Audit 344097

FY End
2023-09-30
Total Expended
$2.54M
Findings
14
Programs
4
Year: 2023 Accepted: 2025-02-27

Organization Exclusion Status:

Checking exclusion status...

Findings

ID Ref Severity Repeat Requirement
524652 2023-001 - - P
524653 2023-001 - - P
524654 2023-001 - - P
524655 2023-001 - - P
524656 2023-001 - - P
524657 2023-001 - - P
524658 2023-001 - - P
1101094 2023-001 - - P
1101095 2023-001 - - P
1101096 2023-001 - - P
1101097 2023-001 - - P
1101098 2023-001 - - P
1101099 2023-001 - - P
1101100 2023-001 - - P

Programs

ALN Program Spent Major Findings
93.273 Alcohol Research Programs $255,648 Yes 1
93.361 Nursing Research $176,806 Yes 1
93.242 Mental Health Research Grants $171,564 Yes 1
93.865 Child Health and Human Development Extramural Research $100,790 Yes 1

Contacts

Name Title Type
HB8HEMLHJUJ4 Michele Ybarra Auditee
8773026858 Jeanne Mann, CPA Auditor
No contacts on file

Notes to SEFA

Title: BASIS OF PRESENTATION Accounting Policies: The accompanying schedule of expenditures of federal awards (the Schedule) includes Federal grant activity of CiPHR and is presented on the modified accrual basis of accounting. The information in this schedule is presented in accordance with the requirements of Title 2 U.S. Code of Federal Regulations Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance). Therefore, some amounts presented in this schedule may differ from amounts presented in, or used in the preparation of, the financial statements. De Minimis Rate Used: N Rate Explanation: The organization is using their approved indirect cost rate The accompanying schedule of expenditures of federal awards (the Schedule) includes Federal grant activity of CiPHR and is presented on the modified accrual basis of accounting. The information in this schedule is presented in accordance with the requirements of Title 2 U.S. Code of Federal Regulations Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance). Therefore, some amounts presented in this schedule may differ from amounts presented in, or used in the preparation of, the financial statements.
Title: INDIRECT COST RATE Accounting Policies: The accompanying schedule of expenditures of federal awards (the Schedule) includes Federal grant activity of CiPHR and is presented on the modified accrual basis of accounting. The information in this schedule is presented in accordance with the requirements of Title 2 U.S. Code of Federal Regulations Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance). Therefore, some amounts presented in this schedule may differ from amounts presented in, or used in the preparation of, the financial statements. De Minimis Rate Used: N Rate Explanation: The organization is using their approved indirect cost rate CiPHR has not elected to use the 10% de minimus costs rate.

