Audit 354825

FY End
2024-12-31
Total Expended
$1.32M
Findings
0
Programs
1
Organization: Valley Crossroads, Inc. (UT)
Year: 2024 Accepted: 2025-04-28
Auditor: Tanner LLC

Organization Exclusion Status:

Checking exclusion status...

Findings

No findings recorded

Programs

ALN Program Spent Major Findings
14.181 Supportive Housing for Persons with Disabilities $96,183 Yes 0

Contacts

Name Title Type
K5J6URAAPTA5 Spencer Seaquist Auditee
8017225164 Douglas J Hansen Auditor
No contacts on file

Notes to SEFA

Title: 1 Accounting Policies: The accompanying schedule of expenditures of federal awards (the Schedule) includes the federal grant activity of Valley Crossroads, Inc. under a program of the federal government for the year ended December 31, 2024. The information in this Schedule is presented in accordance with the requirements of the Code of Federal Regulations (CFR) Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance). Because the Schedule presents only a selected portion of the operations of the Project, it is not intended to and does not present the financial position, changes in net assets, or cash flows of the Project. The Project has not elected to use the 10 percent de minimus indirect cost rate allowed under the Uniform Guidance. De Minimis Rate Used: N Rate Explanation: The Corporation has elected not to use the 10% de minimis indirect cost rate as allowed under the Uniform Guidance. The accompanying schedule of expenditures of federal awards (the Schedule) includes the federal grant activity of Valley Crossroads, Inc. under a program of the federal government for the year ended December 31, 2024. The information in this Schedule is presented in accordance with the requirements of the Code of Federal Regulations (CFR) Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance). Because the Schedule presents only a selected portion of the operations of the Project, it is not intended to and does not present the financial position, changes in net assets, or cash flows of the Project. The Project has not elected to use the 10 percent de minimus indirect cost rate allowed under the Uniform Guidance.
Title: 2 Accounting Policies: The accompanying schedule of expenditures of federal awards (the Schedule) includes the federal grant activity of Valley Crossroads, Inc. under a program of the federal government for the year ended December 31, 2024. The information in this Schedule is presented in accordance with the requirements of the Code of Federal Regulations (CFR) Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance). Because the Schedule presents only a selected portion of the operations of the Project, it is not intended to and does not present the financial position, changes in net assets, or cash flows of the Project. The Project has not elected to use the 10 percent de minimus indirect cost rate allowed under the Uniform Guidance. De Minimis Rate Used: N Rate Explanation: The Corporation has elected not to use the 10% de minimis indirect cost rate as allowed under the Uniform Guidance. Expenditures reported on the Schedule are reported on the accrual basis of accounting. Such expenditures are recognized following the cost principles contained in the Uniform Guidance, wherein certain types of expenditures are not allowable or are limited as to reimbursement.
Title: 3 Accounting Policies: The accompanying schedule of expenditures of federal awards (the Schedule) includes the federal grant activity of Valley Crossroads, Inc. under a program of the federal government for the year ended December 31, 2024. The information in this Schedule is presented in accordance with the requirements of the Code of Federal Regulations (CFR) Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance). Because the Schedule presents only a selected portion of the operations of the Project, it is not intended to and does not present the financial position, changes in net assets, or cash flows of the Project. The Project has not elected to use the 10 percent de minimus indirect cost rate allowed under the Uniform Guidance. De Minimis Rate Used: N Rate Explanation: The Corporation has elected not to use the 10% de minimis indirect cost rate as allowed under the Uniform Guidance. In a prior year, the Project’s construction costs were primarily financed through a Section 811 Capital Advance from HUD. The capital advance mortgage note does not bear interest, nor require repayment, as long as the housing remains available for very low-income persons with disabilities in accordance with Section 811 of the Affordable Housing Act of 1990 and the Regulatory agreement between Valley Crossroads, Inc. and HUD. The Project received no additional advances during 2024.