Audit 356656

FY End
2024-06-30
Total Expended
$132.56M
Findings
100
Programs
30
Year: 2024 Accepted: 2025-05-20
Auditor: Rsm US LLP

Organization Exclusion Status:

Checking exclusion status...

Findings

ID Ref Severity Repeat Requirement
561008 2024-003 - - L
561009 2024-003 - - L
561010 2024-003 - - L
561011 2024-003 - - L
561012 2024-003 - - L
561013 2024-003 - - L
561014 2024-003 - - L
561015 2024-003 - - L
561016 2024-003 - - L
561017 2024-003 - - L
561018 2024-003 - - L
561019 2024-003 - - L
561020 2024-003 - - L
561021 2024-003 - - L
561022 2024-003 - - L
561023 2024-003 - - L
561024 2024-003 - - L
561025 2024-003 - - L
561026 2024-003 - - L
561027 2024-003 - - L
561028 2024-003 - - L
561029 2024-003 - - L
561030 2024-003 - - L
561031 2024-003 - - L
561032 2024-003 - - L
561033 2024-003 - - L
561034 2024-003 - - L
561035 2024-003 - - L
561036 2024-003 - - L
561037 2024-003 - - L
561038 2024-003 - - L
561039 2024-003 - - L
561040 2024-003 - - L
561041 2024-003 - - L
561042 2024-003 - - L
561043 2024-003 - - L
561044 2024-003 - - L
561045 2024-003 - - L
561046 2024-003 - - L
561047 2024-003 - - L
561048 2024-003 - - L
561049 2024-003 - - L
561050 2024-003 - - L
561051 2024-003 - - L
561052 2024-003 - - L
561053 2024-003 - - L
561054 2024-003 - - L
561055 2024-003 - - L
561056 2024-003 - - L
561057 2024-003 - - L
1137450 2024-003 - - L
1137451 2024-003 - - L
1137452 2024-003 - - L
1137453 2024-003 - - L
1137454 2024-003 - - L
1137455 2024-003 - - L
1137456 2024-003 - - L
1137457 2024-003 - - L
1137458 2024-003 - - L
1137459 2024-003 - - L
1137460 2024-003 - - L
1137461 2024-003 - - L
1137462 2024-003 - - L
1137463 2024-003 - - L
1137464 2024-003 - - L
1137465 2024-003 - - L
1137466 2024-003 - - L
1137467 2024-003 - - L
1137468 2024-003 - - L
1137469 2024-003 - - L
1137470 2024-003 - - L
1137471 2024-003 - - L
1137472 2024-003 - - L
1137473 2024-003 - - L
1137474 2024-003 - - L
1137475 2024-003 - - L
1137476 2024-003 - - L
1137477 2024-003 - - L
1137478 2024-003 - - L
1137479 2024-003 - - L
1137480 2024-003 - - L
1137481 2024-003 - - L
1137482 2024-003 - - L
1137483 2024-003 - - L
1137484 2024-003 - - L
1137485 2024-003 - - L
1137486 2024-003 - - L
1137487 2024-003 - - L
1137488 2024-003 - - L
1137489 2024-003 - - L
1137490 2024-003 - - L
1137491 2024-003 - - L
1137492 2024-003 - - L
1137493 2024-003 - - L
1137494 2024-003 - - L
1137495 2024-003 - - L
1137496 2024-003 - - L
1137497 2024-003 - - L
1137498 2024-003 - - L
1137499 2024-003 - - L

Programs

ALN Program Spent Major Findings
84.425D Education Stabilization Fund $62.22M - 1
10.553 School Breakfast Program $5.54M Yes 1
84.367 Supporting Effective Instruction State Grants (formerly Improving Teacher Quality State Grants) $3.32M - 1
10.582 Fresh Fruit and Vegetable Program $1.08M Yes 1
84.365 English Language Acquisition State Grants $1.07M Yes 1
84.048 Career and Technical Education -- Basic Grants to States $1.05M - 1
84.010 Title I Grants to Local Educational Agencies $998,628 - 1
10.555 National School Lunch Program $968,261 Yes 1
84.060 Indian Education Grants to Local Educational Agencies $569,245 - 1
93.600 Head Start $549,412 - 1
93.575 Child Care and Development Block Grant $489,000 - 1
93.777 State Survey and Certification of Health Care Providers and Suppliers (title Xviii) Medicare $476,764 - 1
93.505 Affordable Care Act (aca) Maternal, Infant, and Early Childhood Home Visiting Program $353,053 - 1
84.334 Gaining Early Awareness and Readiness for Undergraduate Programs $346,151 - 1
84.027X Special Education Grants to States $321,075 - 1
10.579 Child Nutrition Discretionary Grants Limited Availability $302,554 - 1
84.013 Title I State Agency Program for Neglected and Delinquent Children and Youth $174,290 - 1
15.130 Indian Education Assistance to Schools $136,806 - 1
84.126 Rehabilitation Services Vocational Rehabilitation Grants to States $108,219 - 1
32.009 Covid-19: Emergency Connectivity Fund Program $104,599 - 1
84.173 Special Education Preschool Grants $90,153 - 1
10.558 Child and Adult Care Food Program $51,774 - 1
93.778 Medical Assistance Program $41,208 - 1
84.041 Impact Aid $39,384 - 1
84.027 Special Education Grants to States $26,252 - 1
84.371 Comprehensive Literacy Development $16,689 - 1
84.196 Education for Homeless Children and Youth $15,055 - 1
84.425U Education Stabilization Fund $13,598 - 1
93.981 Improving Student Health and Academic Achievement Through Nutrition, Physical Activity and the Management of Chronic Conditions in Schools $8,477 - 1
10.559 Summer Food Service Program for Children $6,823 Yes 1