Finding Details

Criteria: As a condition of receiving federal awards, the awardee organization must comply with filing the required reports timely, specifically, submission of an audit report within nine months after the end of the audit period. Condition: The entity submitted their audit report eleven months after the end of their audit period September 30, 2022. Cause: The entity has not been able to close their books in a timely manner due to the late submission of vendor invoices. At times their closing has conflicted with the auditor’s availability and therefore, the audit was unable to be completed within the nine month period. Effect: The entity was not in compliance with the deadline for the audit report under 2 CFR 200.516 (a). Questioned costs: None Reported Context/Sampling: None Reported Repeat Finding from Prior Year: No Recommendation: We recommend that management communicate with their vendors to assure that timely invoices are submitted and that a strict timeline for completion of the audit is adhered to. Views of Responsible Officials: The entity has implemented wording in their vendor contracts that they will not honor invoices that are more than 90 days out.
Criteria: As a condition of receiving federal awards, the awardee organization must comply with filing the required reports timely, specifically, submission of an audit report within nine months after the end of the audit period. Condition: The entity submitted their audit report eleven months after the end of their audit period September 30, 2022. Cause: The entity has not been able to close their books in a timely manner due to the late submission of vendor invoices. At times their closing has conflicted with the auditor’s availability and therefore, the audit was unable to be completed within the nine month period. Effect: The entity was not in compliance with the deadline for the audit report under 2 CFR 200.516 (a). Questioned costs: None Reported Context/Sampling: None Reported Repeat Finding from Prior Year: No Recommendation: We recommend that management communicate with their vendors to assure that timely invoices are submitted and that a strict timeline for completion of the audit is adhered to. Views of Responsible Officials: The entity has implemented wording in their vendor contracts that they will not honor invoices that are more than 90 days out.
Criteria: As a condition of receiving federal awards, the awardee organization must comply with filing the required reports timely, specifically, submission of an audit report within nine months after the end of the audit period. Condition: The entity submitted their audit report eleven months after the end of their audit period September 30, 2022. Cause: The entity has not been able to close their books in a timely manner due to the late submission of vendor invoices. At times their closing has conflicted with the auditor’s availability and therefore, the audit was unable to be completed within the nine month period. Effect: The entity was not in compliance with the deadline for the audit report under 2 CFR 200.516 (a). Questioned costs: None Reported Context/Sampling: None Reported Repeat Finding from Prior Year: No Recommendation: We recommend that management communicate with their vendors to assure that timely invoices are submitted and that a strict timeline for completion of the audit is adhered to. Views of Responsible Officials: The entity has implemented wording in their vendor contracts that they will not honor invoices that are more than 90 days out.
Criteria: As a condition of receiving federal awards, the awardee organization must comply with filing the required reports timely, specifically, submission of an audit report within nine months after the end of the audit period. Condition: The entity submitted their audit report eleven months after the end of their audit period September 30, 2022. Cause: The entity has not been able to close their books in a timely manner due to the late submission of vendor invoices. At times their closing has conflicted with the auditor’s availability and therefore, the audit was unable to be completed within the nine month period. Effect: The entity was not in compliance with the deadline for the audit report under 2 CFR 200.516 (a). Questioned costs: None Reported Context/Sampling: None Reported Repeat Finding from Prior Year: No Recommendation: We recommend that management communicate with their vendors to assure that timely invoices are submitted and that a strict timeline for completion of the audit is adhered to. Views of Responsible Officials: The entity has implemented wording in their vendor contracts that they will not honor invoices that are more than 90 days out.
Criteria: As a condition of receiving federal awards, the awardee organization must comply with filing the required reports timely, specifically, submission of an audit report within nine months after the end of the audit period. Condition: The entity submitted their audit report eleven months after the end of their audit period September 30, 2022. Cause: The entity has not been able to close their books in a timely manner due to the late submission of vendor invoices. At times their closing has conflicted with the auditor’s availability and therefore, the audit was unable to be completed within the nine month period. Effect: The entity was not in compliance with the deadline for the audit report under 2 CFR 200.516 (a). Questioned costs: None Reported Context/Sampling: None Reported Repeat Finding from Prior Year: No Recommendation: We recommend that management communicate with their vendors to assure that timely invoices are submitted and that a strict timeline for completion of the audit is adhered to. Views of Responsible Officials: The entity has implemented wording in their vendor contracts that they will not honor invoices that are more than 90 days out.
Criteria: As a condition of receiving federal awards, the awardee organization must comply with filing the required reports timely, specifically, submission of an audit report within nine months after the end of the audit period. Condition: The entity submitted their audit report eleven months after the end of their audit period September 30, 2022. Cause: The entity has not been able to close their books in a timely manner due to the late submission of vendor invoices. At times their closing has conflicted with the auditor’s availability and therefore, the audit was unable to be completed within the nine month period. Effect: The entity was not in compliance with the deadline for the audit report under 2 CFR 200.516 (a). Questioned costs: None Reported Context/Sampling: None Reported Repeat Finding from Prior Year: No Recommendation: We recommend that management communicate with their vendors to assure that timely invoices are submitted and that a strict timeline for completion of the audit is adhered to. Views of Responsible Officials: The entity has implemented wording in their vendor contracts that they will not honor invoices that are more than 90 days out.
Criteria: As a condition of receiving federal awards, the awardee organization must comply with filing the required reports timely, specifically, submission of an audit report within nine months after the end of the audit period. Condition: The entity submitted their audit report eleven months after the end of their audit period September 30, 2022. Cause: The entity has not been able to close their books in a timely manner due to the late submission of vendor invoices. At times their closing has conflicted with the auditor’s availability and therefore, the audit was unable to be completed within the nine month period. Effect: The entity was not in compliance with the deadline for the audit report under 2 CFR 200.516 (a). Questioned costs: None Reported Context/Sampling: None Reported Repeat Finding from Prior Year: No Recommendation: We recommend that management communicate with their vendors to assure that timely invoices are submitted and that a strict timeline for completion of the audit is adhered to. Views of Responsible Officials: The entity has implemented wording in their vendor contracts that they will not honor invoices that are more than 90 days out.
