Audit 3557

FY End
2023-06-30
Total Expended
$22.10M
Findings
12
Programs
10
Organization: Southern Nazarene University (OK)
Year: 2023 Accepted: 2023-11-17
Auditor: Hogantaylor LLP

Organization Exclusion Status:

Checking exclusion status...

Findings

ID Ref Severity Repeat Requirement
2026 2023-001 - - N
2027 2023-001 - - N
2028 2023-001 - - N
2029 2023-001 - - N
2030 2023-001 - - N
2031 2023-001 - - N
578468 2023-001 - - N
578469 2023-001 - - N
578470 2023-001 - - N
578471 2023-001 - - N
578472 2023-001 - - N
578473 2023-001 - - N

Programs

ALN Program Spent Major Findings
84.268 Federal Direct Student Loans $16.14M Yes 1
84.063 Federal Pell Grant Program $3.47M Yes 1
84.038 Federal Perkins Loan Program $970,798 Yes 1
84.031 Higher Education_institutional Aid $413,535 - 0
84.042 Trio_student Support Services $251,663 - 0
84.217 Trio_mcnair Post-Baccalaureate Achievement $242,093 - 0
84.379 Teacher Education Assistance for College and Higher Education Grants (teach Grants) $227,263 Yes 1
84.033 Federal Work-Study Program $201,647 Yes 1
84.007 Federal Supplemental Educational Opportunity Grants $162,716 Yes 1
43.008 Education $3,736 - 0

Contacts

Name Title Type
FMC7DS3QGZN4 Phil White Auditee
4058208522 Richard Wright Auditor
No contacts on file

Notes to SEFA

Title: Note 1 – Basis of Presentation Accounting Policies: Expenditures reported on the Schedule are reported on the accrual basis of accounting. Such expenditures are recognized following the cost principles contained in the Uniform Guidance, wherein certain types of expenditures are not allowable or are limited as to reimbursement. The Company has elected not to use the 10% de minimis indirect cost rate as allowed under the Uniform Guidance. De Minimis Rate Used: N Rate Explanation: The Company has elected not to use the 10% de minimis indirect cost rate as allowed under the Uniform Guidance The accompanying schedule of expenditures of federal awards (the Schedule) includes the federal awards activity of the University under programs of the federal government for the year ended June 30, 2023. The information in this Schedule is presented in accordance with the requirements of Title 2 U.S. Code of Federal Regulations Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance). Because the Schedule presents only a selected portion of the operations of the University, it is not intended to and does not present the financial position, changes in net assets, or cash flows of the Company.
Title: Note 2 – Summary of Significant Accounting Policies Accounting Policies: Expenditures reported on the Schedule are reported on the accrual basis of accounting. Such expenditures are recognized following the cost principles contained in the Uniform Guidance, wherein certain types of expenditures are not allowable or are limited as to reimbursement. The Company has elected not to use the 10% de minimis indirect cost rate as allowed under the Uniform Guidance. De Minimis Rate Used: N Rate Explanation: The Company has elected not to use the 10% de minimis indirect cost rate as allowed under the Uniform Guidance Expenditures reported on the Schedule are reported on the accrual basis of accounting. Such expenditures are recognized following the cost principles contained in the Uniform Guidance, wherein certain types of expenditures are not allowable or are limited as to reimbursement. The Company has elected not to use the 10% de minimis indirect cost rate as allowed under the Uniform Guidance.
Title: Note 3 – Federal Perkins Loan Program Accounting Policies: Expenditures reported on the Schedule are reported on the accrual basis of accounting. Such expenditures are recognized following the cost principles contained in the Uniform Guidance, wherein certain types of expenditures are not allowable or are limited as to reimbursement. The Company has elected not to use the 10% de minimis indirect cost rate as allowed under the Uniform Guidance. De Minimis Rate Used: N Rate Explanation: The Company has elected not to use the 10% de minimis indirect cost rate as allowed under the Uniform Guidance The University administers the Federal Perkins Loan Program. There were no new loans awarded during the year ended June 30, 2023, and no administrative cost allowances. The loan balance outstanding at June 30, 2023, was $745,109, net of an allowance for doubtful accounts of $475,310. No further loan disbursements can be made due to regulation changes to the program. Schools have the option of continuing to collect on outstanding balances or can voluntarily liquidate the program. The University has no current plans to initiate the liquidation process.
Title: Note 4 – Subrecipients Accounting Policies: Expenditures reported on the Schedule are reported on the accrual basis of accounting. Such expenditures are recognized following the cost principles contained in the Uniform Guidance, wherein certain types of expenditures are not allowable or are limited as to reimbursement. The Company has elected not to use the 10% de minimis indirect cost rate as allowed under the Uniform Guidance. De Minimis Rate Used: N Rate Explanation: The Company has elected not to use the 10% de minimis indirect cost rate as allowed under the Uniform Guidance The University provided no federal awards to subrecipients.

Finding Details

Management's response is reported in "Management's Views and Corrective Action Plan" at the end of this report.
Management's response is reported in "Management's Views and Corrective Action Plan" at the end of this report.
Management's response is reported in "Management's Views and Corrective Action Plan" at the end of this report.
Management's response is reported in "Management's Views and Corrective Action Plan" at the end of this report.
Management's response is reported in "Management's Views and Corrective Action Plan" at the end of this report.
Management's response is reported in "Management's Views and Corrective Action Plan" at the end of this report.
Management's response is reported in "Management's Views and Corrective Action Plan" at the end of this report.
Management's response is reported in "Management's Views and Corrective Action Plan" at the end of this report.
Management's response is reported in "Management's Views and Corrective Action Plan" at the end of this report.
Management's response is reported in "Management's Views and Corrective Action Plan" at the end of this report.
Management's response is reported in "Management's Views and Corrective Action Plan" at the end of this report.
Management's response is reported in "Management's Views and Corrective Action Plan" at the end of this report.