Contacts

Name Title Type
MWFTLQL8MEY4 Clint Everhart Auditee
4055870252 Tino Robledo Auditor
No contacts on file

Notes to SEFA

Title: Note 1. Basis of Presentation Accounting Policies: Expenditures reported on the Schedule are reported on the accrual basis of accounting. Such expenditures are recognized following the cost principles contained in the Uniform Guidance, wherein certain types of expenditures are not allowable or are limited as to reimbursement. Negative amounts shown on the Schedule, if any, represent adjustments or credits made in the normal course of business to amounts reported as expenditures in prior years. De Minimis Rate Used: N Rate Explanation: The District has elected not to use the 10% de minimis indirect cost rate allowed under the Uniform Guidance The accompanying schedule of expenditures of federal awards (the “Schedule”) includes the federal award activity of the Independent School District No. 89 of Oklahoma County, Oklahoma, also known as the Oklahoma City Public Schools (the District) under programs of the federal government for the year ended June 30, 2024. All federal awards received directly from federal agencies, as well as federal awards passed through other governmental agencies, and expended during the year are included in this Schedule. The information in this Schedule is presented in accordance with the requirements of Title 2 U.S. Code of Federal Regulations Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance). Because the Schedule presents only a selected portion on the operations of the District, it is not intended to and does not present the financial position, changes in net assets, or cash flows of the District.
Title: Note 2. Summary of Significant Accounting Policies Accounting Policies: Expenditures reported on the Schedule are reported on the accrual basis of accounting. Such expenditures are recognized following the cost principles contained in the Uniform Guidance, wherein certain types of expenditures are not allowable or are limited as to reimbursement. Negative amounts shown on the Schedule, if any, represent adjustments or credits made in the normal course of business to amounts reported as expenditures in prior years. De Minimis Rate Used: N Rate Explanation: The District has elected not to use the 10% de minimis indirect cost rate allowed under the Uniform Guidance Expenditures reported on the Schedule are reported on the accrual basis of accounting. Such expenditures are recognized following the cost principles contained in the Uniform Guidance, wherein certain types of expenditures are not allowable or are limited as to reimbursement. Negative amounts shown on the Schedule, if any, represent adjustments or credits made in the normal course of business to amounts reported as expenditures in prior years.
Title: Note 3. Indirect Cost Rate Accounting Policies: Expenditures reported on the Schedule are reported on the accrual basis of accounting. Such expenditures are recognized following the cost principles contained in the Uniform Guidance, wherein certain types of expenditures are not allowable or are limited as to reimbursement. Negative amounts shown on the Schedule, if any, represent adjustments or credits made in the normal course of business to amounts reported as expenditures in prior years. De Minimis Rate Used: N Rate Explanation: The District has elected not to use the 10% de minimis indirect cost rate allowed under the Uniform Guidance The District has elected not to use the 10% de minimis indirect cost rate allowed under the Uniform Guidance.
Title: Note 4. Noncash Assistance Accounting Policies: Expenditures reported on the Schedule are reported on the accrual basis of accounting. Such expenditures are recognized following the cost principles contained in the Uniform Guidance, wherein certain types of expenditures are not allowable or are limited as to reimbursement. Negative amounts shown on the Schedule, if any, represent adjustments or credits made in the normal course of business to amounts reported as expenditures in prior years. De Minimis Rate Used: N Rate Explanation: The District has elected not to use the 10% de minimis indirect cost rate allowed under the Uniform Guidance The schedule includes federal awards in the form of noncash assistance (commodities) received during the year in the amount of $ 1,768,936 related to USDA Commodities grants (CFDA Number 10.555) provided by the U.S. Department of Agriculture and passed through the Oklahoma Department of Human Services.

Finding Details

Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.
Finding 2024-003 Noncompliance All Assistance Listing Numbers and Federal Agencies included on the schedule of expenditures of federal awards for year ended June 30, 2024 Federal Clearinghouse Annual Submission Finding: The Single Audit package was not submitted to the Federal Clearinghouse within the required time period. Criteria: Uniform Guidance 2 CFR 200.512(a) requires that organization’s audit must be completed and the data collection form and reporting package should be submitted within the earlier of 30 days after receipt of the auditor’s report or nine months after the end of the audit period. Condition: The Single Audit package for the District’s year ended June 30, 2024 should have been submitted to the Federal Audit Clearinghouse by March 31, 2025. Cause: The audit was not completed by March 31, 2025 due to delays in the overall audit process caused by a shortage of resources. Effect or potential effect: Potential suspension of funding provided by federal agencies. Questioned costs: None Context: The June 30, 2024 Single Audit package. Identification as a repeat finding, if applicable: No Recommendation: We recommend the District file the reporting package timely to the Federal Audit Clearinghouse. Views of responsible officials: Management agrees with this finding. Management acknowledges the finding. The delay in submitting the Single Audit package was primarily due to the external auditor’s resource constraints, which impacted the timely completion of the audit. Management views this as an isolated event and assures that it will not occur again. To prevent future delays, the District will coordinate closely with the external auditors to ensure adequate resources are available and will monitor audit timelines to ensure timely submission of future audit packages.