Criteria: As a condition of receiving federal awards, the awardee organization must comply with filing the required reports timely, specifically, submission of an audit report within nine months after the end of the audit period. Condition: The entity submitted their audit report eleven months after the end of their audit period September 30, 2022. Cause: The entity has not been able to close their books in a timely manner due to the late submission of vendor invoices. At times their closing has conflicted with the auditor’s availability and therefore, the audit was unable to be completed within the nine month period. Effect: The entity was not in compliance with the deadline for the audit report under 2 CFR 200.516 (a). Questioned costs: None Reported Context/Sampling: None Reported Repeat Finding from Prior Year: No Recommendation: We recommend that management communicate with their vendors to assure that timely invoices are submitted and that a strict timeline for completion of the audit is adhered to. Views of Responsible Officials: The entity has implemented wording in their vendor contracts that they will not honor invoices that are more than 90 days out.
Criteria: As a condition of receiving federal awards, the awardee organization must comply with filing the required reports timely, specifically, submission of an audit report within nine months after the end of the audit period. Condition: The entity submitted their audit report eleven months after the end of their audit period September 30, 2022. Cause: The entity has not been able to close their books in a timely manner due to the late submission of vendor invoices. At times their closing has conflicted with the auditor’s availability and therefore, the audit was unable to be completed within the nine month period. Effect: The entity was not in compliance with the deadline for the audit report under 2 CFR 200.516 (a). Questioned costs: None Reported Context/Sampling: None Reported Repeat Finding from Prior Year: No Recommendation: We recommend that management communicate with their vendors to assure that timely invoices are submitted and that a strict timeline for completion of the audit is adhered to. Views of Responsible Officials: The entity has implemented wording in their vendor contracts that they will not honor invoices that are more than 90 days out.
Criteria: As a condition of receiving federal awards, the awardee organization must comply with filing the required reports timely, specifically, submission of an audit report within nine months after the end of the audit period. Condition: The entity submitted their audit report eleven months after the end of their audit period September 30, 2022. Cause: The entity has not been able to close their books in a timely manner due to the late submission of vendor invoices. At times their closing has conflicted with the auditor’s availability and therefore, the audit was unable to be completed within the nine month period. Effect: The entity was not in compliance with the deadline for the audit report under 2 CFR 200.516 (a). Questioned costs: None Reported Context/Sampling: None Reported Repeat Finding from Prior Year: No Recommendation: We recommend that management communicate with their vendors to assure that timely invoices are submitted and that a strict timeline for completion of the audit is adhered to. Views of Responsible Officials: The entity has implemented wording in their vendor contracts that they will not honor invoices that are more than 90 days out.
Criteria: As a condition of receiving federal awards, the awardee organization must comply with filing the required reports timely, specifically, submission of an audit report within nine months after the end of the audit period. Condition: The entity submitted their audit report eleven months after the end of their audit period September 30, 2022. Cause: The entity has not been able to close their books in a timely manner due to the late submission of vendor invoices. At times their closing has conflicted with the auditor’s availability and therefore, the audit was unable to be completed within the nine month period. Effect: The entity was not in compliance with the deadline for the audit report under 2 CFR 200.516 (a). Questioned costs: None Reported Context/Sampling: None Reported Repeat Finding from Prior Year: No Recommendation: We recommend that management communicate with their vendors to assure that timely invoices are submitted and that a strict timeline for completion of the audit is adhered to. Views of Responsible Officials: The entity has implemented wording in their vendor contracts that they will not honor invoices that are more than 90 days out.
Criteria: As a condition of receiving federal awards, the awardee organization must comply with filing the required reports timely, specifically, submission of an audit report within nine months after the end of the audit period. Condition: The entity submitted their audit report eleven months after the end of their audit period September 30, 2022. Cause: The entity has not been able to close their books in a timely manner due to the late submission of vendor invoices. At times their closing has conflicted with the auditor’s availability and therefore, the audit was unable to be completed within the nine month period. Effect: The entity was not in compliance with the deadline for the audit report under 2 CFR 200.516 (a). Questioned costs: None Reported Context/Sampling: None Reported Repeat Finding from Prior Year: No Recommendation: We recommend that management communicate with their vendors to assure that timely invoices are submitted and that a strict timeline for completion of the audit is adhered to. Views of Responsible Officials: The entity has implemented wording in their vendor contracts that they will not honor invoices that are more than 90 days out.
Criteria: As a condition of receiving federal awards, the awardee organization must comply with filing the required reports timely, specifically, submission of an audit report within nine months after the end of the audit period. Condition: The entity submitted their audit report eleven months after the end of their audit period September 30, 2022. Cause: The entity has not been able to close their books in a timely manner due to the late submission of vendor invoices. At times their closing has conflicted with the auditor’s availability and therefore, the audit was unable to be completed within the nine month period. Effect: The entity was not in compliance with the deadline for the audit report under 2 CFR 200.516 (a). Questioned costs: None Reported Context/Sampling: None Reported Repeat Finding from Prior Year: No Recommendation: We recommend that management communicate with their vendors to assure that timely invoices are submitted and that a strict timeline for completion of the audit is adhered to. Views of Responsible Officials: The entity has implemented wording in their vendor contracts that they will not honor invoices that are more than 90 days out.
Criteria: As a condition of receiving federal awards, the awardee organization must comply with filing the required reports timely, specifically, submission of an audit report within nine months after the end of the audit period. Condition: The entity submitted their audit report eleven months after the end of their audit period September 30, 2022. Cause: The entity has not been able to close their books in a timely manner due to the late submission of vendor invoices. At times their closing has conflicted with the auditor’s availability and therefore, the audit was unable to be completed within the nine month period. Effect: The entity was not in compliance with the deadline for the audit report under 2 CFR 200.516 (a). Questioned costs: None Reported Context/Sampling: None Reported Repeat Finding from Prior Year: No Recommendation: We recommend that management communicate with their vendors to assure that timely invoices are submitted and that a strict timeline for completion of the audit is adhered to. Views of Responsible Officials: The entity has implemented wording in their vendor contracts that they will not honor invoices that are more than 90 days out.