10% de minimis indirect cost rate for its federal programs for the year ended December 31, 2024. The indirect cost rates used on the Coalition's federal program are determined by the relevant federal agency.
The accompanying schedule of expenditures of federal awards is presented on the accrual basis of accounting. The information in this schedule is presented in accordance with the requirements of Title 2 U.S. Code of Federal Regulations Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance). Therefore, some amounts presented in this schedule may differ from amounts presented in, or used in the preparation of, the basic financial statements.
Title: NOTE 2 - CONTINGENCY
Accounting Policies: The accompanying schedule of expenditures of federal awards is presented on the accrual basis of accounting. The information in this schedule is presented in accordance with the requirements of Title 2 U.S. Code of Federal Regulations Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance). Therefore, some amounts presented in this schedule may differ from amounts presented in, or used in the preparation of, the basic financial statements.
De Minimis Rate Used: N
Rate Explanation: The Coalition has elected to not use the 10% de minimis indirect cost rate for its federal programs for the year ended December 31, 2024. The indirect cost rates used on the Coalition's federal program are determined by the relevant federal agency.
Amounts received or receivable from grantor agencies are subject to audit and adjustment by those agencies. Any disallowed claims, including amounts already received, might constitute a liability for the return of those funds. In the opinion of management, all grant expenditures were in compliance with the terms of the grant agreements and applicable federal laws and regulations.
Title: NOTE 3 - INDIRECT COST RATES
Accounting Policies: The accompanying schedule of expenditures of federal awards is presented on the accrual basis of accounting. The information in this schedule is presented in accordance with the requirements of Title 2 U.S. Code of Federal Regulations Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance). Therefore, some amounts presented in this schedule may differ from amounts presented in, or used in the preparation of, the basic financial statements.
De Minimis Rate Used: N
Rate Explanation: The Coalition has elected to not use the 10% de minimis indirect cost rate for its federal programs for the year ended December 31, 2024. The indirect cost rates used on the Coalition's federal program are determined by the relevant federal agency.
The Coalition has elected to not use the 10% de minimis indirect cost rate for its federal programs for the year ended December 31, 2024. The indirect cost rates used on the Coalition's federal program are determined by the relevant federal agency.